Specialization:
Production Engineering and Logistics
Report number: 2013.TEL.7746
Title:
Redesigning inspection process
upon repairs at Tronox Pigments
B.V.
Delft University of Technology Department Maritime and Transport Technology Mekelweg 2 2628 CD Delft the Netherlands Phone +31 (0)15-2782889 Fax +31 (0)15-2781397 www.mtt.tudelft.nl
This report consists of ## pages and # appendices. It may only be reproduced literally and as a whole. For commercial purposes only with written authorization of Delft University of Technology. Requests for consult are only taken into consideration under the condition that the applicant denies all legal rights on liabilities concerning the contents of the advice.
Specialization:
Production Engineering and Logistics
Report number: 2013.TEL.7746
Title:
Redesigning inspection process
upon repairs at Tronox Pigments
B.V.
Author:
E.P. van Os
Title (in Dutch) Herontwerp van het inspectie en reparatieproces bij Tronox Pigments B.V.
Assignment: Masters thesis
Confidential: yes (until March 01, 2018) Initiator (university): prof.dr.ir. G. Lodewijks
Initiator (company): P. Kats MSc (Tronox Pigments BV) Supervisor: dr.ir. H.P.M. Veeke
Delft University of Technology Department of Marine and Transport Technology Mekelweg 2 2628 CD Delft the Netherlands Phone +31 (0)15-2782889 Fax +31 (0)15-2781397 www.mtt.tudelft.nl
Student: E.P. van Os BSc Assignment type: Master thesis
Supervisor (TUD): Dr.ir. H.P.M. Veeke Creditpoints (EC): 35 Supervisor (Tronox
Pigments)
P. Kats MSc. Specialization: PEL
Report number: 2013.TL.7746 Confidential: Yes
until March 01, 2018
Subject: Redesigning inspection process upon repairs at Tronox Pigments B.V. I Introduction
Tronox Pigments B.V., located in Botlek, the Netherlands, is a producer of titan dioxide (TiO2)
pigment. The plant consists of a large collection of static pressure equipment (e.g. vessels and boilers) and piping, subject to (statutory) inspections upon (temporary) repair or modification. Test and inspection plans need to be drawn up before a (temporary) repair or modification is conducted. These plans indicate how a (temporary) repair or modification is to be conducted and which inspections need to happen during or after repair or modification. Test and inspection plans need to be obeyed,
returned after completion and reviewed. In specific cases an external supervisor is to be involved. Furthermore, due to the presence of large amounts of chemicals such as chlorine, the factory is subject to legislation demanding a controlled execution of all operations, including maintenance and inspections.
II Problem statement
An investigation of the inspections concerning (temporary) repairs revealed a situation incompliant with the prevalent legislation and compromising safety:
• The control system governing the inspection fails. Test and inspection plans remain unreturned and therefore unreviewed.
• The involvement of the external supervisor is not executed according to law, specifically the supervision is executed in hindsight
Ad1. Reasons are identified to be the lack of a measurement and control system, lack of intrinsic interest combined with lack of (enforced) incentives.
Ad 2. Reasons are identified to be the pressure to minimize downtime, combined with an external supervisor allowing the situation to pertain.
Delft University of Technology Department of Marine and Transport Technology Mekelweg 2 2628 CD Delft the Netherlands Phone +31 (0)15-2782889 Fax +31 (0)15-2781397 www.mtt.tudelft.nl
III Assignment description
Redesign processes pertaining to test and inspections concerning (temporary) repairs and modifications.
IV Execution
• Identify all functional and legal requirements of the repair- and inspection process • Establish the necessary functions present in the process
• Establish a control system of said process
• Define the roles and responsibilities of actors in the process execution and control • Identify the means (tools) to be used
• Quantify the cost and benefits inflicted by the redesigned process
• Motivate how the redesigned process will be adhered to in practice, and thus will meet requirements and solve deficiencies identified earlier, specifically with respect to legal compliance and safety
• Study relevant literature
A detailed implementation plan is not part of the execution.
The report should comply with the guidelines of the section. Details can be found on the website.
Supervisor
Professor
Table of Contents
1. Introduction ... 1
1.1
Tronox ... 1
1.2
Titanium dioxide TiO
2... 1
1.3
TiO
2production at Tronox Botlek ... 1
1.4
Safety and environment ... 2
1.5
Legislation and supervision ... 2
1.5.1
Legislation and safety... 3
1.5.2
Supervision ... 4
1.6
Repair and inspection ... 5
1.7
Problem statement and initial research question ... 7
2. Current inspection regime at Tronox Botlek ... 8
2.1
Safety control system: KPMS ... 8
2.2
Software system ... 9
2.3
Equipment ... 9
2.3.1
Piping ... 9
2.3.2
Equipment ... 9
2.3.3
Statutory inspection regime vs. duty of care ... 10
2.4
Summary of statutory inspection regime ... 10
2.4.1
Inspection upon first commissioning of new equipment ... 11
2.4.2
Periodic Inspections ... 11
2.4.3
Inspections upon repair or modification ... 11
3. Analysis of repair and inspection process... 12
3.1
Introduction ... 12
3.2
Operating instruction ... 13
3.3
General observations on KEs ... 14
3.3.1
Large or small operation ... 14
3.3.2
Timescale ... 14
3.3.3
Work order ... 14
3.3.4
Hold points and witness points ... 15
3.3.6
Quality norms ... 15
3.3.7
Paper form ... 15
3.4
Systemic representation of the KE process... 16
3.4.1
Control system ... 18
3.4.2
Commissioning ... 18
3.5
Quantitative analysis of KE process ... 18
3.6
AKI involvement ... 21
3.7
Relation between deficiencies and safety ... 22
3.7.1
Compromise to safety due to unreturned KEs ... 22
3.7.2
HP registration ... 23
3.7.3
Safety compromise due to AKI involvement in hindsight ... 24
3.8
Incompliance due to deficiencies ... 24
3.9
Causes of deficiencies ... 25
3.9.1
Cause: KEs are not returned for review ... 25
3.9.2
Cause: AKI involvement is executed in hindsight ... 25
3.9.3
Cause: Registration of hold point execution is lacking ... 25
3.10
Conclusion ... 26
3.11 Supplementary deficiencies ... 26
4. Temporary repairs ... 27
4.1
Introduction ... 27
4.2
Procedure ... 27
4.3
General observations on TReps ... 29
4.3.1
Large or small operation ... 29
4.3.2
Timescale ... 29
4.3.3
Emergency repairs ... 29
4.3.4
Equipment governed ... 29
4.3.5
KE ... 29
4.4
Systemic representation of TRep process ... 29
4.4.1
Control system ... 31
4.4.2
Commissioning ... 31
4.5
Quantitative analysis of TRep process ... 31
4.6
Inspectorate and AKI involvement ... 33
4.7.1
TRep forms remain unreturned ... 34
4.7.2
Not involving inspectorate or AKI ... 35
4.7.3
Extension ... 35
4.8
Incompliance due to deficiencies ... 36
4.9
Causes of deficiencies ... 36
4.9.1
Causes: Unreturned TRep forms ... 36
4.9.2
Causes: Inspectorate/AKI involvement in hindsight ... 36
4.10
Interrelation KE and TReps ... 37
4.10.1 Determining the workload for the inspectorate and AKI ... 37
4.10.2 Historical data analysis ... 39
4.11 Conclusion ... 39
5. Final research question ... 40
6. User inspectorate IVG ... 42
6.1
Cost and yields ... 42
6.2
Flexibility ... 45
6.3
Periodic inspections ... 45
6.4
Safety... 46
6.5
Gap analysis ... 46
6.6
Decision ... 46
7. Redesign of repair and inspection process ... 47
7.1
Introduction ... 47
7.1.1
Research question ... 47
7.1.2
System boundary ... 48
7.1.3
Method ... 49
7.1.4
Other (Tronox) plants ... 50
7.2
Requirements ... 51
7.3
Functional design of repair and inspection process ... 52
7.3.1
Establishing contents and structure of functional design ... 52
7.3.2
Sequential dependencies ... 53
7.3.3
Continuity of process ... 56
7.3.4
Conclusion functional design ... 57
7.4
Proposal control design ... 58
7.4.2
Control design ... 59
7.4.3
Conclusion on control system ... 60
7.4.4
Scenarios ... 61
7.5
Proposal practical implementation ... 64
7.5.1
Functional streams ... 65
7.5.2
Practical details on control system ... 67
7.5.3
Procedure ... 68
7.5.4
AKI involvement ... 68
7.5.5
Repairs and modifications not inspected by IVG ... 68
7.5.6
Intervention and sanctioning ... 69
7.6
Incorporating temporary repairs ... 70
7.6.1
Integrating KE and TReps ... 70
7.6.2
Temporary repair on equipment on VL53.003 ... 70
7.6.3
Temporary repairs on equipment outside inspection regime ... 71
7.6.4
Emergency repair ... 71
7.7
Theory of system behavior ... 72
7.7.1
Theory of violations ... 72
7.7.2
Theory of IT use and acceptance ... 73
7.7.3
Parallels in compliance theory and theory on use of IT ... 75
7.8
Transposing theory on redesign ... 77
7.8.1
Current incompliance at Tronox ... 78
7.8.2
Culture ... 78
7.8.3
System behavior of redesign... 80
7.9
Conclusion on redesign... 87
7.9.1
Meeting requirements ... 87
7.9.2
Adherence to theory on compliance ... 87
7.9.3
Extant risks ... 88
8. Conclusion... 91
References ... 94
Appendix A – Research paper ... 97
APPENDIX B - Tronox titanium dioxide production ... 104
1. Tronox ... 104
1.2
Locations ... 105
1.2.1
Former locations ... 105
1.2.2
Current operations ... 105
1.3
Titanium dioxide TiO
2... 107
1.4
TiO
2Production in detail ... 108
1.5
TiO
2Production at Tronox Botlek ... 110
1.5.1
Input ... 110
1.5.2
Throughput ... 111
1.5.3
Output ... 111
1.5.4
Capacity ... 111
1.6
Operations at Tronox Botlek ... 113
1.6.1
General ... 113
1.6.2
Production ... 114
1.6.3
Maintenance ... 114
1.6.4
Plant stops ... 115
1.6.5
Project engineering ... 115
1.6.6
Maintenance engineering ... 115
1.6.7
Inspection ... 115
APPENDIX C - Study on Legislation ... 117
1. Legal requirements on safety ... 117
1.1
Permit ... 118
1.2
Wabo ... 118
1.3
BRZO ... 118
1.3.1
Safety Control system VBS ... 121
1.3.2
BRZO supervision ... 122
1.4
Additional legislation ... 137
1.4.1
BEVI ... 137
1.4.2
Fire brigade ... 137
1.5
Future developments on safety, supervision and legislation ... 137
1.5.1
Incidents... 138
1.5.2
Media coverage and political reaction ... 139
1.5.3
Problems with supervision ... 142
1.6
Compliance and safety ... 149
2. Law governing the use of pressurized equipment ... 152
2.1
History of pressurized equipment and legislation ... 152
2.2
Current law regarding pressure equipment ... 153
2.2.1
Construction of pressure equipment ... 153
2.2.2
Operation phase ... 157
2.3
Inspections during lifetime of equipment ... 160
2.3.1
Assembly ... 161
2.3.2
Putting into use (commissioning) ... 161
2.3.3
Operation phase ... 161
2.4
Statutory inspection regime under AKI supervision ... 162
2.4.1
Inspection upon Comissioning KvI: VvI ... 162
2.4.2
Periodic inspection ... 164
2.4.3
Inspection following repairs ... 166
2.4.4
Inspection upon secondary commissioning ... 166
2.5
User inspectorate ... 167
2.5.1
History of user inspectorates. ... 167
2.5.2
Criteria on IVG ... 168
2.5.3
Scope of certification. ... 169
2.5.4
Supervision on IVG ... 170
2.5.5
Certification ... 170
2.6
IVG regime ... 170
2.6.1
Periodic inspection (fixed interval) ... 171
2.6.2
Periodic inspection (extended interval) ... 171
2.6.3
Periodic inspection (flexible interval) ... 172
2.6.4
Inspections – Structural Alterations ... 172
2.6.5
Inspection - Repairs ... 173
2.7
Future legislation ... 173
APPENDIX D - Equipment and Piping ... 174
Equipment and piping ... 174
Pressure equipment ... 174
Piping ... 176
1. Quantitative analysis of in and output of KE process ... 178
1.1
Amount of KEs issued annually ... 178
1.2
Analyzing in- and output ... 178
2. Zooming in on KE process quantitatively... 184
2.1
Locating the discrepancy of unreturned KEs ... 185
2.2
Work in Progress and buffer ... 186
2.2.1
Backlog ... 186
2.3
Intermediate conclusion ... 187
2.4
Specifying the discrepancy ... 188
2.4.1
Contractors ... 189
2.4.2
Other factors ... 190
APPENDIX F - AKI involvement ... 191
1. AKI involvement ... 191
Analysis of dates on KE forms ... 191
AKI involvement: Approval of KE in hindsight ... 193
Unreturned KEs pertaining to statutory inspections ... 193
AKI role ... 194
APPENDIX G - Safety and deficiencies... 196
1. Compromise to safety due to deficiencies in KE process ... 196
Compromise on safety due to unreturned KEs ... 196
Commissioning ... 198
Compromise to safety due to AKI involvement in hindsight... 200
APPENDIX H - Legal compliance and deficiencies ... 200
1. Incompliance due to deficiencies in KE process... 200
APPENDIX I - Causes of deficiencies ... 201
1. Causes for deficiencies ... 201
KEs are not returned for review ... 202
Cause 1 No measuring system ... 202
Cause 2 No ownership materializing ... 203
Cause 3 Lack of incentive or dependencies ... 203
Cause 4 Suppliers are aware of lack of control ... 204
Capacity and availability... 206
HP execution not traceable ... 209
APPENDIX J - Analysis of TRep implementation ... 210
1. Frequency of TReps ... 210
Quantitative analysis of TRep process ... 213
Input output ... 213
SAP work order ... 213
Paper TRep forms ... 214
Discrepancy between work orders in SAP and paper forms ... 214
Extension of validity dates... 216
AKI involvement ... 216
APPENDIX K - Study on cost and yield of IVG status ... 218
1. IVG user inspectorate ... 218
1.1
Compliant without IVG status... 220
1.1.1
Approach ... 221
1.1.2
Analysis TReps and AKI involvement ... 231
1.1.3
Analysis of KEs ... 233
1.1.4
Nature of KE and TRep ... 233
1.1.5
Other costs ... 234
1.1.6
Conclusion: Compliant without IVG ... 235
1.2
Compliant with IVG ... 236
1.2.1
Yields offered by IVG status ... 237
1.2.2
Costs offered by IVG status... 244
1.2.3
Conclusion Compliant with IVG ... 247
1.3
Comparison IVG and non-IVG ... 248
1.4
Safety... 249
1.4.1
IVG and factor F1, Problem P1 ... 250
1.4.2
IVG and factor F2, Problem F2 ... 250
1.4.3
Conclusion on safety ... 253
1.5
Gap between current situation and IVG ... 254
1.5.1
Personnel requirements ... 254
1.5.2
Procedures ... 254
1.5.3
Organizational requirements ... 255
APPENDIX L - Inventorying of requirements on redesign ... 257
1. Requirements ... 257
1.1
Vision and policy ... 257
Policy declaration SHE ... 258
KPMS Quality Management system ... 259
KPMS ISO9001 Quality handbook ... 259
PBZO Prevention policy document ... 260
Risk assessment matrix ... 260
Conclusion: Requirements from policy/vision ... 261
Future policy ... 262
1.2
Goal and function ... 262
Goal and function ... 262
What is left out of consideration ... 264
1.3
Deficiencies in current design ... 266
Hiatus H1 KEs are not returned for review... 267
Hiatus H2 AKI approval is executed in hindsight... 267
Hiatus H3 Registration of hold points is lacking ... 268
Additional hiatus: no verification of hold points before commissioning ... 268
Temporary repairs ... 270
Conclusions: requirements from deficiencies ... 271
1.4
Legal outline ... 272
Functions ... 274
Streams ... 276
Buffer 276
Actors 277
Norms 277
Other (Control) ... 278
Conclusion: Requirements from legal outline ... 278
1.5
Boundary conditions ... 278
KPMS 278
SAP
279
Conclusion: Requirements from boundary conditions ... 282
Leadership team ... 283
Reliability and integrity coordinator ... 283
Inspectorate (Senior inspector) ... 283
WD operational staff ... 284
WD management ... 284
Conclusion: User requirements ... 284
1.7
Conclusion on requirements ... 284
APPENDIX M - Construction of contents of functional design ... 289
1. Functional Design ... 289
Integration of repair plan request and repair plan creation ... 290
Additional functions ... 291
APPENDIX N Introducing dependencies ... 294
1. Introducing dependencies ... 294
Method ... 295
Sequences ... 295
Repair plan inspection plan ... 295
Inspection plan
Judge ... 295
Judge
Repair ... 296
Redesign: Repair plan
Inspection plan
Judge
repair ... 296
Sequences ... 299
Repair
Inspect ... 299
Inspect Start up ... 299
Redesign: Repair
Inspect
Start Up ... 300
Sequences ... 302
Repair
Review ... 302
Redesign: Repair
Review ... 302
Conclusion introducing dependencies ... 303
APPENDIX O - Control system ... 305
1. Establishing a control system ... 305
1.1
Control theory ... 306
1.2
Control design ... 307
1.2.1
Making repair plan Making inspection plan
Judging ... 307
1.2.3
Repair & Inspect ... 310
1.2.4
Inspect
startup ... 311
1.2.5
Repair
review ... 312
1.2.6
Review completion ... 313
1.3
Conclusion ... 314
APPENDIX P - Incorporating temporary repair ... 315
1. Incorporating the temporary repair... 315
1.1
Method ... 315
1.2
Requirements ... 315
1.3
Functional design ... 315
1.3.1
Reducing streams ... 316
1.3.2
Integrating KE and TRep ... 317
1.3.3
Two situations ... 318
1.4
Temporary repair on equipment on VL53.003: Integrating ITP and TRep. ... 320
1.5
Temporary repair on equipment NOT on VL53.003 ... 322
1.6
Extension ... 323
1.7
Control of TRep process ... 323
1.7.1
Control of TRep on VL53.003 ... 323
1.7.2
Control of TRep NOT on VL53.003 ... 325
1.8
Emergency repairs ... 325
1.9
Scenarios ... 326
APPENDIX Q - Literature study on incompliance and violations ... 326
1. Theory study: Compliance with procedures ... 326
1.1
Consequences of human error ... 327
1.2
Danger of Incompliance ... 328
1.3
Types of violations ... 328
1.4
Who violates? ... 328
1.5
Modeling human behavior ... 329
1.5.1
Human behavior economic model... 329
1.5.2
Behavioral Cause model ... 330
1.5.3
Redefinition model ... 332
1.5.4
Conclusion on modeling behavior ... 332
1.6.1
Conflicting goals and faineance ... 333
1.6.2
Unrealistic procedures ... 333
1.6.3
Climate, culture and pressure exerted by management ... 334
1.6.4
Role of management ... 335
2. Theory study: Achieving compliance ... 335
2.1
Designing proper procedure ... 336
2.2
Promote safety and compliance through culture ... 337
2.3
Supervision ... 337
3. Conclusion on theory on compliance ... 339
APPENDIX R - Literature study on IT system use and acceptance 1 Literature
study on use and acceptance of IT systems ... 340
1.1 ERP systems ... 340
1.2 Success of IT systems or successful use of IT systems ... 341
1.3 Acceptance of IT systems ... 341
1.4 Technology Acceptance Model ... 341
1.5 Factors determining use of IT systems ... 342
1.5.1 Explaining argument for change ... 342
1.5.2 Understanding one’s position in the wholeness of systems ... 342
1.5.3 Prior usage and legacy systems ... 343
1.5.4 Same process conventions throughout organization ... 343
1.5.5 Functional match between system and reality ... 343
1.5.6 Data Integrity ... 343
1.5.7 Identify need for circumvention/ease of workaround ... 343
1.5.8 Interdependencies and short term consequences ... 344
1.5.9 Personal characteristics ... 344
1.5.10 Interface usability ... 344
1.5.11 Organizational support ... 344
1.5.12 Training ... 345
1.5.13 Culture and the role of management ... 346
1.5.15 Sequence of events of implementation ... 346
APPENDIX S -Discussion of KE form ... 347
The KE form ... 347
TRep Form ... 349
APPENDIX U - Concept of new procedure ... 352
APPENDIX V - Safety matrix ... 356
APPENDIX W - Work order print out ... 363
APPENDIX X – Adherence to requirements ... 365
APPENDIX Y – Adherence to theory ... 367
Summary (in Dutch)
Tronox Pigments (Holland) B.V. is de enige titaandioxide,TiO
2producent in Nederland. Jaarlijks
produceert de in de Botlek, de bakermat van de Nederlandse chemische industrie, gelegen
fabriek jaarlijks zo’n 100 kiloton titaandioxide uit evenzoveel erts. TiO2 is een wit pigment welke
gebruikt wordt in papier, verf maar bijvoorbeeld ook in tandpasta. Het is een ongevaarlijk
product.
Bij de productie van TiO2 worden echter veel gevaarlijke chemische tussenproducten en
katalysatoren gebruikt. Met name de aanwezigheid van chloor en titaan tetrachloride zorgt voor
de nodige risico’s die beheerst dienen te worden. Om die reden heeft de overheid strenge regels
opgelegd aan grote chemische bedrijven zoals Tronox. Men is verplicht alle activiteiten zoals
productie maar ook onderhoud en inspecties beheerst te laten verlopen.
Daarnaast bestaan er specifieke regels omtrent het gebruik van drukapparatuur.
Drukapparatuur omvat alle apparatuur welke een volume onder druk bevat, zoals vaten en
ketels maar dus ook leidingwerk. De specifieke regels voor het gebruik van drukapparatuur
schrijven periodieke keuringen voor. Ook moet er voorafgaand aan een inspectie een plan
worden opgesteld welk goedgekeurd dient te worden door een externe toezichthouder (AKI,
Aangewezen Keurings Instelling). Na goedkeur mag de reparatie (of wijziging) uitgevoerd
worden volgens het plan. Tijdens of na reparatie worden inspecties uitgevoerd, eveneens
volgens het plan.
Nadat de reparatie opgeleverd is, wordt het plan en aangehechte documenten beoordeeld
(reviewed), en eveneens na goedkeur van de toezichthouder gearchiveerd.
De praktische uitvoering van het voornoemde proces is bij Tronox onderzocht. Vele
tekortkomingen zijn aan het licht gekomen welke ontegenzeggelijk inbreuk op de wetgeving
vormen en mogelijk ook afbreuk doen aan veiligheid.
Twee voornaamste hiaten welke zijn aangetroffen zijn ten eerste het feit dat de externe
toezichthouder AKI dikwijls pas achteraf wordt betrokken, en ten tweede wordt opgemerkt dat
de reparatie en inspectieplannen en aangehechte documenten dikwijls niet worden
geretourneerd en daarmee ook onbeoordeeld.
Uitgesloten kan niet worden of er hierdoor wellicht ongekeurde of ondeugdelijke apparatuur in
gebruik is genomen.
Een specifiek soort reparaties, tijdelijke reparaties, vertoonde vergelijkbare hiaten.
Ten aanzien van het achteraf betrekken van een AKI wordt gesteld dat dit een rudiment is van
eerder wetgeving waaronder deze situatie toegestaan was. Het betrekken van een AKI levert
downtijd op voor Tronox. Dat is de reden waarom men de Aki dikwijls achteraf betrekt.
De fabriek van Tronox wordt gekenmerkt door veel correctief onderhoud. De huidige wetgeving
voorziet in de mogelijkheid om een eigen inspectiedienst gecertificeerd te krijgen als IVG
(Inspectiedienst van de Gebruiker). Er gelden hiertoe voorwaarden op het gebied van opleiding,
onafhankelijkheid en procedures. Een IVG mag taken van de AKI zelfstandig uitvoeren zoals het
keuren van plannen voor reparatie en het uitvoeren van inspecties. Een dergelijke status zou
Tronox de mogelijkheid bieden om de huidige modus operandi min of meer voort te zetten, zij
het binnen een wettelijk kader in plaats van daarbuiten.
Tronox beschikt momenteel niet over de IVG status.
Een onderzoek naar de baten en kosten van de IVG status in vergelijking met opereren binnen
wettelijk kader zonder de IVG status is uitgevoerd.
Op basis van de resultaten is gekozen om de IVG status na te jagen aangezien de meeste
voorwaarden reeds zijn voldaan (bijv. opleiding). Gezien de grote hoeveelheid onverwachte
correctieve reparaties zou het betrekken van een AKI zeer veel downtime opleveren. Een IVG
status daarentegen biedt flexibiliteit.
Nu de eerste hiaat daarmee van de baan is, dient nog een herontwerp te worden gemaakt van
het reparatie en inspectieproces. Onderliggende oorzaak van het niet terugkeren van reparatie
en inspectieplannen ter review, is gelegen in het feit dat geen enkele prikkel bestaat om dat wel
te doen. Daarnaast wordt opgemerkt dat het papieren proces veel rompslomp oplevert en
beheersen van een niet digitaal proces nauwelijks doenlijk is.
Een herontwerp is gepresenteerd, rekening houdende met alle wettelijke bepalingen. Door de
reparatie en inspectieplannen te integreren met de werkorders in het ERP systeem worden de
broodnodige afhankelijkheden (prikkels) ingebouwd. Orders kunnen nu simpelweg geen
doorgang vinden zolang de nodige stappen niet zijn uitgevoerd.
Bovendien is een digitaal proces makkelijker te beheren. Afwijkingen of orders die te laat zijn
kunnen makkelijk worden opgespoord om vervolgens in te grijpen. Hiertoe wordt dan ook ,
naast het functionele ontwerp, een formeel beheerssysteem aangebracht.
Dat gezegd hebbende wordt onderkend dat geen enkel proces waterdicht is. Een aantal
scenario’s bestaan waarin het bedoelde procesverloop wordt overtreden. Aanvullende
maatregelen zijn daarom nodig om het reparatie en inspectie te laten verlopen zoals gewenst.
Het inbouwen van aanvullende prikkels, afhankelijkheden en sanctionering dienen te zorgen dat
dit laatste gebeurt.
Uit alle waarnemingen en theorie blijkt echter dat cultuur de grootste invloed heeft op het wel
of niet volgen van procedures. Hoewel de herontworpen processen het mogelijk maken, is een
aanvullende taak weggelegd voor het management om een cultuur te creëren waarin het niet
volgen van procedures, hoewel fysiek nooit tegen te houden, simpelweg not done is.,
Summary
Tronox Pigments (Holland) B.V. is the only TiO
2producer in the Netherlands. Situated in the
heartland of Dutch chemical industry, this plant in the Botlek, Rotterdam turns around 100kT of
ore into TiO
2annually. TiO
2is a white pigment, found in paper, paint and for example
toothpaste. The product itself is non-toxic.
The production of TiO
2does involve dangerous chemical substances as intermediate products
and catalysts. Specifically, chlorine and titanium tetrachlorine present risks that need to be
controlled. To this extent, authorities have placed the specific demand on large chemical
companies, such as Tronox, that all operations such as production, maintenance and inspections
are conducted in a controlled way.
Secondly, specific rules apply on the use of pressure equipment. Pressure equipment concerns
all equipment enclosing a volume under pressure, such as piping or vessels or boilers. The
specific rules on use of this equipment state that periodic inspections need to be carried out.
Furthermore, upon repair or modification, a plan needs to be issued first. This so called
‘inspection and test’ plan needs to be approved by an external inspectorate (AKI, Aangewezen
Keurings Instelling). After approval a repair or modification may commence. During or after the
repair or modification, inspections apply according to the inspection and test plan. After the
repair or modifications is complete, the inspection and test plan and accompanying
documentation of the operation are to be reviewed, approved by the external inspectorate and
filed.
A study was executed on the implementation of the repair and inspection process at Tronox.
The study revealed many shortcomings, which present definite breach of legislation and
possible risks to safety.
Two main hiatuses found were the fact that the AKI external inspectorate is often involved in
hindsight, and the fact that inspection and test plans and documentation remain largely
unreturned an thus reviewed. As a result, it is unclear whether uninspected or deficient
equipment is commissioned.
A study of a special class of repairs, temporary repairs revealed similar hiatuses.
With regard to involving the AKI in hindsight, it was concluded that the situation was acceded by
the AKI as a remnants of earlier legislation in which such a situation was allowed. Involving the
AKI in hindsight means Tronox is able to commence repairs and commission the plant
immediately, rather than having to await approval before repairing and before commissioning.
The Tronox plant is a plant where a lot of corrective (unexpected) maintenance occurs.
Current legal provisions offer the possibility of having a certified user inspectorate (IVG,
Inspectiedienst van Gebruiker). Conditions with respect to personnel, independence and
procedures apply. Such an IVG is allowed to perform tasks such as approving inspection and test
plans and inspecting repairs before commissioning. Such a status would allow Tronox to
continue its current modus operandi legally. Note that Tronox is currently not granted the status
and is in violation when involving an AKI in hindsight.
A study was performed to take stock of the costs and benefits if such an IVG status, as compared
to a fully compliant way of working without. It was decided to pursue certification as IVG, as
requirements such as personnel (education) are already met. Given the high amount of
unexpected corrective maintenance, it was calculated that the need to involve an AKI and
awaiting approval at all times would incur a large amount of downtime, whereas an IVG offers
flexibility.
Having defied the first hiatus, the second hiatus of the unreturned inspection and test plans is to
be addressed by redesigning the repair and inspection process. Root causes for the hiatus are
the fact that the current process includes no dependencies whatsoever with respect to whether
they are returned. On top of that, the fact that it is a paper process means that it is a burden to
adhere to the process and keeping track of all inspection and test plans is infeasible due to the
amount of paperwork.
After taking stock of all relevant legal demands, a functional redesign was made in which the
above shortcomings are attacked. By making the inspection and test plans an integrated part of
the work order in the ERP software, dependencies are incurred. Orders may not progress until
necessary steps are executed. Furthermore, being a digital system, it is easy to measure and
spot deficiencies such as unreturned or overdue items and execute subsequent control. To this
extent, a control system is designed on top of the functional design.
No process is completely impervious: Scenarios are defined as theoretical possibilities how the
process could be infringed. Additional measures are installed to mitigate the remaining risks.
The thesis concludes with discussing the system behavior. It will be motivated that, firstly, the
redesigned process can be adhered to, i.e. facilitates what it needs to, and meets all
requirements established. And secondly, the process will be adhered to due to the installed
dependencies, incentives and sanctioning.
However, culture is identified to be the main predictor of compliance. Although the redesign
facilitates a future compliant way of working, management commitment to compliance
throughout all operations is adamant. Specifically, a situation in which incompliance is no longer
condoned or regarded to be normal is to be established.
List of abbreviations
As referenced in main text or appendices:
Alphabetical as abbreviated:
AAKI
Aangemelde Aangewezen Keurings Instelling
AKI
Aangewezen Keuringsinstelling
AKVG
Aangemelde Keuringsdienst van Gebruiker
AlCl3
Aluminium Chloride
AMvB
Algemene Maatregel van Bestuur
ARBO
Arbeidsonstandigheden
ATEX
Atmosphere Explosive
AVR
Afvalverwerking Rijnmond
BD
Beleidsdocument (policy document)
BTP
Bestuurlijk Toezichts Programma
BEVI
Besluit Externe Veiligheid Inrichtingen
BIP
Bestuurlijk Inspectie Programma
BN
Bin
BRZO
Besluit Risico Zware Ongevallen
Cl2
Chlorine
CM
Column
CMMS
Computerised Maintenance Management System
C
Carbon
CCvD DA
Centraal College van Deskundigen – Drukapparatuur
CKI
Certificerings- en Keuringstinstelling
CO
Carbon monoxide
CO2
Carbon dioxide
DC
Dust collector (scrubber)
DCMR
Dienst Centraal Milieubeheer Rijnmond
DR
Dryer
EC
European Commission
EEC
European Economic Community
EEG
Europese Economische Gemeenschap (EEC)
ERP
Enterprise Resource Planning
et seq.
Et sequitur
E171
Food additive code of TiO
2, issued by European Food Safety
Authority
FC
Furnace
FL
Filter
FTE
full time equivalent
HCL
Hydrochloric Acid
HP
Hold point
HSE
Health and Safety Executive, alt. Health, Safety and
Environment
HX
Heat exchanger
I&K
Inspectie en keuringstechniek
I&M
Infrastructuur en Milieu
IPO
Initial Public Offering alt. Interprovinciaal Overleg
ISO
International Standards Organisation
ITP
Inspection- and Test plan
IVG
Inspectiedienst van Gebruiker (User inspectorate)
IWE
International Welding Engineer
jis.
Junctis
jo.
Juncto
LAT RB
Landelijk Aanpak Toezicht Risico Bedrijven
LOC
Loss of Containment
LPG
Liquified Petroleum Gas
LPI
La Praktijk Ingenieur (IWE)
KPMS
Kerr-McGee Pigments Management System
KTA
Kiloton Annum
KVG
Keuringsdienst van Gebruiker
MHC
Major Hazard Control (Competent Authority Commodities act
pressure equipment
MIP
Meerjaren Inspectie Plan
NDT
Non Destructive Testing
NIL
Nederlands Instituut voor Lastechniek
NIM
New Inspection Method
NoBo
Notified Body
NVBR
Nederlandse Vereniging voor Brandweerzorg en
Rampenbestrijding
NYSE
New York Stock Exchange
OI
Operating Instructions
OvV
Onderzoeksraad voor Veiligheid
PBZO
Preventie Beleid Zware Ongevallen
PbEG
Publicatieblad van de Europese Gemeenschap
PED
Pressure Equipment Directive
PEU
Perceived ease of use
PGS
Publicatiereeks gevaarlijke stoffen
PRDA
Praktijkregels Drukapparatuur
PU
Perceived usefulness
RD
Review Documents
RISA
Richtlijn Specifiek Accreditatie Schema PED
RToD
Regels voor Toestellen onder Druk
RUD
Regionale Uitvoerings Dienst
RvA
Raad van Accreditatie
RvS
Raad van State
RWS
Rijkswaterstaat
SAP
Systeme, Anwendungen und Produkte (ERP software)
SHE
Safety, Health and Environment
SOK
Samenwerkings Overeenkomst
Stbl.
Staatsblad (State Journal)
StCr.
Staatscourant (State Gazette)
SP
Separator
SZW
Sociale Zaken en Werkgelegenheid
TAM
Technology Acceptance Model
TC
TiCl4 (Tronox specific abbreviation)
TCD
Technische Commissie Drukapparatuur
TiCl4
Titanium tetrachloride (‘Tickle’)
TiO
2Titanium dioxide (‘pigment’)
TK
Tank
TPB
Theory of planned behavior
TRA
Theory of reasoned action
TREP
Temporary repair
UV
Ultraviolet (radiation)
VBS
Veiligheids Beheer Systeem (safety control system)
VGM
Veiligheid, Gezondheid en Milieu (SHE)
VI
Veiligheidsinstructie (safety instruction)
VL
Verzamellijs (collection list)
VMS
Veiligheids Management Systeem (safety management
system)
VNCI
Vereniging Nederlandse Chemische Industrie
VNG
Vereniging Nederlandse Gemeenten
VROM
Volkshuisvesting, Ruimtelijke Ordening en Milieu
VR
Veiligheidsrapportage alt. Veilgheids Regio
VS
Vessel
VvH
Verklaring van Herkeuring
VvI
Verklaring van Ingebruikname
WABO
Wet Algemene bepalingen omgevingsrecht
WD
Werktuigkundige dienst (Planning and job preparation dept.)
WECCO
western electro chemical company
WED
Wet op de Economische Delicten
WESA
Wet Specifiek Accreditatie Schema Drukapparatuur
WGHOR
Wet geneeskundige hulpverlening bij ongevallen en rampen
WIP
Work In Progress
WM
Wet Milieubeheer
WP
Witness point
WRZO
Wet rampen en Zware Ongevallen
WVR
Wet Veiligheidsregio’s
X
Examine
"un examen détaillé, complet et fréquent, effectué par
un homme compétent suffirait pour réduire de 75% au moins le
nombre d'explosion d'appareils à vapeur, d'autant plus que toute
machine peut, à la longue, évoluer vers un mauvais état qu'un
examen détaillé permettrait de reconnaître"
Robert Vinçotte, as early proponent of the usefulness of inspection regimes on steam equipment, 1872.
1.
Introduction
Toothpaste, an IPod, an aspirin tablet, sheets of paper and wall paint. Finding a common denominator of these products may seem farfetched. Yet a readily observable commonality, the white color of these products, is what ties them to each other and to the company Tronox.
The pigment that gives all the above mentioned products their bright vibrant white color is called titanium dioxide, abbreviated TiO2. In fact, most white surfaces found, ranging from mundane applications such as
lines on a road, up to exotic applications such as the coating on space crafts, owe their color to TiO2.
Tronox produces TiO2 out of ore. Using several continuous chemical processes, the ore is transformed
into TiO2 powder.
1.1
Tronox
This thesis describes a research conducted at, and presents analysis and results applicable specifically to the TiO2 production facility of Tronox at Botlek, the Netherlands. This plant is a subsidiary of the
international chemical company Tronox ltd.
Headquartered in Connecticut, Tronox features pigment production facilities in the Netherlands, USA and Australia. Besides chemical operations, Tronox has mineral sands operations in South Africa and Australia. The mineral sands being mined are partially used as feedstock for Tronox’s own chemical plants, the remainder is traded.
Worldwide, Tronox ltd. has 3500 employees across all operations. Tronox is among the largest producers of TiO2. For reference, [Appendix B] contains more detail on the history of Tronox [Appendix B 1.1] and
an elucidation of the current global operations of Tronox [Appendix B 1.2].
1.2
Titanium dioxide TiO
2Titanium dioxide is used as white pigment in many applications, such as coatings and plastics. TiO2 is
sometimes referred to as ‘the perfect white’, because of its superior whiteness and opacity as compared to other white pigments as zinc oxide or lime.
TiO2 is non-toxic and is also found in food as additive E171. Global production is approximately 7 million
tons. More information on TiO2 is found in [Appendix B 1.3].
1.3
TiO
2production at Tronox Botlek
Tronox Botlek facility is operated 24/7 to produce approximately 90kT per annum of TiO2. The plant has a
nominal capacity of approx. 100kTA, yet due to (either planned or unplanned) maintenance achieves an uptime of 90%.
Tronox Botlek has a staff of approximately 250 people, either own personnel or contractors.
The production of TiO2 uses the chloride process. This process consists of two main chemical reactions:
Chlorination (1) of titanium ore (already containing up to 95% of TiO2) to form TiCl4. The TiCl4 is oxidized
(2) to form pure TiO2 again. The chlorine is fed back to the chlorination step.
The two steps mentioned happen in a continuous process in what is referred to as plant 1. In a separate plant (indeed, plant 2), the TiO2 undergoes some mechanical treatments such as milling and drying. This
Figure 1. Systemic representation of TiO2 Production at Tronox Botlek.
More detail on the process in general [Appendix B 1.4], as well as specific details on the TiO2 production
[Appendix B 1.5] and operations [Appendix B 1.6] at Botlek are given in the [Appendix B].
1.4
Safety and environment
Although TiO2 is a non-toxic and harmless product, its production is concerned with the use of many
dangerous chemicals, imposing risks to human and environment. Chief amongst which is chlorine (Cl2).
The intermediate product TiCl4 (‘Tickle’) is a dangerous, highly corrosive and reactive substance. Over
seven hundred tons of TiCl4 are present at the premises of Tronox, as well as a thousand tons of
sulphuric acid and four hundred tons of hydrochloric acid.
The presence of these and many more chemical substances classifies Tronox among the most dangerous class of chemical industry. Under normal circumstances, no or limited substances are emitted. Substances are contained in equipment such as piping or vessels. In terms of safety, any loss of containment (LOC), e.g. a leakage or blowout is the prime risk present at Tronox.
1.5
Legislation and supervision
Owing to the risks present, Tronox’s operations are governed by a plethora of legislative provisions. An exhaustive study on all provisions1 applicable is performed [Appendix C]. This study has established exactly which legislation prevails in the remainder of this thesis. Specifically, the results of the study will allow us to:
• Determine whether current operations at Tronox are in compliance with prevalent legislation. • Establish a redesign which meets all legislative requirements.
Also, the summary of legislation, including references to specific articles, as presented in [Appendix C] is offered to the reader who wants to assess2 the contents of this thesis against legal determinations to allow him to do so without profound legal knowledge, or the need to take stock of legislation comprising over a thousand pages spread across various legal sources.
A final reason for performing such exhaustive study on legislation is the fact that within Tronox, no profound knowledge of the matter is present. Furthermore, it was noted that the subject of law is
1
European and national bills, guidelines, acts, orders, decrees, directives and jurisprudence.
2
i.e. be (practically) able to judge and test truthfulness, in accordance with the spirit of Popper’s theories of refutibility and falsifiability as per Popper, K. ‘The Logic of Scientific Discovery’. New York, USA: Basic Books, 1959.
especially apt to being discussed by laypersons enunciating many a myth3. The study allows separating
myth from fact.
The study is found in [Appendix C], the results are summarized in the subsequent subparagraphs.
1.5.1
Legislation and safety
The (state of) equipment is the first barrier to prevent loss of containment. Ultimately, the state of equipment determines whether chemicals are contained or a leakage may occur.
To keep equipment in a fit state, maintenance is applied, and equipment is operated within operational limits.
A third barrier is presented by managing said maintenance and operations. For example, making sure all jobs are performed, within time. This third barrier is governed by so called BRZO legislation (Besluit Risico’s Zware Ongevallen). This legislation applies to high risk class of chemical companies. It demands companies to formalize the management of operations and maintenance, in a so called VMS (Veiligheids Management System) Safety Management System.
Figure 2. Safety barriers (green= preventive, orange = repressive).
To assure the legislative provisions are met, authorities conduct supervision (audits, reporting), as will be discussed in subsequent subparagraph. The supervision aims at both the preventive measures such as VMS Safety Management System as well as the repressive measures discussed next.
Legislation demands Tronox to have emergency plans and facilities such as a fire brigade, which come into play if and when an accident has occurred.
As final repressive measure, when all the above has failed, BEVI legislation (Besluit Externe Veiligheid Inrichtingen) applies. In short, this legislation determines that no housing is to be built within a certain perimeter of Tronox or vice versa, and it determines that certain types of chemical installations may not be neighboring to prevent ‘domino effects’.
Note that many more determinations stemming from legislation apply. Presented here are (the spirits of) the main provisions. For interested readers, more provisions and detail are found in [Appendix C 1]. Above and beyond any of the aforementioned, it is noted that BRZO includes an empty framework decree stating that, in short, Tronox should simply do whatever is necessary to operate safely4.
3
For example, many still refer to archaic law such as ‘Hinderwet’, or ‘Stoomwezen Equipment’, without being aware of exact provisions, and unaware of the fact that these Acts were revoked decades ago.
Also many general statements are made such as ‘this is legally allowed’ or ‘this is obligatory. By law’, without being able to state any source, rendering evaluation of the correctness of such statements impossble.
4
BRZO, Article 5, Clause 1 states: “He who operates an installation, takes all measures necessary to prevent major accidents and to limit the consequences thereof to both human and environment’.
BEVI (Spatial clearance)
Emergency Plan/Fire brigade etc.
BRZO Supervision
VMS Safety Management System
Maintenance and operation
Equipment
Note, any and all provisions which are relevant for the remainder of this thesis (specifically pressure equipment provisions [Appendix C 2]) will be discussed (or referenced) if and when relevant, leaving reading of the entirety of [Appendix C] discretionary.
1.5.2
Supervision
A study5 was also conducted on the supervision which the chemical industry in general, and as such
Tronox, is subjected to. The study is found in [Appendix C 1, 1.3 et seq.].
This study was carried out to gain understanding of what authorities asses to be compliant or
incompliant. To illustrate, some legal provisions are very clear e.g. “a pump with electrical power above 100kW needs two emergency switches’’, yet some provisions are open to interpretation e.g. “owner of equipment must be in control of maintenance of equipment”.
However, the study revealed another conclusion with respect to supervision.
It was concluded that supervision on high risk companies is insufficient. In the last 15 years, the budget for supervision in general has been decreased fivefold. Besides bringing down budget, and hence the amount of supervisors and subsequently the amount of supervisory inspections (audits), another (resulting) change is witnessed.
Supervision audits used to be focused at on-site inspections of the state of equipment, presence of facilities etc. In recent years supervision has taken the form of what is called ‘system supervision’. In short, such supervision does not inspect the actual state of equipment or actual compliance (e.g. correct usage of tools, safety garments etc.). Rather, system supervision focuses on inspecting the management system of a company. When a management system is in order, it is implicitly assumed that the ‘physical reality’ suffices as well. The trend of system supervision (sometimes called horizontal
supervision, metasupervision, 2nd line supervision and supervision on supervision) is found in many areas,
including such areas as finance and taxing.
Supervision on BRZO companies such as Tronox also constitutes system supervision. Only one or two days per year, an audit is conducted. The specific focal point (i.e. subject) of the audit is disclosed in advance, as is the moment of auditing.
Recent grave incidents with chemical companies have incurred criticism on the decreased and superficial ‘paper’ supervision conducted by authorities. Experts criticize the current supervision as being a paper reality and insufficient, as well as lacking knowledge and being too lenient.
Public opinion pursuant to recent incidents increasingly puts blame on supervisory bodies (competent authorities), besides the companies where the incident occurred itself.
Expert opinion and public pressure have led to, or are paralleled by, political pressure and initiatives to reconsider current supervision on chemical companies.
The above criticism is not just opinionated, but has taken formal cause as well. Most of recent severe accidents were followed by independent investigations into the accident and its run–up. Almost without exception, lack of supervision or enforcement is among the causes.
A verdict was recently enunciated in court presenting a novum: A competent authority was held liable for damage stemming from a fire at a company under its supervision. The judge’s verdict stated the
competent authority was ‘too forbearing’ in interpreting its (otherwise discretionary) supervision task. All of the above leads to the conclusion that supervision is absolutely insufficient, in that it is not able to spot deficiencies with respect to compliance and ultimately safety of the chemical industry. In other words, Tronox may by no means assume that passing an audit of a competent authority means that Tronox may conclude that no deficiencies exist. Therefore the study concludes:
5
Literature review and a series of interviews with several inspectorates in the chemical industry as well as competent authorities.
‘Tronox should assure itself of being in complete control of all processes with regard to maintaining and operating its equipment safely’
It is to be expected that supervision will be increased following recent criticism, and that enforcement will be more stringent and competent authorities less forbearing67. In fact bills have been proposed to do so. The above statement remains unaltered in the light of these developments.
1.6
Repair and inspection
Tronox produces TiO2, using chemical processes or mechanical treatments (e.g. drying, filtering). Safety
is defined to be the first priority within the company. Indeed, attention for safety is called for, since it was established that the production of TiO2 involves presence of high amounts of dangerous substances at
high pressure and temperature.
It was established that preventing loss of containment (LOC) of these substances boils down to making sure equipment does not fail. A chemical process has been defined (‘the recipe’), and equipment has been designed to facilitate.
We can deduce further then that an unsafe situation, as in loss of containment, which is the main danger at Tronox in general, can materialize when any of two things happens (or a combination):
1. The recipe is not adhered to and e.g. larger pressures exist, wrong reactions occur, meaning the equipment is not capable to contain.
2. The equipment does not meet its specifications (anymore), so that it is unable to contain the substances.
The first deviation could occur when the plant is operated beyond its operational limits, e.g. in terms of temperature or pressure. The subject is not discussed any further here and is left to the field of process engineering and control.
Equipment used in the plant is designed to cope with the chemical composition, phase, temperature, and especially pressure as intended in the chemical recipe. Obviously, equipment will not fail upon (mild) exceeding of these nominal characteristics, as a safety factor is always incorporated.
Figure 3. Severe yet typical corrosion on heat exchanger in corrosive medium (Left: new Right: several weeks of operation).
6
Since conducting the study [Appendix C] on supervision, Tronox was indeed subjected to unannounced, midnight (!), BRZO inspection. Also the frequency of audits has risen.
7
Since conducting the study [Appendix C] on supervision, it was indeed stated by the competent authority (of BRZO legislation as well as specific pressure equipment legislation), that they will enforce more stringently. “We will no longer apply the coercive penalty of fine anymore, rather a fine will be issued unwaveringly and immediately upon ascertion of incompliance.’ Anton J. Tol, director of Inspectie SZW, department MHC Major Hazard Control competent authority BRZO , ARBO, Warenwet. Enunciated at Praktijkregels Drukapparatuur Jaarcongres, December 4, 2012, the Hague, Netherlands. Attended
However, equipment experiences physical degradation. Equipment may be overdesigned to allow a certain amount of degradation, yet a situation may arise when equipment is simply unfit to perform its task safely anymore. Sometimes, this may be apparent when equipment is e.g. already leaking, sometimes it may be discovered upon a periodic inspection.
Whenever it is established that equipment is unfit, it needs to be repaired. The largest class of equipment at Tronox is static pressure equipment, such as vessels or piping. One could state that the whole factory consists of pressure equipment, with the exception of pumps and instruments (e.g. sensors) and civil construction (e.g. supports, fencing).
A subclass of such static pressure equipment is subject to an inspection regime. This means that it is to be periodically inspected, and that an inspection is to be conducted during or after a repair has taken place. This determines whether equipment is indeed fit to safely be commissioned.
The topic of repairs is even more relevant due to the fact that degradation, and hence the need for repairs, occurs in profusion at Tronox. The presence of highly corrosive chemicals such as TiCl4, Cl2, HCl
and the presence of solid material8 incurring abrasion and clogging, lead to a facility requiring high
amounts9 of both corrective and preventive maintenance. Approximately 1000 work orders per month
are issued for maintenance, incurring 1,5 million euro of maintenance costs every month.
Repairs are mostly conducted by contractors, and sometimes by the Tronox WD (Werktuigkundge Dienst) department (mechanical service department) who is also concerned with issuing and planning jobs, and accepting the result afterwards. Repairs are typically conducted on site at the Tronox premises, mostly requiring equipment to be shut down.
Inspections are carried out by Tronox’s inspectorate. This department of four inspectors is led by a sr.inspector. Inspectors are present during office hours, and available oncall 24/7 outside office hours.
Figure 4. Repair work being executed (note use of life air due to presence of chlorine etc.).
8
Ore and finished product are granular material, dissolved in slurry, and sand is blasted through certain parts to prevent clogging.
9
i.e. requiring maintenance effort well above what is considered average in the chemical industry at large in terms of OPEX fraction, or amount of forced shutdowns due to repairs.