• Nie Znaleziono Wyników

The canalization of the lower Rhine

N/A
N/A
Protected

Academic year: 2021

Share "The canalization of the lower Rhine"

Copied!
69
0
0

Pełen tekst

(1)

(

I

I

RIJKSWATERSTAAT

COMMUNICATIONS

rIO

THE CA ALIZATION OF

•• A.c...

..

o.r

•• P , ' " '

(2)

RIJKSWATERSTAAT COMMUNICATIONS

THE CANALIZATION

OF THE

LOWER RHINE

by Ir. A. C. de Gaay

Chief Engineer of Rijkswaterstaat, Directie Bovenrivieren

and

Ir. P. Blokland

Chief Engineer of Rijkswaterstaat, Directie Sluizen en Stuwen

(3)

DIRECTIE ALGEMENE DIENST VAN DE RIJKSWATERSTAAT

THE HAGUE - NETHERLANDS

The views in this report are the authors' own. Section I by ir. A. C. de Gaay

Section II by ir. P. Blokland

(4)

Contents

page

I. Why eanalization with loeks, sluiees, ete. was needed

5 1. Introduction

6 2. Basic information and considerations

6 1. Water management

7 2. Inland navigation

9 3. Remedies

9 4. River bed characteristics

10 5. Hydro-electric generating plant

11 3. The project

11 1. Objectives

11 2. Operation

13 3. Adapting the river bed

13 4. Consequences

14 4. How the project was carried out

14 1. Building operations

16 2. Management

16 3. Cost

11.

The eonstruetion of the weir eomplexes

19 1. General

24 2. Brief description of the tbree weir complexes

24 1. Hagestein complex

26 2. Amerongen complex

27 3. Driel complex

30 3. Description of Hagestein weir complex

30 1. Design of gates

32 1.1. Hydraulic study

38 1.2. Model studies on gates

40 2. The fishways

40 2.1. Remarks

43 2.2. Eel passages

44 3. Hydro-electric generating plant

50 4. Tbe visor gates

50 1. Lifting gear

57 5. Tbe cylindrical gate valve

57 1. Gate valve lifting gear

(5)

MAAS RHÖNE

-.

,

-

.-'.

'.

,

EMS

,.

WESER

11

ELBE

o : __....:'~O:..._....:'~O~O '~'~O:..._-.:'~O~O

__.:;250

k"",

rigurc I. Calchment area of Ihe Rhine.

(6)

I.

Why canalization with locks, sluices etc. was needed

1. Introduction

A few kilometres after crossing the Dutch frontier the Waal splits off from the river Rhine and flows to the left carrying 70% of the Rhine's water. A few kilometres further down, the IJssel splits olf and flows to the right carrying 12% of the water coming down the Rhine. The river Rhine turns to the left carrying the remaining 18% of its original quantity. The river is then called Neder-Rijn (Lower Rhine) and after some 50 km westwards its name is changed into Lek.

This must be regarded as Nature's distribution; the layout of the canals and cities, and the dimensions of dikes, sluices and bridges were all conditioned by it.

On the other hand, the water coming down the river had to be put to the best pos-sible use, so the flow had to be redistributed or at all events had to be made redistri-butable. The exigencies of both water management and inland shipping made a certain degree of regularisation desirabie, particularly when the Rhine discharge was low.

To meet the principal requirements, a scheme was worked out by Rijkswaterstaat (the Water Control and Public Works Department) which:

a. when the discharge was either ave rage or high would maintain the original distri-bution over the three branches;

b. when the discharge was low would enable to control distribution of the Rhine's water between the Waal, IJssel and the Lower Rhine.

When the discharge is low, the Lower Rhine is reduced to a temporary canal the discharge of which is controlled and the navigation depths of which are optimized by three sets ofweirs and locks.

The scheme is known as the Lower Rhine canalization project. The Lower Rhine will be acting as a canal for six to nine months every year, depending on the natural regime of the river Rhine and on the exigencies of water management and transport. During the remaining period of higher discharges, when the arguments against artificial distribution prevail, the weirs will be raised, thus reinstating Nature's distri-bution ofthe discharge over the th ree branches.

(7)

2. Basicinformation andconsiderations

The catchment area of the river Rhine covers the greater part of Switzerland and vast areas of France, Germany, Luxembourg, Belgium and the Netherlands; it totals to about 160,000 square kilometers (Figure 1).

The river is mainly fed by rain water but in spring and early summer melting snow helps to swell the river quite considerably. Low water periods, sometimes protracted, generally occur in autumn (Figure 2).

2.1. Water management

The Rhine runoff is discharged through the three branches known as the Waal, Lower Rhine/Lek and IJssel and the distribution is fairly stabIe, as the following table shows.

Discharges in cub.m.per sec.

Rhine Waal

Lower Rhine IJssel

Lowest OLR Average Highest

recorded recorded

630 1,000 2,140 13,500

490 720 1,490 8,250

90 185 390 2,700

50 95 260 2,300

The reader might get the impression that this would be amply sufiicient to satisfy all the low lying country 's possible fresh water needs.

But it is not. The minima give rise to three problems viz. a. The intrusion of salt water through river mouths and locks; b. The welling up of saline groundwater;

c. The lack of water for flus hing polluted water.

Large quantities of river water in excess of the country's normal consumptive requirements are needed to combat these evils. The situation is aggravated by the fact that the Rhine water itself is highly contaminated.

The reader will understand that it is becoming increasingly essential for the Nether-lands to formulate and pursue a sound water-conservation policy in view of the ir-regularity of the discharges and the growing demands for water.

One way of doing so is to provide fresh water stocks in the south-west and centre ofthe country (Figure 3).

The former Zuyderzee (now called Lake IJssel) is a natural reservoir, provided of course that sufibent water can be made available. To ensure adequate supply, it was considered desirabie that the runoff of the IJssel effluent he improved. This involved

(8)

7000 6000 5000 4000 3000 w Cl 2000

'"

< J: ~ <:> 1000 ,~" / \ /

1\

/

"

" / "-" 2 % / ~

"

11

I~

5'

<:

/

/

\ /

!/

~

\ \ / /

J

~

\ / / / \ / \ / /

V--

25 %

~

'--

-

"

/

/

I'--

--...

r--

-

-t--

l /

V

501~

V

V ' -r- ...

~

--

/

25~r---

r--

I

-V

V V

---f%'-

10 ~

~

I'----

/ r--- r--..

r---VI

-...

r--

"'r

-

I'---

I - -

/ , , -

-

-

-- - -

-

r---

t

-/

-

-

-

~t-" ;-2 %

--

--

r

-aCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP aCT

Figure 2. Frequency of mean discharges of the Rhine at Lobith.

both enlargement of the lower discharges and reconditioning of the river-bed. These points are dealt with in paragraph 3.2.

2.2. Inland navigation

Itwill be clear from the low discharge figures in the above table that in dry periods , navigation is greatly hampered by lack of depth.

In both the Lower Rhine and the IJssel the water in the navigation channel is sometimes less than one metre deep.

During OLR conditions (i.e. the conditions obtaining when the runoff is below the ordinate low river runoff, which occurs for 20 days in an ave rage year) incidental depths of not more than 2.40 m in the Waal, 1.50 m in the Lower Rhine and 1.40 m in the IJssel are recorded.

These figures are obviously below the standards for inland navigation (i.e. 2.50 m-2.70 m) and for international Rhine traflic (3.00-3.30 m).

(9)

lEEUWA.RDEN o

,

,

,

,

..

, , .' c. (-.-,.-..;

,

J'

,

,

".-., ..1'.

,

" f ENSCHEDE (,

,

i.

,

'"

i ZWOllE o / , f EINDHOVEN o

,.,

; , THE H.... GLJE o

WEIRS IN lQWER RHINE

I1

=

BELGIUM

,.~.

"

.

.., " AA\IIlICHfI " .>

_

...~.~._~.

Figurc 3. The Rhinc andilsemuents in lheNClherlands.

(10)

2.3. Remedies

These considerations show that in dry periods there is simply not enough water for three rivers but the runoff could do for two (although even then the requirements are not always met).

In order to solve the problems it was decided to stem the discharge of the middle effluent in dry periods by means of a weir at Driel near Arnhem. The water held back in this marmer will then swell the natural discharges of the IJssel and the Waal.

Below this master weir two additional weirs have been built to control the water level in the lower course of the river and ensure thatitremains navigable without causing

s~riousfiooding.

A similar condition must of course be set for the IJssel: fiooding might result here if the Lower Rhine discharge were to be stemmed during higher discharges. These con-ditions are dealt with in paragraph 3.1.

Figure 4.

MAIN DIKE SUMMER DIKE

FORELAND

2.4. River bed characteristics

In view of what is said below about the lay-out of the weirs, the operation of the system and fiooding it is essential that the ultimate configuration of the longitudinal section and cross-section of the rivers be studied.

In cross-section (Figure 4) the river bed consists of two parts: firstly, the minor bed, the width of which is fixed by means of groynes and embankments; it increases as one goes downstream and is of such dimensions as will ensure that the minor bed will carry normal discharges while providing areasonabIe navigation channel.

This principle has been adopted for 150 years; it is based upon practical and theo-retical considerations, including mnd movement calculations and model tests.

The second part consists of the fiood plain which is generally found on both banks between the main dikes. The main dikes proteet the low country behind them against fiooding. The flood plain is often protected against small summer floods by means of

"summer dikes".

Both the minor bed and the flood plain are kept as clear of obstacles as possible so as to provide sullicient capacity for fioods and ice.

Bibliography.-a. "The Ingenieur" 1956, No. 37 (The Rhine Canalization, summary by E. M. H. Schaank) No. 39 (The construction of Hagestein weir, by H. C. Wentink) and No. 41 (Bed Load computations, by

K.van Til);

b. XXII International Navigation Congress, Paris 1969, paper S. 1-5 (Sand Transport Studies related to the canalization ofthe Lower Rhine, by R. P. Sybesma, M. de Vries and A. Zanen).

(11)

!

1---+---+--+----+

1

-+---+---1_++

L

/ "

...V V PROGR. 35 '---+---+-_t__:

L

--LL/----,;;,~=

- -

L-..

, ----t-I- - _ . - - c - - /./" ROGR. 12501 ~'"

1 ./

_L _ _/ Z ~.\~

!;,v

V:<

NAP 1- 2- 3- 4- 5- 6- 7- 8-990 980 970 960 950 940 930 920

Figure 5. Longitudinal section of the Lower Rhine.

910 900 890 880 870

A 10ngitudinal section of the Lower Rhine is shown in Figure 5. Gradients

de-crease from 15.10-5in the upper reaches to 10.10-5in the middle reaches and decrease

still more towards the sea.

It should be noted that the bed material of the upper reaches of the Rhine effiuents consists ofsand. Medium grain sizes range from 1.5 to 0.5 mmo

2.5. Hydro-electric generatingplant

The design of Hagestein weir included a 2,500KVA hydro-electric generating plant.

The 10 KV ACelectricity generated is fed directly into the grid.

The semi-automatic plant runs without attention. A fuIl description is given in a

separate chapter.

The idea of equipping the two other weirs with generating plants was abandoned, since the power obtainable would have been less than that produced at Hagestein weir and even that was not particularly great.

(12)

3. The project

The set-up ofthe project is described in paragraph 3.2. The object ofthe undertaking must be considered before the scheme itself can be understood. Figure 3 should be consulted for the topography.

3.1. Objectives

Ithas been pointed out that certain limitations must be set to the measure of runoff contro!. They may be formulated as follows:

a. IJssel discharges should be kept above 250 cub.m. per sec. if possibIe to facilitate navigation;

b. IJssel discharges should not be forced above 350 cub.m. per sec. to prevent the unnecessary inundation of flood plains;

c. Lower Rhine discharges should be kept above 50 cub.m. per sec. to satisfy the

n~eds of water-users along its course and to maintain a minimum flushing current; d. levels above the three weirs should be kept below

+

9.20 m,

+

6.00 mand

+

3.00 m (zero = N.A.P.*)to prevent the unnecessary inundation of flood plains;

e. a lock should be built in a by-pass adjacent to each weir in the main river;

f. runoff or bed-load transport conditions should not be altered by the implementation of the project.

ltwas found that the adoption of three steps between Arnhem level and sea level would give satisfactory results.

These boundary-conditions determined the project almost completely. There were further conditions because sites had to be found for the weirs and locks.

The locks were called Drie!, Amerongen and Hagestein, after neighbouring villages. Amerongen is 30 km below Driel and Hagestein is 23 km below Amerongen.

3.2. Operation

As already stated, the IJssel discharges should be kept between 250 and 350 cub.m. per sec. for the longest possible period. What discharge will eventuaUy be chosen will depend on water management requirements, especially in the northern part of the country. This will determine the level to which the water will have to be backed up by the master weir at Driel and for how long.

Within the stated limits of 250 and 350 cub.m. per sec. the weirs will function from between 160 and 270 days in an average year and the level above the weir will fluctuate

a~cordinglybetween

+

8.20 mand

+

9.20 m.

Figure 6 gives the figures for an arbitrary runoff year and a programme based upon a desirabIe IJssel discharge of 300 cub.m. per sec. and a minimum Lower Rhine

(13)

discharge of 50 cub.m. per sec. The quantities discharged byeach of the three branches are shown in the figure.

There is no need to interfere with the natural distribution during the winter months nor woulditbe possible to do so. But in April, when the IJssel discharges fall below the 300 cub.m. per sec. minimum, the level is boosted by partly closing the weirs. This also increases the Waal discharge. The Lower Rhine discharge is correspondingly reduced. The May discharges do not require boosting and the weirs are opened (i.e. raised right out ofthe water).

But in the period from June to mid-August they must be lowered again.

From early July onwards the 300 cub.m. per sec. minimum cannot be adhered to because of the 50 cub.m. per sec. that must be reserved for the Lower Rhine. So in this case the IJssel discharges will drop to 200 cub.m. per sec. and the Waal discharges to 1,050 cub.m. per sec. A short rise in August will allow human intervention to cease for a while but then the autumn drought will bring another operational period.

On the worst day the Rhine runoff will be slightly above OLR but owing to the weir the IJssel discharge will be 175 cub.m. per sec. instead of 100 cub.m. per sec. and the Waal discharge will be 825 cub.m. per sec. instead of 750 cub.m. per sec. This will give a navigable depth of 2.00 m instead of 1.40 m in the IJssel and 2.50 m instead of2.40 min the Waal.

The figures are given by way of illustration and are not claimed to be exact.

4000 m3/sec 3000 2000 1000 WAAL IJSSEL

JAN FEB MAR APR MAY JUN JUL

I

I

t-t-

I i

I

I

AUG SEP ocr NOV DEC

Figure 6. Effect of canalization on the Rhine effiuents in a fictitious year.

(14)

3.3. Adapting the river bed

The ratio in which the backed-up Lower Rhine discharges are distributed over the IJssel and Waal depends mainly on their discharge capacities at their junctions with the Lower Rhine, i.e. by the slopes, widths and bottom levels of their upper reaches. As it was considered essential that the IJssel effluent should receive the major share, the upper reaches of this effiuent had to be modified accordingly. The width was one factor that could not be changed because of its effect on the sand transport character-istics. The slope and bottom level could be changed, however, without fear of com-plications. This was confirmed by model tests.

An increase in slope was effected by straightening out two major bends, one 9 km, the other 25 km, below the bifurcation. This shortened the river by 3-!- and 4-!- kilo-metres respectively. The 30 km stretch was cut to 22 km so the average slope (the aVe rage being 13 X 10-5)was increased by nearly 25%.

ltis not yet fully effective, because it will be a few years before the bottom level has adjusted itself. Nevertheless, bottom erosion is expected to proceed upstream, eventually reaching the bifurcation.

Then the third factor will automatically come into effect. If this automatic process is too slow, dredging may be considered. In any case, there are means by which the IJssel may be helped to swallow its calculated and programmed share.

If they are not employed forthwith, it is because gentle adjustment by nature is preferred to an enforced regime, the consequences of which are hard to predict.

3.4. Consequences

The effects of the scheme on bed load transport and bottom levels, especially near the two bifurcations, have been very carefully weighed indeed. Studies and model tests preceded the operation, which is being watched continuously to ensure there is the closest possible conformity between the plan and its realization.

After all, this low-lying country's defences against flooding, either by the sea or by the rivers, may not be exposed to unpredictable risks.

There might be unpredictable risks if the distribution of flood water over the Rhine effluents got out of hand, or if the presence of the weirs and ancillary structures in the river bed raised the maximum flood levels.

The effect of building the weirs, etc. out of commission was investigated. Recom-mendations were made and the river bed was reshaped accordingly.

Although as a mie the design water levels will not harm the riparian land, some of the lower parts of the flood plains will be affected by the unusual ground-water levels. Complaints were investigated by an arbitration commission, who recommended either that indemnification be paid or that preventive measures be taken. In most cases the second expedient is preferred. Raising low ground, draining low ground towards the river below a weir and pumping are some of the remedies.

(15)

4. How the project was carried out

4.1. Building operations

The implementation of the scheme commenced in 1954-1955 when two bends were straightened out: one in the Lower Rhine a few kilometres above Arnhem, the other in the IJssel some 25 kilometres below Arnhem.

Then, in the years 1954-1961, the first weir and lock near Hagestein were built. The downstream complex was built first because the work at this point would at once improve the navigability of part of the river above the weir, whereas there would always be sufficient depth in the tidal area below the weir.

1t should be borne in mind that neither ofthe downstream weirs (i.e. those at Hage-stein and Amerongen) can affect the volume of runoff.

Work on the upstream weir at Driel, on the other hand, would have affected the Lower Rhine discharge immediately and made the whole river virtually impossible to navigate.It was reasonable, therefore, that this "main tap" should be the last to be constructed and not to put it into commission until both downstream weirs were completed.

Figure 7 shows the Hagestein site on the inner bend of the river where there was room in the flood plain to excavate a pit for the foundations and to build a dike around it to prevent flooding.

When the weir and the lock were finished the river was made to flow through the newly dug bed and the old bend was dammed off.

The middle weir near Amerongen was built by similar methods in the period between 1958 and 1967 but here it was impossible to realign the river by straightening out one bend so the new bed traverses two consecutive bends (Figure 8). Apart from this, the procedure was the same as that adopted for the Hagestein complex.

The "main tap" or master weir near Driel (Figure 9) was constructed in the years 1962-1967, and the adjacent lock in the years 1967-1970. There was not enough room between the hills in the north and the maindike in the south to excavate a pit big enough for the foundations of both weir and lock and place a dike around it that would remove the risk offlooding.

Therefore it was decided to build the weir close to the southern main dike with a temporary dike first, then shift the river into its new bed through the weir, and finally build the lock on foundations surrounded by another temporary dike in the old river bed.

The work was interrupted by high discharges, but that is usual when carrying out river projects. There were no exceptional floods, however, and the work went ac-cording to plan.

The last major work in the project involved the straightening out of a large bend in the IJssel some nine kilometres below Arnhem; this was done in 1969. There were several minor works and adaptations but they are not described in this article.

(16)

:;

.

.

'JL- ~1- ' , " " ' ,

Figure 7. Loc3tion of I-Iagcstein wcir showing dam across farmer rivcr.

Figure 9. Location of "cir at Drie!.

Amerongen- ...

.,'

'.'

(17)

4.2. Management

Each weir with its loek wi11 he operated by eight men. There is housing-accommo-dation for the staff on the site. The operation period will be from six to nine months in an ave rage year. The rest of the time (i.e. when the discharges are high) is spent on maintenance work. The mechanica1 and electrical systems are serviced by specially trained mechanics.

The Lower Rhine is part of the Rhine system and comes under the International Rhine Commission regulations, which stipulate that vessels must he free to use the river without let or hindrance and without having to pay any to11.

Accordingly, the locks are manned round the cIock and there is no charge for their use.

Broad directives are issued hy the Central Water Conservation Board; detailed instructions are sent to the operating staffby the Arnhem headquarters. In accordance with the scheme described in the foregoing pages, the instructions will usua11y he limited to the following points:

a. for Driel weir: maintaining the water level at the IJssel bifurcation at a given gauge level, depending on the runoff and requirements, so as to maintain the IJssel discharge planned;

h. for Amerongen and Hagestein weirs: to keep their respective head-waters at given levels (normally

+

6 mand

+

3 m A.G.D.respectively) and to adjust the water levels gradually when a rise or a fall is expected.

4.3. Cost

Expenditure on the project may be broken down into the following items: - acquisition of sites

- earth and river works - weirs and locks - housing - miscellaneous Total DiL 5.3 million DiL 51.0 million Dfl. 78.0 million Dfl. 1.2 million Dfl. 1.5 million Dfl. 137.0 million The other river reconstruction and adaption works referred to which were directly connected with the canalization scheme involved expenditure totalling Dfl. 25 million. All the designs were prepared hy the Water Control and Puhlic Works Department, who also supervised the actual work.

(18)

-s:<

.-.<-.~~----"

Phol0graphI. Aerial view of Hagestein weiT looking downSlream with lifted visor gates.

(19)

I

00

10.6

WEIR IN CLOSED POSITION

41.00

ELEVATION

WEIR IN OPEN PO$ITlON

IJ);.,/ MAX HEAOROOM

~~

+1

...

;

~_J

L.Ri.' 1.10

4I.o~

DOWNSTREAM

(20)

11.

The construction of the weir complexes

1. General

The preceding section explains why it is necessary to canalize the Lower Rhine and Lek.

The present section deals at some length with the hydraulic structures in concrete that will be needed, chief among them being the three weir and lock complexes (see Photograph 1,Hagestein).

First of all, there are a few general comments to make on the work.

The designs will have to meet requirements laid down by the rivers department. One of the principal requirements is that preferably there should be one opening only in the weir and that the opening should be wide enough to accommodate both upstream and downstream traffic; alternatively there should be two passages, one for upstream and one for downstream traffic, separated by a central pier, each passage having an interval width of 45-50 mand a vertical clearance below the raised gate of at least 9.10 m above the highest recorded water level (a stipulation which was obviously made by the Central Commission for Rhine Traffic at Strasbourg).

A study prepared by directie Sluizen en Stuwen (the Locks and Weirs Directorate), which will be responsible for designing and building these works, shows that a single passage would be very costly and would incur a substantial risk of vibration and operational unreliability.

Consequently, the only solutions considered are those featuring two ship passages. Since the designer has proposed the visor type of gate (about which more later) for closing the ship passage, and since this would not meet the requirements on vertical clearance at the sides, it has been decided to set the net span at 48 m, so that there will be 38 min the centre of the passage within which the stipulated headroom will be assured.

A further important requirement is a fine control opening with adequate capacity (100 cub.m. per second) for dealing with an average head.

ltmust be possible to adjust the weirs with sufficient accuracy to match the water drainage needs; very large gates were not thought suitable for this (though their level can be very precisely controlled).

For reasons of symmetry and to prevent erosion of the banks the designer has sited the fine control not at the sides but in the middle of the pier separating the two ship passages.

In dry periods the visor gates can then be lowered and left on the sill to facilitate the

(21)

-t DOWN STREM-I SECTION A-A

.

.

:i!~' G

v'-C---1U'.B ~ ~ 6ECTION B-B

Figure11. Cross-sectlans of pier and micro-adjustment valve (cylindrical gate valve).

B

(22)

PLAN OF LOCK

CROSS SECTION OF LOeK

~6EJ~~:=BER HEIGHT OFRISE=BO~]_2S+NA.P.

. _ - - - '

OOWNSTREAM LENGTH OF LoeK LoeK eAV LENGTH OF LoeK LoeK eHA..."_BE_" ---",,"-'.,,'---_ _---"'-'N.::CE~NTRALLOCKC:;:;";::.A"""8E"'" 112.~O

: . . - - - . --=E'-"FF==ECC'.'T1V~E==LE""NG",T"-"OF,-,L~OC",K.:c~''''20''''m --!

NDARO H.W=1.2S N.A.P NDARD l.W.::O.50· N.AP.

. LONGITUDINAL SECTION OF LOCK Figure 12. Plan with longitudinaJ and eross-seetion of loek.

This gave an indication of the required pier width, and this in turn governed the ultimate width ofthe river bed at the weir.

For the Hagestein weir this was 2 X 48

+

14= 110 metres. For the weirs at

Amerongen and Drie1 the width is slightly less, as the pier can be somewhat narrower in these weirs because there is no water turbine.

In all other respects the three weirs are practically identical. There may be slight differences in the superstructure due to differences in flood discharge.

All three locks have the same 18 m horizontal clearance, and are equipped with mitre gates in order to give unlimited headroom.

The locks have an intermediate bay to save water in periods of drought.

During periods of flood discharge the locks may be completely under water. To prevent scouring, baffies are fitted in the upstream bays (they can take the form of simple sliding doors), while a dividing wall between the weir and loek channels pre-vents cross currents.

(23)

i~~

I

I

I

1 I I

I

I I

I

: I .

~C-i-1

l~

I

Figure 13. Upstream loek bay and eurrent defleetor.

WING WALL.

~

(24)

LONGITUDINAL SECTION A - A DOWN STREAM ---.liA"" -

__-"Af-,

---, B~ QuT;U JfTu"BLM: ANOÇVltNO~IÇAC" L H ,

(25)

~SQ-2. Brief description of the three weir complexes

2.1. Hagestein complex

At Hagestein the weir and loek were built in a single excavation in the southern flood plain.

When the excavation had been filled in and the access channels dug, a low-topped dam was built in the old river. When the water level is very high the river water spi lIs over this dam, so the width of the winter bed is adequate.

As there is a deep pocket of sand on the site, the seepage path was lengthened mainly by incorporating a thick horizontal bottom covering. Since there might be a covering layer of clay peat over much of the surface, infiltration or drainage strips were provided upstream and downstream to prevent any disruption of the bed through sudden opening or closing.

The loek chamber is 225 m long; this seems relatively short, but since the weir is just above the mouth of the locks at Vreeswijk, vessels plying between Amsterdam and Rotterdam do not have to pass through the Hagestein loek.

The waiting berths are of steel sheet piling supported by a stiffener beam on piles. This gives great stability and has made it possible to build the second loek immediately alongside the first.

Further details are given in paragraph 3.

I

~RAlNA'G~__

I

~105EDE10'[TOM iNF1LTRAJION "" ÇlAY-PEATlAYER_

Figure 15. Closed floor of weir showing drainage system.

(26)

Figure 16.

13.50

11.25

1.55 gr~v~. Cross-section of approach.

AIR INLET

..' . . . ~-' . . . .' . -.~ S'iIFF~_NER:: .:.' .' / / HWL 25

(27)

2.2. Amerongen complex

At Amerongen the works are also on steel foundations and are located in the flood plain on the northern shore of the river. Since there is no water turbine generator, the pier here is only 12.5 metres wide.

In the fine control opening in the middle of the pier there is a cylindrical valve with an air tube behind the seating through which oxygen can be added to the water (as is also the case at DrieI).

As at Hagestein and Drie!, the waiting berths for ships on the upstream side are considerably shorter than those downstream; this is beeause more small vessels are expected to pass upstream (these are, without extra fuel, raised by about 9 m) than downstream, since the latter traflic goes along the Waal where it is helped by the eurrent. At Amerongen, as at Drie!, the loek chambers are 260 m long.

The waiting berths are of the same design as at Hagestein, except that the piling is of Vibro piles with a prestressed Diwidag bar as the tie rod.

. ". . . . . ,

..

.' . ' . . . ' ....-' ". . ., ... .,' . ' wee holes 2.20+ NAP. , sheet ilin

" r

,:,-,' .' , J,' " ',' , "

f;~e

sand 2.80- - -

-~~~

.. ':",'f'

• • I .

I:~'---I

,

,','l

(28)

2.3. Driel complex

At Driel the subsoil consists of layers of clay and sand washed up along the Veluwe. The clay is a preglacial, hard type; it was dredged away on the site of the works and replaced by sand.

The layers of sand underneath the abutments and piers were heavily compacted by deep vibration. Underneath the sills they were slightly vibrated; the sills were also weighted with lead slag concrete.

This very largely prevented uneven settling due to differing foundation pressures. Because of the small space between the confining embankments work on the weir proper started on the southern side.

The river was diverted; then the loek was built on the old river bed.

Since there may be same uneven settling in the loek, the joints have been made watertight by means of PVC-rubber sealing strips. In this it differs from the other locks. The entrance guides are also designed to suit local circumstances. They are sprung braking constructions made from steel tubes with linking sleepers, which can be moved without great expense. They will absorb 4 tm energy at each point of impact at normal stresses, i.e. they are suitable for ships of 2,000 tons.

Since there are no longer any glass-eels in this stretch of the river, there are no eel passages in the fish-ways.

Figure 19. Longitudinal section of excavation for foundations showing improved soil structure beneath foundations.

(29)

I

I

I

+- ---

I I _ _

---+

+---

I

::11

i

I I I I I1

I

I ::

I1

I

I I 11

I

:

i:

I1

I

! ::

11 I - 'SO+I 6'" 9 VAn l.'SO _ ,. L&'S. "0.

- -- ---rl

I . - ,

üo-I

Joint ,I "

---,

Figure 21. Joints betweenloek sectIOns.. L ft: Hagestem ande . Amerongen loeks, ngI . ht. Loek at Drie!..

(30)

J

m

j

m

j

275

j

....

t"-N

5ECTlON A-A

125 5.495+ BOlLARD

A~

WOODEN APRON REMOVED

In

t"-N

Figure 22. View and eross-section of approach to loek at Drie!.

tv

\0

A~

ELEVATION

2.50+

(31)

-3. Description of Hagestein weir complex

This weir differs in a number of respects fr om the types found elsewhere in the Netherlands. The gates are semicircular and have a free span of about 54 metres, the fish-ways have been changed into fish locks and there is a water turbine generator in the central pier.

3.1. Design of gates

The special shape of the gates sprang from a number of theories subscribed to by the designer, namely, that

a. if the gate took the shape of part of a cylinder with the water pressure on the "hollow" side, it would only have to withstand tensi1e loads, so it could be a light construction ;

b. if the bottom edge was rounded the water would flow out radiaI1y when the gate was only slightly raised and the hydraulically sound flow distribution would conse-quently make a light bed protection adequate even if only one gate was being used for drainage;

c. the resulting non-rigid structure of the gate and the curved drain aperture would preclude serious vibration since much of the gate would always be steadied by the mass ofwater behind it.

IN ONE FASE HEAVY VIBRATIONS WEAKENING

VIBRATIONS Figure 23. Diagram showing vibration of flat vertical-lift gate and of visor-type gate.

Apart from smaI1 disturbances due to a slight tendency of the gate to lift and the effect of the girders along the edges, the stresses set up in the plating are mainly dependent on the water pressure and the radius. With a span of 54 metres or a radius of 27 mand a gauge water pressure of 4.5 tons per sq .m., the stress set up in the plating is 0.45 X 2,700 = l,2l5kgpersq.cm.

/

d

30

Figure 24. Stresses in curved plate.

(32)

DOWN STREAM hinge q

pivot

UP STREAM R

Figure 25. Stress diagram of visor gate.

DOWN STREAM q R

pivot

UP STREAM

<

I

,

R

(33)

The plating is 8 mm thick, so the tensile stress is about 1,215 : 0.8 = 1,520 kg per sq.cm., which can be taken as very low indeed for an S.52 steel. Since the extent to which vibration is a hazard is not known, a safety margin of 600 kg per sq.cm. is included in the calculation.

There is a piano-hinge with rubber seal in the centre of the gate; this facilitates dismantling and helps to reduce temperature stresses.

Because of its shape and the method of lifting, this type of gate is called a "visor gate", since it is reminiscent of the visor on a mediaeval knight's helmet.

When the gate is down, itis subjected to tensile stresses only. During the raising operation, stresses are set up in the edge girders; they become less as the gate rises. In the raised position, the edge girders are subjected to compression stresses.

The shape is hydraulically so effective that the coarse-grained sandy bottom does not need protecting. There is na edge turbulence.

The level of the upper stretch of water must be adjusted by means of the visor gates whenever the discharge of the river exceeds 100 cub.m. per sec. (up to this value all the water passes through the fine-control system). Above 550 cub.m. per sec. the gates are fully open. The maximum head at this rate of discharge is 3.50 metres. The mini-mum vertical flow clearance is 15 cm.

In view of the flow characteristics of the Rhine, the gates will be in their partly-raised position for about four months of the year; it is therefore important that there should be no very strong vibration.

3.1.1. Hydraulic study

The Hydraulics Laboratory was responsible for the whole of the hydraulic study. To reproduce the flow phenomena in the prototype in a model it is necessary that for a constant flow pattern the various internal and external forces acting on a particIe of water should continue to act in the same proportions.

For this reason the Laboratory prepared the following appraisal, which was pre-pared by Ir. P. A. Kolkman.

The jol/owing terms are used in the equation Jor the dynamic balance oj a water particle: Acceleration Övx (övx öVx övx ) p~+p vx~+Vy~+vz~ ,etc. in which p= density of fluid v= velocity x, y and z = coordinates t

=

time 32

(34)

Pressure

8P ' h ' h h

8x - etc. In w iC P = P

+

p . g in which

p= local pressure

g = acceleration due to gravity

h= height of the point relative to a datum level Viscous shear stress

8,x 8,x .

kx=

-8;-

+

~ etc. WhiCh corresponds to

(

82vx 82vx 82Vx)

pv ~

+

-8y2-

+

8Z2

etc. Free fluid surface.

At the surface p = p atm. (constant)

8P 8h

-gx=

P.g.8X

Surface tension

(pgas - Pfluid) =

±

cr (

k

+

~2)

in which cr= surface tension

Rl, R2 = radii of curvature of surface

If alllengths are to be reduced by nL, we can determine the scale factor by intro-ducing the invariance of the relationship between the terms.

a. From the acceleration formula it follows that: nt

=

nL/nv

b. From a combination of the pressure and acceleration formulae it follows that:

np = np 'n~

c. From the viscous shear stress formula and the acceleration formulae it follows that: nv •nrjnv = 1

The Reynolds number (Re= vL/v) is constant.

d. From a combination of the free fluid surface and the acceleration formulae it follows that :

n~/ngnL= 1.

(35)

e. From the surface tension formula it follows that : np = nO'/nL, and so combined with the term (np = npn;)given in b. above:

n

p •nL . n;/nO' = 1. (

L 2 '

The Weber number We = p crv ) is constant.

The constancy ofthe Reynolds, Froude and Weber numbers provides the conditions for the velocity scale, while the pressure and time scales foIIow through the relation-ships a. and b. from the velocity scale chosen.

IJ the same gas or fluid is used in model and prototype alike, the conditionsfor velocity are always contradictory.

In fact,

np = nv= na = ng = 1

This means that the flow in al: 20model should be 20times faster according to the Reynolds scale, v20 times slower according to the Froude scale, and v20times faster according to the Weber scale.

The choice wil! depend upon the purpose of the study.

Since the water in the sea or in rivers has surface waves or is turbulent and since hydraulic engineering structures are seldom perfectly streamlined, the particles of water therein must always be in a state of violent acceIeration or deceleration. lt is found that viscosity and surface tension play a minor role in this compared with the forces of acceleration and gravity acting on a particIe (i.e. Re. and We. are very large). Even when there is a steady flow in large pipes or concrete irrigation channels the turbulence caused by the roughness of the waIIs is so great that the effect of viscosity is very slight.

This fact aIIows us some freedom not to incorporate the correct value of Re. in the model, provided the value we do incorporate in the model is sufficiently high.

There is ample information on this point in the literature on the subject. It need hardly be said that certain inaccuracies in the model determined in the laboratory are ;;lccepted for practical reasons.

ltfollows from the foregoing that so long as we do not go below the critical lower limit of Re. there can be a free choice of velocity scale in a model without a free fluid surface. If there is a free surface, the constancy of Fr. will determine the velocity scale. As a means of compensating in a model for too smaII a value of We. or Re., we might mention magnification of the vertical scale with free surface flow and the turbulence mesh to make the boundary layer turbulent more quickly. Obviously, both these methods prejudice the confoffilÎty of the flow pattern.

This completes our examination of the hydraulics side of the question.

(36)

CA K

J

o

J

-

OOr

Figure 27. Amplitude of vibration when subjected to periodic impulses.

The following observations concern the elastic properties of modeis.

The final vibration amplitude of a single mass spring system with periodic excitation is shown in the following diagram:

The shape of the curve is dependent solely on the damping. C = spring stiffness, M = mass, K = force, A = amplitude,

00 = angular frequency of excitation, O)r = angular frequency ofresonance. For reproduction in a flow model, it is necessary that nA = nL, and from this we get:

ncnL/nK = 1 (1)

The scale ofOOrmust also be equal to the scale of the excitation frequency (e.g. the

wave or turbulence frequency)

nW/nWr

=

1 (2)

The relative damping j. (damping/critical damping) must be the same in both prototype and model:

nj

=

1

Conditions(1) and (2) determine the mass scale: nM

=

ne/n?;;r = nK/nL . n?;;

(3)

(37)

Since during the vibration of a structure in fluid an apparent increase in mass occurs, the scale of the model mass and that of the water mass must satisfy these conditions.

For elastic models of compound structures condition (1) can be replaced by: nt= na/nE = nK/nrnE = 1

E

=

relative distortion, cr= material stress

E = modulus of elasticity For shearing, similarly,

nK/nfna= 1

(5)

(Sa) On combining(5) and (Sa) we get na = nE; this is in most cases automatically satisfied.

For the combination offluid with model, where there is flow without a free surface:

for the flow we found np = npn~ consequently

The spring stiffness of an elastic model follows from (1)

ncnL/nK= ncnL/npntn~ = nC/npnLn~ =

The Cauchy number ( Ca=

p~V2)

is constant. F or the frequency of excitation by flow or waves

nt = nL/nv or nw= nv/nL

In combination with(2)we get for the resonance frequency of the model: nLnWr/nv= 1

( (j)rL )

The Strouhal number - v - is therefore constant. For the mass scale we find, from (4), (6) and (8):

nM/npnl= 1

The mass number (

p~3

)is therefore constant.

(6)

(7)

(8)

(9)

The total mass, i.e.Mstruct.

+

Mwater

must in accordance with(9)be geometrically reduced as it were but must keep the same density with respect to the surroundingfluid.

This is already the case with the water mass vibrating with it, so that it is suftkient to haveMstruct.satisfy these conditions.

(38)

For mass spring systems itistherefore possible to obtain a correct model reproduction of the vibration phenomenon of each velocity by adjusting the spring stiffness, the mass ofthe model being independent ofthe velocity.

For compound structures it is preferabIe, when using the same fluid, to make the model from the same materials as the prototype structure. The mass will then be correct for all forms ofvibration.

ltfollows from (5) and (6) that, as nE= n p= 1,then:

(10)

This means that the prototype velocity must be used for the flow in the model. For the combination offluid with model with ajiow with afree surface:

As an extra condition we now introduce the invariance of the Froude number. This gives:

(11)

The stiffness of a model of mass spring systems fol1ows from the invariance of the Cauchy number.

For compound structures we must, according to (5) and (6), write: nf = npnlnUnlnE

This gives us nL/nE

=

1 We also have to satisfy

npstruct. = np

=

I

(12)

There is no such material for the conventional scales. In compound structures, however, the stiffness increases linearly with the plate thickness (with the exception of local bending stiffness of plates and massive girders), so the stiffness can be corrected by sacrificing the geometry. There is a practical preference for adjusting the model for too low an E and consequently for too large a plate thickness. Up to now plastic models have been employed, with nE::::; 60 compared with a steel prototype.

According to(12),this ought to amount to nL= 60, but this would make the models

so smal1 that the Reynolds number would preclude their use.

In our studies of the visor gates at Hagestein we used nL = 20, so that E was too smal1 by a factor of 3. This was compensated for by multiplying the plate thickness by 3. In view of the fact that the plastic material (Trovidur) used was 5-!- times lighter than steel, the 3-fold greater thickness of the plate still gave too light a model.

The correction for this was effected in such a way that the stiffness was unchanged. To do this, smalllead weights were applied at certain points, distributed as nearly as possible in proportion to the deficiency in mass.

(39)

The damping requirement that nj= 1 (3) naturally obtains at all times. The j may be the same in geometrical models made of the same material as the prototype, since j is to a large extent a material constant.

The damping of parts subject to friction, hinges and rubber seals is not automatically to scale. The damping caused by the fluid mayalso be out of scale. The damping will certainly be to scale if it is due to the drag of beams and the like in turbulent currents but not ifviscosity is a criterion (e.g. a plate vibrating in its own plane). The damping of hinges and the like often needs to be considered separately and the question as to whether the fluid damping is to scale must also be gone into.

The damping is a criterion when determining the equilibrium amplitude when there is resonance. As a rule, however, whenever resonance occurs the design needs to be changed to prevent it.

As long as the damping in the model is low enough, preferably lower than in the proto-type, the model wil! show whether or not resonance wil! occur.

The damping factor is important even ifthere is no resonance, since the response to non-periodic excitation resulting from the turbulent flow field also contains components of the resonance frequency, although their effect is less than those concomitant with resonance vibration. Damping is of minor importance in respect of the response to impact phenomena, since the maximum amplitude occurs shortly after impact and there can belittle dissipation of energy.

The damping inherent in the material is too high when plastic is used for the modeIs. On the other hand, when making check measurements at Hagestein it was found that the friction of other parts predominated, so the model as a whole was often even less damped than the prototype.

The distortion in elastically similar models can be measured directly by means of

expansion strips. Since ne= 1, the correct strain value can be read off direct. If the

material is excessively thin, the adhesive and waterproof covering may not affect its elasticity; for this reason, strain gauges are only used to a limited extent on modeIs.

3.1.2. Model studies on gates

On the basis of the foregoing, model studies were carried out on the Hagestein visor gates, and extensive check measurements were carried out on the prototype.

Briefly, themodel studiescomprised the following stages:

a. Vibration patterns and resonance frequencies were determined, using the elastically similar model.

As the model lacked rigidity in the horizontal plane, the minimum resonance frequency was very low indeed, viz. 1.3 cycles per second dry and 0.6 cycles per second when immersed.

(40)

b. Pressure fluctuations were measured on a rigid model of a gate section. The pressures generated all the frequencies between 0 to 10 cyles per second, so some vibration can always be expected. Variations in the shape of the lower edge had little effect on vibration.

c. Lower edge tests: using a model of a gate section (scale 1 : 6) suspended fr om springs, tests were carried out to find out whether resonance vibrations occur when there is horizontal or vertical movement at various resonance frequencies. There were none in the profile selected.

d. Tests on the elastically similar model.

Perforation of the bottom stiffener was found to reduce the vertical vibrations substantially.

Systematic readings with the gate at various heights and with various water levels showed no appreciable vibration amplitudes; the maximum was 7 mm for horizontal movement and 1.7 mm for vertical movement.

e. Scale tests on the model as described in c and a 20 : 1 scale model of this; the vibrations set up by currents and the damping effects of the water were compared.

Since the results of the tests described in d showed that there was a substantial margin of safety and since the results of the tests described in e did not suggest there would be any very great scale effects, the design is considered to be sufficiently safe.

There is some resonance in parts of the plating under certain circumstances; this can be overcome by raising or lowering the gate very slightly. Scarcely any measurable stresses are set up. This was not observed in the elastic model, since the components are much too stiff as a consequence of the excessive plate thickness.

Exhaustive experiments were carried out on the prototype to test the model tech-nique, the model being set up afresh to ensure that all the conditions obtaining when readings were taken were faithfully reproduced. The stiffness of the rubber side seals was tested separately under dynamic loading and the stiffness was reproduced in the model. Since the cables had not yet been fitted when the dry excitation tests were carried out, the gate was temporarily suspended by strips. This was a help when taking the check readings, because otherwise the elasticity of the cables would have had too great an effect and the conclusions regarding the model would have been less reliable. The horizontal tangential and the horizontal radial periodic excitation were compared.

The agreement in frequency in both the dry and the wet state is satisfactory. As a rule, the oscillation was greater in the model than in the prototype.

The effect of the water on the resonance frequencies was adequately reproduced in the model.

We also compared the figures for vertical excitation.

The excessive torsional stiffness of the model (due to extreme simplification of the shape) gives too high a resonance frequency. This was only to be expected. A

(41)

re-markable thing is the powerful damping effect of the water in the prototype; during the tests there were high-frequency vibrations in the plating which presumably absorbed a great deal of energy. The vibrations were also recorded during normal operating, and there was satisfactory agreement between the figures obtained fr om both model and prototype.

The study shows that the model technique used is reasonably reliable, as long as prior allowance is made for the difficulties arising from excessive material damping in the model and as long as a great deal of attention is paid to details snch as the elasticity and damping effect of the rubber seals, friction in and damping effect of hinges, elasticity in the cables.

The tests on the prototype show that the design of gate adopted is the best from the point ofview ofvibration.

Because of the extra stress allowance of about 600 kg per sq.cm., the structure was too heavy. The use of high-strength bolts, a/so for the work done in the factory, has also produced excessively heavy structures. In view of present-day welding techniques, the use of these bolts is justifiable only for work done on site.

3.2. The fishways 3.2.1. Remarks

Even before the Second World War a number ofweirs incorporating fishways were built in the River Maas in Holland.

As our knowledge of the biology of fishes was incomplete, the fishways were of the Denil or basin-ladder type; the argument was that "a fish is a fish".

Since then we have discovered that there is a basic difference between fish that travel very far upstream to spawn (such as trout and salmon) and the white fish found in tidal rivers. Salmon and the like are strong fish easily able to overcome differences in water level by 1eaping upwards to higher reaches.

Fish in tidal rivers are far less strongly developed, since they live in slow-fiowing waters. These "lazy" species are unable to negotiate a basin-ladder or Denil fishway. Consequently, the Fishery Inspectorate and the Water Control and Public Works Department have together developed a fishlock at Lith on the River Maas which raises fish enticed into the loek by a "lure current". This was so effective that the system has also been adopted for the Rhine canalization scheme.

The system operates in the following manner:

The loek has an upstream and a downstream gate. In the lock-chamber behind the upstream gate (which operates as an overspill) there is a chute with an overspill profile. Beneath the fioor of the loek are two "Iure current" conduits with diameters of 50 cm and 90 cm. Each conduit has a stopcock at the upstream end.

Fish pass through the loek in three stages, as follows:

The downstream gate is raised, the upstream overspill provides a moderate infiow

(42)

FISHPASS OF DENJL

SECTION AA

B~

SECTION BB

FISH

STEPS

Figure 28. Fish pass and fish steps.

afwater and the stopeoeks of the large and small eonduits (A and B respeetively) are opened. The strong lure eurrent from the large eonduit entiees the fish from the river away from the weir gates to the fishloek, while the lure eurrent from the small eonduit and that of the water from the transfer basin entiees the fish into the loek.

After a time the gate is suddenly closed (by letting it drop freely against a brake). The large eonduit stopcoek A remains open. As the small eonduit stopcoek B is closed the overspill gate drops, allowing the loek to fill.

Stopcoek B then opens, produeing a eountereurrent in the loek ehamber. Sinee the large eonduit stopcoek A remains open, there is also a lure eurrent passing through the loek passage from the upper pound. These two eurrents together attraet the fish into the upper ground. The idea of leaving the large eonduit stopcoek A open (also during the filling of the loek, i.e. with the gate closed) is to keep the lower lure eurrent flowing.

The overspill gate is closed eompletely when the fish have left the loek ehamber. Stopeoek B remains open and the loek ehamber is emptied by slowly raising the gate until it is wide open. The entire proeess is then repeated. The gates and stopcocks open and close automatically at set intervals.

(43)

lONGITUDINAL SECT/ON AA EEl TRANSPORTATION CHAtt~ll...:

HORIZONTAL 5ECTION NORTHERN ABUTMENT

DOWN STREAN

~-.

4S0+

~

I

i-=

TWIGS ~~ - """

- N.A.P.

---=±

_ -

_

---a •. "., '.

0'

RESTlNG BA51N ] .

k

h ~ . :". . ~I ~ ...

_-UP STREAM ~ -<-Ó\ A

lONGITUOINAl SEcnON BB FISHlOCK

(44)

3.2.2. Eel passages

Separate arrangements have to be made in the lower effiuents to allow the glass-eel (which is brought to the coasts of Europe from the Sargasso Sea by the Gulf Stream when it is a few years old, still transparent (henee the name) and about 10 cm long) to pass weirs on its journey upstream. These eels move close to the bank and can only cope with weak adverse currents. They are unable to get through the fishlocks, because

they are not yet strong enough to do so but they wil! be when they reach the uppermost weir complex at Driel; they wil! have grown by then and wil! be able to negotiate the fishlock there.

For this reason each abutment has been provided with an eel passage having its entrance and exit immediately next to the bank.It is basically a "climbing-channel" with a gradient of l-in-12 filled with year-old willow-twigs through which a slight current fiows. The elvers wriggle upwards through the twigs, arriving halfway up the passage and at the upper end in resting basins where they can gather fresh energy for the remainder of the climb upstream. They still have to pass through the upstream gate into the upper pound; there a straw basket is provided against the top gate for the purpose. Water is let into the basket, which contains straw, from the upstream pound via an overspill in the gate, and the young eels have to crawl vertically upwards through the straw until they are finally enticed into the upper pound by the lure current. The volume and velocity of the water fiowing through the basket and channel are set by raising or lowering the gate to suit the water level at the weir. This is done by a hand-operated winding mechanism.

Provision has to be made for renewing the straw and twigs in the eel passage. Wire netting on frames is placed over the upstream and downstream ends of the passage to keep predatory birds and crabs out. The upper end is shielded by the upper fioor ofthe abutment, so the fish too are weB protected against attacks from without.

There are perspex observation windows in the walls and underwater lamps attached to the opposite walls through which the operation of the fishway can be observed from a shaft alongside them.

Figure 29 and Figure 30. Cross-seetions of fish loek and eel pass.

(45)

3.3. Hydro-electric generating plant

When work on the plans for the weir complexes began in 1950, the question was studied as to whether it would pay to incorporate hydro-electric generating plant in them. The conclusion was that at Hagestein, where advantage could be taken of the ebb and flow below the weir, it would pay to instal a turbine with an intake capacity of 66 cub.m. per second and an annual output of 6 X 106kWh. Itwas found that, for

Amerongen and Driel, whose annual output would be 4 X 106 kWh, the capital

investment would not be justified.

In view of the very complicated conditions under which the turbine had to operate, only one supplier was negotiated with on a cost price basis and when the price had been agreed the turbine was ordered and designed.

A turbine of the Kaplan type was chosen for the hydro-electric power station in the central pier at Hagestein weir, because ebb and flow produce a constantly varying

head at this point.

In this type of turbine both the stator and the rotor blades are adjustable during operation. A cross-section of the turbine is shown in Figures 3la and b.

The turbine governor adjusts the stator and rotor blades to suit the constantly changing head.

To avoid having to construct deep foundations for the turbine discharge flume, the installation was designed on the siphoning principle, a vacuum pump being fitted to initiate and maintain the siphoning action.

The turbine, with a maximum output of 2,590 hp, rotates at 62.5 r.p.m.; it has a maximum intake capacity of 66 cub.m. per sec. and a head of 3.8 metres. Gears are used to step up the speed so that the generator operates at 750 r.p.m.

The generator (maximum output approx. 2,500 kVA) is connected directly to the 10 kV network of the "Provinciale Utrechtse Elektriciteits Mij." (PUEM) and is controlled for constant cos cP to allow for any variations in the mains voltage. An automatic voltage control adjusts the voltage during the running-up period, and after parallel switching functions together with the cos cPcontroller.

When the generator has been automatically coupled in parallel with the grid the entire installation comes under the control of a Rittmeyer controller. Water-level measuring points built close to the weir complex, both upstream and downstream, have floats with transducer equipment which measure the head.

In addition, there is Rittmeyer volume metering equipment in the pier to measure the amount of water flowing through the turbine. A receiver installation working in conjunction with the turbine governor ensures that the quantity of water flowing through is kept constant irrespective of the head at any particular time.

The turbine can only be put into operation if a number of essential conditions are met: the turbine governor oil circuit must be pressurized, there must be a vacuum in the siphon, and the temperature of the control-gea~oil and lubricating oil must be

(46)

high enough. There must also be suflicient oil between the surfaces of the Mitchell block, which acts as a bearing carrying the verticalload.

The plant comes into operation in the following manner. A servo motor sets the rotor blades in the starting position. A second servo motor linked to the control ring of the guide apparatus then opens the 24 stators, allowing water to flow through the turbine from the volute and the turbine and generator gather speed.

Mounted on the generator shaft is an oscillating-type generator with permanent magnets coupled electrically to the main turbine governor motor.

The governor has two major components, one of which reacts to the turbine's speed of rotation and the other to the gear ratio. There is also an oil accumulator containing control-circuit oil under air pressure provided by an electrically driven compressor. The oil in the accumulator and the servo motors referred to above can close both the stators and the turbine blades under all conditions.Ittakes about six seconds to close the stators.

To prevent water hammer, the control ring actuates two venting valves in the volute housing. Should the stators fail to close during a shut-down, two further vent valves, each fitted in a recess in the pier above the volute, will open to break the siphon va-cuum.

Mains water is pumped round a closed cooling circuit for the generator, gearbox and governor, and is itself cooled by river water in a heat exchanger. The river water inlet is fitted with a changeover filter which can be cleaned during operation. Two electric pumps are fitted in both the river and mains cooling water supply lines, each acting as a standby to the other. Should one ofthe pumps fail due to an electrical or mechanical fault, the other will automatically take over. A magnetic filter is incorporated in the lubricating oil system. An electrically driven grease pump automatically lubricates the plain bearing ofthe turbine shaft.

The temperature of the control-circuit oil and lubricating oil must be right before the turbine is started; should it be too low, electric heater elements will raise it. The temperature of all the bearings in the installation and of the generator cooling air is shown on thermometer dials in the control room. The thermometers are fitted with switches which automatically shut down the turbine if the bearings or cooling air reach inadmissibly high temperatures, and a relay drops an annunciator flap to indicate the location of the fault. In addition to these visual warnings, there is also an audible alarm which can be heard virtually throughout the weir complex. When a mechanical breakdown occurs, the load on the plant is reduced and the generator cut offfrom the grid; this minimizes the rise in turbine speed.

If an electrical breakdown occurs, the generator will cut out immediately, irrespec-tive of the level of the load, and in most cases even the generator rotor will be de-magnetized.

All the relays needed to protect the generator are fitted.Itwas decided to have the plant shut down automatically in the event of a breakdown, because the power plant would be minded by lock-keepers, who are not trained electrical engineers.

(47)

CROSS SECTION A - A

SECTION

at

4og+

Figure 31a. Cross-sections of pier showing "Kaplan" turbine.

46

(48)
(49)

The electricity for this and other purposes must come from a source wholly inde-pendent of the three-phase mains supply. Accordingly, it is obtained from an auto-matically charged set of accumulators giving 110 V.

The electricity supply for the operation of the weir and locks, which must be main-tained at all times, is in the event of a breakdown in the 10 kV supply taken over by a diesel standby generator unit, which will start up automatically within 7 seconds of any power failure. The standby unit is capable of supplying 70 kVA, or 56 kWat cos4>0.8. The mains voltage is then 220/380 V.

The standby unit switching is arranged so that the signal lights for shipping, the lighting at the weir complex and a group of units regarded as vita!, such as coolant pumps, oil pumps, the air compressor and greaser pump, will be switched over automaticalIy in the event of a breakdown.

The non-vital group is not connected to any emergency source of current; this group includes such units as the heater elements and the vacuum pump, which do not need to function when the turbine unit is being shut down.

The power-consuming groups used in weir and lock operation, such as those op-erating the weir and lock gates, cannot draw electricity from the standby generator unit until the turbine has stopped.

To reduce the turbine shut-down time the generator is fitted with a hydraulic brake which comes into operation when the shaft speed has dropped to about 30% of its nominal figure. The frequency-responsive braking relay is linked to the oscillating generator for the purpose.

The hydro-electric plant is remote controlled from a switch console in the central control building. The system has been automated as far as possible, so that after the start-up signal has been received by the turbine's own operating equipment (which then comes into action entirely automatically in a predetermined order) the turbine will run up of its own accord and the generator will be automatically switched into the grid.

The Rittmeyer equipment referred to then controls the load on the generator automatically, and the correct operation of the switches is indicated on the console by a panel oflights.

Both deliberate and emergency stoppage (to deal with breakdowns) is likewise automated. The installation can also be brought into operation "by hand" by a fully-qualified engineer. There is a contral panel behind the switch console on which the following items of control equipment are clearly laid out:

a. The Rittmeyer apparatus, which carries out the functions described above and also records the upstream and downstream water levels on chart-paper rolls; the water throughput, both that preset and that actually passed by the turbine, can also be read

off.

b. The automatic voltage contro!, which during operation acts in conjunction with c. The automatic cos 4> contra!, to keep the cos 4> at the 0.7 level required by the PUEM, and the reverse-feed cutout.

(50)

d. The automatic Oerlikonparal1el~switchingunil.

The electric cul-outs reCerrcd Lo are f1ued with individual annunciator flaps and arc houscd in ascparatc rclay panel.

The switch console also has a mimic circuit diagram of the 10 kV switching and distribmion point. hisatthis point th at the generator and thePUEM grid arc linkcd.

A transformer providing the turrent to opcratc the weir and locks is also shown. This 200 kVA transformer eonverts the 10 kV voltage into a 220/380 V supply for the weir and locks.

Besides the conventional voltmeters. am meters. wattmeters, etc. the turbine console also carries instruments10 show lhe position of the apcrlurc limiter, the stators and the head control roller.

Thc console also carries a rcvolution counter and the synchronizer instrument which indicates any discrcpancy in voltage. frequency and "phase position" between the P EM grid and the generator during the pamllcl-switching opcration.

Lastly, the console has panellights whieh indieate mechanical and electrical faults and show irnmediately in which group of annunciator relays the trouble is to be

found.

Cytaty

Powiązane dokumenty

2. 2% of newly manufactured processors have damaged cores. A laptop with a damaged core overheats; overheating also appears in 0.002% of laptops with fully functional cores. We

A researcher owning 3 umbrellas walks between his home and office, taking an umbrella with him (provided there is one within reach) if it rains (which happens with probability 1/5),

Mr Smith buys one randomly chosen lottery ticket every day (we assume that tickets from the two lotteries are equally numerous on all days); the choices on different days

An adsorption isotherm for a single gaseous adsorbate on a solid is the function which relates at constant temperature the amount of substance adsorbed at equilibrium to

An electron is in a one-dimensional trap with zero potential energy in the interior and infinite potential energy at

• “Nowy Sącz Experiment” in the end of 50’s and 60’s years and its influence on city's innovation,.. • 7 economical “tigers” – there is always somebody behind

Wydaje się, że znaczący wpływ na opisywane zjawiska patofizjologiczne może mieć także stwierdzana u alkoholików zwiększona proliferacja komórek neuro- endokrynnych w

Bismuth, Financial Sector Regulation and Financial Services Liberalization at the Crossroads: The Relevance of International Financial Standards in WTO Law, 'Journal of World