• Nie Znaleziono Wyników

Development of a Total Support System for the Entire Life Cycle of an LNG Carrier

N/A
N/A
Protected

Academic year: 2021

Share "Development of a Total Support System for the Entire Life Cycle of an LNG Carrier"

Copied!
8
0
0

Pełen tekst

(1)

Development of a Total Support

of an LNG Carrier

Nono Yamamoto

Senichi Sasaki

*

1.

INTRODUCTION

Judging from energy resources trends, construction of new LNG ships will likely take recent studies on the long-term usage plans of LNG carriers into greater consideration. To ensure the stable use of LNG ships over a long period, it is necessary to control the causes of age-related deterioration both during construction and while in service in order to reduce life

cycle cost and risks. In recognition of these circumstances,

research was carried out over a period of two years from 2007

through 2008 willi the aim of offering an integrated support

service for the entire life cycle of LNG ship to shipowners. as well as shipyards.

The research carried out included development of: (I) corrosion protection technology

(2) technology for safety

management of fatigue strength: and (3) preventive

maintenance technology for machinery and equipment. The

research conducted under each of these themes is listed below.

(1)

Corrosion protection technology

Actual condition survey of coating deterioration in ballast tanks of the ship was carried out. The condition of coating deterioration in ballast tanks was confirmed.

A system for judging the coating deterioration condition in ballast tanks was developed using coating deterioration sensors and potential distribution simulation technology in ballast tanks according to the boundary element method.

(2) Technology for safety management of fatigue strength

(a) Management method during construction was proposed for high risk locations that were bases of fatigue strength management and were selected by risk ranking among potential risk locations. (h) A system for assessing hot-spot stress with high

accuracy was studied.

) The applicability of fatigue condition monitoring

using fatigue sensors was studied as part of fatigue condition monitoring technology for ships after commissioning.

Resaerch Institute. Nippon Kaiji Kyokai (ClassNK)

System for

the Pntire

I if' Cr-1

Deift University of Technology

Ship HydromeChafliCS

laboratory

Library

Mekelweg 2

26282 CD DeIft

Phone: 31 (0)15 2786873

E-mail: p.w.deheer@tUdelft.fll

Preventive maintenance tecnnologv ¡or macninety

and equipment

The change of damage rates over time was summarized by analyzing and assessing damage data from main engine parts.

RBM/RBI system of all machinery/parts including main turbines and engine room auxiliary equipment was prepared.

An overview of the systems for judging the level of coating

deterioration in ballast tank, fatigue strength management procedures during construction, and RBM/RBI system of main engine is introduced here.

(3)

2.

Development of quantitative coating

condition monitoring system

2.1 Concept of monitoring method

Ballast tanks in

ships arc required to be provided with

protective coating. While the paint is effective for insulating tank surfaces from sea water (ballast water), once the coating

deteriorates, local macro-cells form around the deteriorated part

of the coating, and corrosive currents are generated. Usually,

sacrificial anodes are installed to maintain an effective coating

system in the ballast tanks. As a result, galvanic cells are

formed between the deteriorated coating parts and sacrificial

anodes. If the potential changes in the ballast tank

accompanying formation of such

galvanic cells can be

measured by potential measurement, deterioration of coating

can be detected.

The relationship between the potential Ø [VI in the electrolyte

near the material surface and current density i [A/rn2] can be expressed by polarization characteristics. Using this relationship, the relationship between change in potential and

change in current density can be obtained. The magnitude of

surface resistance is related to the insulation performance; thus,

the effectiveness of coating can be assessed by the surface resistance value. Consequently, if the magnitude of surface resistance can be derived from potential measurements, the condition of the coating can be judged because a correlation

exists between the ratio of reduction rate of surface resistance value and the coating deterioration area.

(2)

2.2

Measurement procedures

The tank surface resistance can be assessed by measuring the

differential potential when current is impressed. Fig. I shows

the concept of the newly developed measurement system.

2.3 Verification experiment

To verify the applicability of the developed method, the

potential was measured in a ballast tank of an LNG ship with

an age of 23 years, as shown in Fig. 2. The measurements were performed in one compartment within one transverse space in the side ballast tank shown in Fig. 3. This ballast tank had been painted five years previously. Slight coating deterioration could

be seen on the edge of the

stiffeners,

but no coating

deterioration was found in other parts. The condition of the

coating was extremely satisfactory.

Fig. 4 shows the potential distribution measurements at the bottom surface of the compartment (depth 12.8 m) from the ballast water surface (depth 5.2 m) in the compartment. The maximum value of the differential potential was measured at the position where additional anode was installed. Similar

results were also obtained by potential distribution simulation

in the compartment by boundary element method (BEM). In

this study example, the surface resistance value in the

compartment was estimated as

500 (m2).

This value

corresponds to the result that the mean coating deterioration

area in the compartment is approximately 0.2% (=1/500).

From such actual ship measurements, it was confirmed that measurements of differential potential can be made from the measurement method with system configuration shown in Fig. I. Moreover,

it was also confirmed that the potential

distribution in the

tank can be effectively

estimated by

numerical simulation using the boundary element method. This showed that the coating deterioration state in the ballast tank of a ship can be judged using the proposed method.

Optional

a nod e

Reference

electrode

Figure 1 Potential measurement model in ballast tank

0.018 0.0 16 0.0 14 ? 0.012 C) 0.010 0.008 0.006 0.004 0.002 O

Figure 2 LNG ship in which potential measurements were made

Figure 3 Coating condition ill which the potential measurements were made

-e-

Meas.i

---o Meas. 2 -0-- Meas. 3

Analysis

ClassNK TECHNICAL BULLETIN 2009

5 6 7 8 9 10 11 12 13 14

Depth Im]

Figure 4 Measured and evaluated potential distributions when the optional anode was installed at a position 1 .6 m from the

seawater surface

(surface resistance of the tank walls is 500 Çm2)

2.4 Development of practical system

As a pilot test, a trial coating deterioration monitoring system

was designed and installed on an actual LNG ship. The

reference electrodes, additional anodes and connecting cables

were to be installed in the ballast tank for a long period, so the

specifications important to these items were set as waterproof performance. ability to withstand pressure, and durability. Since the cargo areas of an LNG ship are hazardous areas, intrinsically safe circuits are essential for the system to be

(3)

installed. An intrinsically safe barrier must be provided at the boundary of the hazardous area and the safe area. Flameproof

cables are required to be used within the hazardous areas. Fig. 5 shows the arrangement of the system assuming its installation on an actual ship.

Safety Area (engine room)

measurement unit intrinsic safety barrier Hazardous flameproofjunction box Area f TTTTiT1 optional anode I ref. electrode optional anode ref. electrode optional anode ref electrode shunt anode ßallast Tank optional anode1 ref. electrode OpL!Onal anode] ref. eledrode I optional anode ref. electrode shunt anode

Figure 5 Block diagram of the system applied to LNG ship

3.

Fatigue management during

construction

3.1 Concept of fatigue management

FatigLie cracks are potentially likely to occur in most welded

joints of the hull structure. The possibility of initiation of a fatigue crack, however, varies depending on the detail of the welded joint type, magnitude of load received, workmanship,

and so on. Also, the degree of hazard for the developed crack varies depending on the position of the member in which it has

occurred and the functions of the member. Accordingly, it is important to assess the overall fatigue risk at the potential fatigue hazard locations in the hull structure, and carefully manage the processes during construction at locations where

high risk has been assessed so as to effectively ensure overall fatigue strength and safety. By clearly recording the conditions at locations with high fatigue risk when the ship is newly built, the records can be effectively used as reference indices during visual inspection after the ship is commissioned.

3.2 Assessment of fatigue risk

For assessing fatigue risk, (i) tile possibility of fatigue crack initiation

(2) the

hazard of initiated crack; and (3)

the possibility of detection of initiated crack during survey, must be

assessed from the overall perspective. The assessment of

fatigue risk is to be carried out according to the procedure

below.

Assessment ofthe possibility offatigue crack

initiation

The fatigue strength assessment of locations in the hull structure where fatigue crack may occur is an essential design requirement. The possibility of fatigue crack initiation is to be

assessed taking the cumulative fatigue damage as ari index. This kind of fatigue strength assessment should preferably be performed in line with the concepts of the "Guidelines for

Fatigue Strength Assessment". However, assessment must be

performed considering the differences in design conditions

specified in the guidelines and those of ships to be assessed (for instance, differences in typical service route which is the basis

of design loads, differences in design life, differences in post

weld treatment, such as grinding and so on).

The judgment on fatigue strength conforming to the guidelines

corresponds to assessment with 2-sigma lower limit curves;

therefore, the possibility of fatigue damage when the allowable

damage is satisfied is

about 2.3%, and the possibility of

damage below this value becomes a pre-condition of

assessment. Based on such a pre-condition, risks can be

categorized into grades such as low degree of hazard with the assessed fatigue life greater than i O times the design life; high

degree of hazard with the assessed fatigue life

less than

I .3 times the design life, and a medium degree of hazard lying in between these two grades.

Assessment of a hazard of initiated fatigue crack Even if the fatigue crack initiated in the hull structure has the

same crack pattern, the degree of hazard differs depending on the importance of the member ill which the crack has initiated.

Moreover, even if the crack is initiated in a member having important structural functions, the effect on the function may

differ depending on the location where the crack initiates. The degree ofhazard must therefore bejudged considering all these points.

The most important function in a hull structural member is watertighiness. From this perspective, cracks with a high degree of hazard may be referred to as cracks that initiate in a member that forms part of a compartment boundary subjected

to liquid pressure. Such a crack initiates at a position close to the boundary of shell plating. watertight bulkhead, stiffeners

attached to shell plating and watertight bulkhead (longitudinals),

and girders attached

to shell plating and tile *atertight

bulkhead. Crack with medium degree of hazard refers to a

crack that initiates in a member at the compartment boundary

(4)

close to the boundary

of airtight

bulkhead, stiffeners (longitudinals) attached to airtight

bulkhead, and girders

attached to airtight bulkhead. A crack with a low degree of

hazard refers to a crack that initiates at a location distant 1mm the compartment boundary.

(3) Assessment of the effects of inspection

Loss of functions and catastrophic failure of structural

members can be prevented beforehand by detecting and

repairing a crack that has initiated in the hull structure during

thc period from its initiation until its growth to the loss of

functions or catastrophic failure. In this case, inspection has important significance, and the effects of inspection can be

assessed by how a crack can be detected before loss of

functions or catastrophic failure occurs with the growth of the

initiated crack. That is, the possibility of detecting a crack

during inspection depends on the ease of inspection (ease and dependence on the inspection environment), and the chances to discover cracks during inspection.

In principle, inspection is performed visually, therefore the

brightness

of the

location to be inspected considerably

influences the possibility of discovering cracks. From this

viewpoint, the inspection environment can be classified based

3.3 Enhanced

construction

monitoring

for

fatigue

Fatigue management during construction has the purpose of

adequately ensuring the desired fatigue strength by monitoring the workmanship and work conditions in detailed construction

system, which becomes pre-conditions of fatigue

strength assessment to be considered during design at important fatigue

locations. Conventionally, such monitoring of workmanship

was performed adequately by classification societies, shipbuilders. and ship owner's representatives, but by recording

the monitoring conditions, the important locations can be

clearly identified. Moreover, by properly recording the workmanship condition, the records are anticipated to be used as reference standards for monitoring after the commissioning

of the ship.

In principle, inspection during construction is

Table I Classification and management of fatigue risk ranks

on the visibility when performing visual inspection.

Whether the relevant member or location can be approached closely and inspected or not (accessibility) is a key point in performing inspections. If the space within the compartment during dry-docking is not empty, whether inspection can be performed or not can be classified by these two conditions:

possible in practice and not possible.

When considering the crack

propagation,

cracks can be

classified by the judgment standards, whether a crack will propagate and lead to major damage during the short period

less than two and a half years between Intermediate Surveys, or

whether the possibility of a crack propagating this way in a

five-year period between Special Surveys is small.

(4) Assessment of fatigue risk

Fatigue risk is assessed by estimating the sum of the product of

the degree of risk mentioned earlier, namely (i) possibility of

fatigue risk initiation; (ii) degree of hazard of initiated fatigue crack; (iii) inspection environment; (iv) accessibility to inspection location: and (y) rate of crack propagation. and the weighting factor. Depending on the assessed fatigue risk value, a management method can be decided as shown in Table I.

similar to the conventional inspection procedure, but it is also

necessary to acquire records for confirming the necessary

conditions in each process.

Monitoring method includes preparing the recording forms for

each of the following: (1) summarizing general information

related to monitoring of relevant locations, and (2) summarizing the recommendations for check items and recording items in the inspection at relevant locations; and implementing monitoring according to the assessment category of fatigue risk rank. Such a method can ensure effective monitoring.

The monitoring procedure according to the assessed fatigue

risk rank is as given below.

-I. Perform close-up inspection and record results in each process during construction for locations classified as risk rank A. Record the state of workmanship quality in each

Rank Management method

A location that needs to he monitored carefull. In addition to completion surs ey. inspection during construction is implemented at locations requiring fatigue management during

construction, records of workmanship quality condition in each process maintained, and records of the state of completion also maintained.

B

Although this is a location to be monitored, the risk is judged to be lower than that of rank A. Completion survey is implemented at locations requiring fatigue management during construction, and records of the state of completion are maintained.

C This is a location judged to have no problems in particular. and the usual classification survey is

applicable.

(5)

process and also record the state of completion.

-.

Perform close-up inspection and record results in each procs during construction for locations classified as risk rank B. Record the state of completion.

The records of state of workmanship quality are meant for

indicating the following states:

State of plate edge in the installed state before welding State that satisfies workmanship quality standards such as gap. misalignment, etc. in the installed state before welding

If specified, the back gouging state External appearance of weld bead

1f specified, the extent of full penetration weld/deep penetration weld

If additional leg length, etc.. is specified, the leg length/throat thickness

If specified. the state of weld treatment Other states deemed necessary.

Recording procedures for recording the state of completion are as below.

(I) Record of final state that shows the position of the hot spots at relevant locations in the structure.

After completion of construction. records that have been divided into several stages that identify the positions of the relevant locations in the hull are to be kept, and finally. records that correspond to the records mentioned above are also to be maintained.

If the records divided into several stages mentioned above are difficult to obtain, then recorded positions

(photographed points) are to be recorded with the photographs.

In case of longitudinals. the names of compartments retrieved from records are to be recorded with the photographs.

4.

RBM/RBI system for main engine

4.1 Background of the development

Although the maintenance and inspection of machinery and equipment in ships is based on time-based maintenance and

inspection with fixed time interval as the basis, condition based

maintenance (CBM) is the nonna! practice for deciding the

period of open-up inspection based on the results of condition

monitoring in case of steam turbine ships. On the other hand.

Risk-Based Maintenance (RBM) /Risk-Based Inspection (RBI)

with which maintenance and inspection arc implemented on a priority basis starting with equipment and parts with high risk

and based on the results of risk assessment, have recently been implemented for in shore-based plants.

4.2 Base ofthe RBM system

ClassNK has developed an RBM system for machinery and equipment to be installed on diesel ships and steam turbine

ships. This system has been developed referring to the "API 581

Risk-Based Inspection

Base Resource Document" of the

American Petroleum Institute (API). Risk is generally expressed as fiuilurc rate x "importance

of damage

(consequence)", but risk is defined as "occurrence probability of failure" x importance of damage (consequence) by API. The

definition of risk in this system also follows the API definition. The definition is as given below.

Occurrence probability of failure = "Standard failure frequency" x "equipment modification factor" x 'management modification factor".

Importance of damage = "Extent of voyage interruption" x

"average repair man-hours".

Here, "standard failure frequency" X (%/year) was assigned as

a function of the ships age T. The value of the constant based

on the Society's damage data was determined for each part, and

the initial value of the standard failure frequency was set.

However, the standard failure frequency varies depending on

the state of damage that has occurred during voyage or damage discovered during Periodical Surveys: therefore, in this system. this calculation formula was formulated enabling updates based on the Bayes method.

A=aexp(b/T)

(1)

a, b: Constants depending on each part

"Equipment modification factor" is determined by the condition monitoring method used and by the maintenance and inspection method of the equipment. "Management modification factor" is a factor related to ship management.

"Extent of voyage interruption" expresses the consequence of failure for a ship when the relevant machinery or equipment is damaged it is associated with the redundancy of the machinery or equipment. "Average repair man-hours" is expressed as the

product of the number of persons required for repairs and the

hours required for repairs.

4.3 Developed RBM system

Fig. 6 shows ax example of the software screen for specifying

the occurrence probability of failure in the developed system.

while

Fig. 7 shows an example of the

software screen specifying the importance of damage.

(6)

part of equipment; the next inspection period of the equipment

is determined based on this risk. Fig. 8 shows an example. In this case, the green and yellow colored boxes show that the

relevant equipment can be used in continuation without open-up inspection. The orange and red colored boxes indicate that the period for open-up inspection has been reached. The

maintenance of equipment is planned such that open-up

inspection is performed preferentially starting with high-risk

equipment.

At present, the maintenance and inspection of equipment is

considered to

be time-based maintenance for reasons of

practicality. However maintenance according to CBM or RBM is more rational. In the future, it is anticipated that either CBM

or RBM will be selected and implemented according to

equipment choices. The system developed by ClassNK this time is a prototype of an RBM system that may be developed in the

future, and its detailed image has been offered as an example

system.

Figure 6 Occurrence probability of failure

5.

CONCLUSION

To ensure the stable use of LNG ships over a long period,

management of the causes of deterioration from ageing while in service and during the construction of the ship is important for

reducing life cycle cost and risks. Therefore, research and

development was carried out over a period of two years related

to the following: (1) Corrosion protection technology: (2)

Technology for safety management of fatigue strength: and (3) Preventive maintenance technology for machinery and equipment.

A method based on potential measurements in the ballast tank as a technology that can be practically applied was developed as

a method for judging the state of required coating objectively for corrosion protection. Further, an effective quality control

procedure during construction was developed for fatigue

management according to the risk rank of important locations associated with fatigue. Finally,

a prototype of a system

assigning data for judging maintenance based on assessed risk values was developed for preventive maintenance and management of machinery and equipment.

CIassNK Risk Base Maintenance System

jl;;'-

-Ship Name. #1 NK MARU

Modi

V

End ..1nc r.1ti. Likelihood Equipment Result on. 2 Main Engine

V

K

1997 FWD Likelihood Failure Frequency 0.02 1.

>

Equip. Modification Factor X, 10. Inspection Effectiveness.

Corn po nent #1 CyL Liner.

V

M ana gerne nt+'

Modification Factor

x,

2-5

Condition Monitoring Method. ' Lesell.' : Visual Check O.. Lesell. . Not Equipped

D.

j.

LeseI2. LeseI3. : Measurement,r :Nondesthictive Inspection. O.' @.' Level2, Lesel3 X. Q.' O. Alarm Monitoñng.

E LeseI4. : Pressure Test Q. Level4. Q,. High Grade Q.' Leel5 Monitonng.'

60

ClassNK TECHNICAL BULLETIN 2009

V

Ship Code

(7)

CIassNK Risk Base Maintenance System

Analyzed Result Ship Name Inspection Result Master Data Equipment Result on.-

<

Consequence Main Engine.-

V

1997 FWD.-

V

Voyage Interruption

O.. Rep aiid by Ship.

@. Speed Reduction-c O+ Cylinder Cut

Operation.-O. MiE Stop

>

Component 3.

Ns

Working Member. #1 Çy. Liner..

M

Man Hour.' For Repair. 5

WK Hour..

End

CIassNK Risk Base Maintenance System

Figure 7 Importance of damage

BackupL

Restaf

Maintenance Plan Risk Ma elihood Consequence

Figure 8 Output of RBM system

.-.-Control Panel -Code Equipment ConhixIlerl Intenal 2007.' 2008 2009 2010 2011 2012.'

n'lo AFT.- ft/I] AFT FWU All IWO AFT.' AFT.' IWD AFT.

[0010 MnEnglie

8000iíiaar

#?CLier airi Engre. 0000. H.

uivari

-

_.

H.

im'

lR

£0010 Main £nqlie.' 2000.' -SIE.' CyEIiìer.' H.-£0010 Hain E lie.' $000.- - -01F.' bCyLIir.' H.-01'A.' MnEngiie.' 60::

i

U..Lai U

S?.'

600:i Record 1225. Ship Code

V

Ship Name #1 NK MARU.-

V

Analyzed Inspection Master

-Result Result Data

#1 NI( MARU

N!

Ship

Code.-P' Marn

Consequence

4.- 2 X. 2

(8)

Cytaty

Powiązane dokumenty

Nie jest jednak jasne, czy Miller uważa, że jest do tego zmuszony jako autor przez potrzebę znalezienia pewnego wzoru, czy jest zmuszony przez impuls Foucaulta

Światowe badania pokazują bowiem, że języki migowe realizują wzorce funkcjonowania społecznego, jakie można zaobserwo- wać w językach mówionych (Bailey, Lucas 2011: 83). Oznacza

POCZĄTKI JĘZYKOZNAWCZEJ REFLEKSJI NA TEMAT AFAZJI — STRUKTURALIZM Założeniem podejścia strukturalnego jest ujęcie języka jako struktury formalno-funk- cyjnej składającej się

Mówią, że się to zaczęło od wielkich wojen, co tam się niegdyś odbywały, a w których wiele narodu zgi- nęło i dotąd to krew ludzka, choć z ziemią pomieszana, uspokoić

Відповідно, для забезпечення позитивних змін, яких потребує морська політика України, система пра- вового регулювання морської

Ziębie tytuł Maryi Arka Przymierza kojarzy się w znacznym stopniu ze skrzyniami pełnymi skarbów, ukrytymi w tajemniczych miejscach (s.78-79). Maryja została

Przedmiotem zarządzania personelem w przedsiębiorstwie są wszelkie działania związane z analizą zapotrzebowania na kompetencje stanowiskowe, dopasowanie kompetencji do stanowisk,

Oceniając tendencje wskaźnika zysku na akcję w badanym okresie, można stwierdzić, że drugi kwartał charakteryzował się systematycznym spadkiem.. Ostatni kwartał