• Nie Znaleziono Wyników

Ontwerp van een meervoudig toepasbare bulkseperatie (summary)

N/A
N/A
Protected

Academic year: 2021

Share "Ontwerp van een meervoudig toepasbare bulkseperatie (summary)"

Copied!
1
0
0

Pełen tekst

(1)

Delft University of Technology

Faculty Mechanical, Maritime and Materials Engineering Transport Technology

D. van Vliet Ontwerp van een meervoudig toepasbare bulkseparatie. Masters thesis, Report 97.3.TT.4858, Transport Technology.

European Bulk Services is a stevedoring company active in the Port of Rotterdam. The main activity of the company is the transhipment of dry bulk solids of agricultural origin (agri bulk) and mineral origin. Frequently the holds of bulk carriers contain more than one type of product. In such cases the (different products are separated, using a separation, made of light weight plastic and other disposable materials. While removing the final layer of product on top of the separation, a large reduction of unloading capacity is experienced together with an increase in labour intensity. The decrease of unloading capacity is mainly due to the fact that all material on the separation has to be removed, with equipment developed for this purpose only, before the separation itself can be removed. To increase the capacity, a method has been suggested in which the separation is made of strong and reusable textile segments. The segment can than be used to remove the bulk residue by hoisting the separate segments with a grab crane.

The purpose of this project is to engineer such a separation. The main characteristics of the design process are, determining the loads on the

construction, the calculation of the structural strength of the materials used, and determining the method in which the separation is used. Loads have been measured during prototype testing. The structural strength has been calculated, using a finite element model of a detailed part of the construction. The research has led to a design that complies with the program of demands. The proposed segment has the dimensions 7.5x7.5 m and is fitted with an unloading opening underneath, for controlled unloading. The suspension consists of eight lifting loops sewn on the textile structure. Hoisting of the segments is achieved by using cables (length: 3.5 m), which are attached to the grab of a crane. The application of a material such as Geolon results in a cost price of a complete separation that does not form an obstacle for introduction. Furthermore, a well considered introduction is achieved by further testing of the segments followed by certification of the design. The introduction of the new method does not require supplementary investments and equipment.

Reports on Transport Engineering (in Dutch)

Cytaty

Powiązane dokumenty

0 oo It is well known that every A, can be represented as the operator algebra 1=1 acting in some Hilbert space Hi in such a way that there exist in each Hi unit

Scheiden  van  functies  kan  worden  toegepast  om  twee  belangrijke  redenen:  óf  om  de  productie  te  verhogen,  of  om  de  productiekosten  te 

In  order  to  successfully  research  the  dredging  process  of  the  trailing  suction  hopper  dredger,  when  separation  of  functions  is  applied  and  when 

Pracodawca moe take ograniczy koszty z tytuu zwikszonego wynagrodzenia pracownika przez to, e w zamian za czas przepracowany w godzinach nadliczbowych, pracodawca udzieli

Mocniej nie tyle do serca, co do gardła, wziął sprawę kolega G., który publicznie pokrzykiwał, że pora się samo- określić, więc on zapytuje, po której ja „stoję

33 Pieśń o Męce Pana Naszego Jezusa Chrystusa, którą się śpiewa przy wszystkich Stacjach.. kalwaryjskich, Wadowice

W rozdziale drugim autorka skoncentrowała się na przedstawieniu rozwoju struktur dekanalnych na Bracławszczyźnie oraz tamtejszej sieci parafi alnej.. Zre- konstruowała proces

Wznowienie następuje dopiero we wrześniu 1945 roku i kronika jest kontynuowana nieprzerwanie do roku 1971.. Należy odnotować, że w tym okresie (z wyjątkiem pierwszych dwóch lat)