Polish NPP project and EIA requirements
IAEA, Vienna, 18.05.2016
Krzysztof Wojciech FORNALSKI
PGE EJ 1 Sp. z o.o.
2
This Presentation has been prepared by PGE S.A. (“ PGE”) and PGE EJ 1 Sp. z o.o. (“ PGE EJ 1”) (the
“Company”) on the basis of information received from different sources, including not independently audited and publicly available information. The Company is not responsible for the accuracy, reliability and consistency of information contained in this Presentation (“ Presentation”).
This Presentation includes results of preliminary analyses considered by PGE and PGE EJ 1. PGE and PGE EJ 1 reserve the right to introduce changes and modifications as well as to complement this information at any given stage and are not under obligation to explain reasons for these changes, modifications and complementation.
The information included in this Presentation cannot form the basis for any claims or civil law suits against PGE, PGE EJ 1 or any other entity from within PGE Capital Group, in particular with regards to damages or indemnities to be paid in case of negligence in contracting.
PGE and PGE EJ 1 wish to inform that all responsibilities and risks pertaining to and resulting from any decisions taken on the basis of or in relation to the information provided in the Presentation shall be borne by makers of these decisions. As a result, PGE and PGE EJ 1 on their own behalf and on behalf of all their directors, partners, employees and agents, declare that none of the entities listed herein will incur any liability towards any person in connection with any consequences of the decisions and/or actions taken in reliance on this Presentation and information provided.
This Presentation reflects prevailing conditions, and PGE and PGE EJ 1’s understanding of the current situation, all of which are accordingly subject to change after this date upon obtaining new information or occurrence of new events.
For internal distribution only.
Disclaimer
3
EIA requirements in Poland (NPP project)
The proposed scope of the EIA report for Polish NPP
Agenda
Site selection process for the first Polish NPP
Polish Nuclear Power Plant (NPP) new build project overview
Polish NPP project and EIA regulations
4
EIA requirements in Poland (NPP project)
The proposed scope of the EIA report for Polish NPP
Agenda
Site selection process for the first Polish NPP
Polish Nuclear Power Plant (NPP) new build project overview
5
Unchanged country imperatives driving nuclear power introduction to Poland – security of supply (aging generation fleet, EU climate change policies)
– Electricity supply shortage (near blackout) in August 2015, State Grid
Operator forced strong electricity supply reductions on large and industrial customers for the first time since 1989
Continued Polish government commitment to the implementation of the Polish Nuclear Power Programme
Nuclear power in future fuel mix according to the Polish Energy Policy until 2050 (each of three reference scenarios defined includes nuclear in the national energy fuel mix)
Increase of Poland’s industrial capabilities with a number of Polish companies having potential to join the nuclear supply chain
Diversification of Poland’s generation portfolio in order to lower CO2 emission (currently approx. 90% based on coal and lignite)
PGE as the leader continues NPP build project development activities with important milestones achieved
Business purpose of NPP new build project NPP Project
Polish NPP project and EIA regulations
6 Mining
Power generation
Transmission
Distribution
Wholesale &
Supply
• 2 open pit lignite mines (Bełchatów and Turów)
• Lignite output 50 million tons p.a.
• Production net ca. 55 TWh
• Installed capacity ca. 12.6 GW
• Sales of heat ca. 18 million GJ
• 2 Lignite-fired power plants (Bełchatów and Turów)
• 2 Hard coal-fired power plants (Opole and Dolna Odra)
• Combined heat and power plants – 8 sites (Szczecin, Pomorzany, Gorzów, Bydgoszcz, Zgierz, Kielce, Rzeszów and Lublin-Wrotków)
• Hydroelectric power plants (Hydro ca. 97 MW, Pumped-storage ca. 1.5 GW), Wind farms 311 MW
• Activity of PSE S.A.
PGE Polish Energy Group – Main Investor
• Distribution of energy 32.54 TWh
• Distribution grid: 281,290 km
• Number of substations: 91,374
• Final consumers 39.60 TWh
• Wholesale market 62.44 TWh
• Balancing market 1.10 TWh Nuclear potential locations
7
Stage II Stage III Stage IV
Stage I
Pre-development Development Construction Start-up
and commissioning
Site selection – site investigation and environmental surveys – obtaining the decision on environmental conditions and site permit
Development and execution of Integrated Proceedings (amongst others selection of technology)
Business and financing model development (incl. support mechanisms)
National and site infrastructure planning (incl. transmission system)
Communication and Education (public support)
Preparation and implementation of Integrated Management Systems
Building nuclear and other specific competences (Capacity Building)
Obtaining the Decision in Principle
Preparation of a detailed technical plan of a nuclear power plant (FEED)
Prep. of a preliminary safety report
Obtaining key decisions, permits and licences:
– Licence issued by the PAA (Polish National Atomic Energy Agency) – Construction permit for NPP and
environmental permit
Signing a contract regarding the connection to the transmission grid
Development of associated infrastructure for the NPP construction
Communication (public support)
Building of key competences and human resources development
Financial close and Final Investment Decision
Site preparation and initiation of the final stage of the process
First concrete
NPP construction process
Delivery of long lead equipment
System tests
Development of national and site infrastructure for the NPP operations
Connection to the transmission grid
Simulator installation
Further expertise development and building site operator structure
Fuel Loading Permit
Power tests
Start-up Licence
Integration of the NPP with the National Grid
Operating licence
Concession for power production
Commercial operation (COD)
Daily operations of the NPP
Maintenance of the NPP
Fuel management
Waste management
Decision
in Principle Final Investment Decision Fuel Loading
IAEA (Phase 2) IAEA (Phase 3)
Source: own materials
Preparation of the investment process and construction of Poland’s first nuclear power plant is divided into four key stages (in line with IAEA recommended approach)
8 Decision in
Principle Source: own materials
National and site infrastructure planning and preparation
Feasibility Study Site selection
(EIA, Site Permit) based on site characterization
Stakeholder Management and
Communication (local communities
focus)
Integrated Proceedings
Implementation of Integrated Management
System
Capacity Building Support
mechanisms and business
model
Legislation and relations with
European Commission
Decision in Principle
Organization of Polish Nuclear Program – 10 main projects
9
EIA requirements in Poland (NPP project)
The proposed scope of the EIA report for Polish NPP
Agenda
Site selection process for the first Polish NPP
Polish Nuclear Power Plant (NPP) new build project overview
Polish NPP project and EIA regulations
10
Site selection
Full environmental studies and site characterization works to be started in 2016 (seismic already ongoing, meteo equipment under installation)
Preliminary national and site infrastructure plan developed in cooperation with local communities and Pomerania voivodeship
First stage of transmission grid and transmission infrastructure analyses completed for candidate sites in cooperation with PSE – Polish National Grid So far studies and analyses were conducted in three considered sites of a nuclear power plant: "Choczewo ", "Lubiatowo-Kopalino" (Choczewo) and
"Żarnowiec" (Gniewino and Krokowa). Based on their results, in January 2016, two sites were selected for the full program of site characterization
and the environmental impact assessment - "Lubiatowo-Kopalino" and
"Żarnowiec".
11
Environmental assessment
The purpose of environmental assessment is to provide data necessary for a decision whether a given site is suitable for the
construction of a nuclear power plant in terms of environmental protection.
Start – 2016 Duration – 12 months
Site investigation
The objective of site investigation is to confirm that a given site is suitable for a nuclear power plant in terms of nuclear safety.
Start –2016 Duration – 24 months
Site
characterization and environmental assessment
Preparations are underway to launch full environmental assessment and site investigation by PGE EJ 1
The Environmental Scoping Report (ESR) has been prepared and, on the 5th of August 2015, the first stage of the environmental impact assessment (EIA) procedure
was launched.
Polish NPP project and EIA regulations
12
EIA requirements in Poland (NPP project)
The proposed scope of the EIA report for Polish NPP
Agenda
Site selection process for the first Polish NPP
Polish Nuclear Power Plant (NPP) new build project overview
13
EIA Requirements
EIA requirements in Poland – Nuclear Power Plant context
Polish NPP project and EIA regulations
THE E.I.A. ACT
The Act of 3 October 2008 on the Provision of Information on the Environment and its Protection, Public Participation in Environmental Protection and Environmental Impact Assessments
Polish: Ustawa z dnia 3 października 2008 r. o udostępnianiu informacji o środowisku i jego ochronie, udziale społeczeństwa w ochronie środowiska oraz o ocenach oddziaływania na środowisko
Other acts of the Parliament:
The Environmental Protection Act
Polish: Ustawa Prawo ochrony środowiska
The Atomic Law Act
Polish: Ustawa Prawo atomowe
Secondary legislation to Atomic Law: Regulation of the Council of Ministers of 10 August 2012 on detailed scope of assessment with regard to land intended for the location of a nuclear facility, cases excluding land to be considered eligible for the location of a nuclear facility and on requirements concerning the location report for a nuclear facility (Journal of Laws of 10 August 2012, item 1025)
14
This Act shall implement within the scope of its regulation the following Directives of the European Communities:
Council Directive 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment (OJ L 175 of 05.07.1985, p. 40, as amended;
OJ, Polish special edition, Chapter 15, Vol. 1, p. 248);
Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora (OJ L 206 of 22.07.1992, p. 7, as amended; OJ, Polish special edition, Chapter 15, Vol. 2, p. 102);
Directive 2001/42/EC of the European Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain plans and programmes on the environment (OJ L 197 of 21.07.2001, p. 30; OJ, Polish special edition, Chapter 15, Vol. 6, p. 157);
Directive 2003/4/EC of the European Parliament and of the Council of 28 January 2003 on public access to environmental information and repealing Council Directive 90/313/EEC (OJ L 41 of 14.02.2003, p. 26; OJ, Polish special edition, Chapter 15, Vol. 7, p. 375);
Directive 2003/35/EC of the European Parliament and of the Council of 26 May 2003 providing for public participation in respect of the drawing up of certain plans and
programmes relating to the environment and amending with regard to public participation and access to justice Council Directives 85/337/EEC and 96/61/EC (OJ L 156 of 25.06.2003, p.
17; OJ, Polish special edition, Chapter 15, Vol. 7, p. 466);
Directive 2008/1/EC of the European Parliament and of the Council of 15 January 2008 concerning integrated pollution prevention and control (OJ L 24 of 29.01.2008, p. 8).
THE E.I.A. ACT
EIA Act
15
The selection of the proper site for NPP construction is a complicated multi-step process. The EIA items are represented in, inter alia:
• site investigations lasting up to 24 months consisting of
meteorological, archeological, (hydro) geological as well as natural environment studies
• envelope boundary conditions for the nuclear technology (Gen III reactors)
• analysis and modelling of environment impacting factors, e.g. air pollutants dispersion calculations from conventional (combustion) and unconventional (radionuclides) sources, noise mapping, landscape and natural environment impact, water quality and cooling water plume, wastes management
• application for the environmental permit including the EIA report (first stage, conceptual design) preparation and submission to the relevant authority (General Directorate of Environmental Protection [GDOŚ])
EIA and the site selection process for NPP – #1 EIA Requirements
Polish NPP project and EIA regulations
16
Continued…
• the EIA report review as a part of administrative procedure, including:
opinions of Director of Maritime Office, Ministry of the Environment, State Sanitary Inspector and State EIA Commission
transboundary procedure coordinated by the General Directorate of Environmental Protection (GDOŚ) (+ Espoo Convention)
necessary for the environmental decision of investment
can be repeated (if necessary)
• environmental decision by GDOŚ after EIA (but before the site and construction/building permissions)
• national and local EIA commissions (which advise GDOŚ)
• the EIA report (second stage at the construction permit issuance) preparation and submission to the relevant authority (GDOŚ)
• EIA report review as a part of administrative procedure, following the same steps as at the first stage
• opinion of the President of National Atomic Energy Agency (PAA) – the Polish nuclear regulatory body
EIA and the site selection process for NPP – #2
EIA Requirements
17
EIA requirements in Poland (NPP project)
The proposed scope of the EIA report for Polish NPP
Agenda
Site selection process for the first Polish NPP
Polish Nuclear Power Plant (NPP) new build project overview
Polish NPP project and EIA regulations
18
General description of the project and general plan of the site
Schedule for construction and exploitation phases including start-ups
Description of the construction phase and impact zones with materials and utilities requirements - balance sheet
Description of the natural environment
Geological, hydrological and geotechnical site relevant conditions
Surface and underground water conditions (quality, levels, flow velocity and direction etc.)
Population distribution and living conditions including archeology
NPP safety and emergency plans and procedures
Climate change (and associations) and adaptation measures
Technological aspects of NPP exploitation and impacts analysis
including technological and location variants – impact assessment and minimization measures implementation (if exceedances reached)
The proposed scope of the EIA Report for the first Polish NPP
EIA Report
19
Description of different options expected by the Investor
Accident scenarios
Nuclear and non-nuclear impacts
Dispersion of radioisotopes in air, water and ground
Description of assessment methods
Description of all other activities
Restricted use area around NPP
Social aspects and local community support
Plans for future monitoring of the environment
Attachments
Maps and figures
Abstract
References
The proposed scope of the EIA Report – continued #2 EIA Report
Polish NPP project and EIA regulations