Simulation tool for testing crane and berth assignment procedures in a dry bulk import terminal (summary)

N/A
N/A
Protected

Academic year: 2021

Share "Simulation tool for testing crane and berth assignment procedures in a dry bulk import terminal (summary)"

Copied!
1
0
0

Pełen tekst

(1)

Delft University of Technology

Faculty Mechanical, Maritime and Materials Engineering Transport Technology

C.J.D. Louw Simulation tool for testing crane and berth assignment procedures in a dry bulk import terminal Computer program, Report 2008.TEL.7251, Transport Engineering and Logistics.

As a result of the increased world trade, induced by global economic growth, shipping is one of the fastest growing economic sectors. These increasing volumes of traded commodities are handled by ports. A common commodity that is transported by sea is dry bulk which is transported by dry bulk carriers. These ships are unloaded at dry bulk import terminals. Global competition between these terminals leads to an increasing focus on cost control. Efficiency improvements are required to cope with the increasing volumes of dry bulk.

This report describes the design of a simulation tool that explores possibilities of increasing the performance of a dry bulk import terminal with the existing infrastructure and handling equipment. The scope of the research is the ship waiting area and the quayside operations. A simulation model is designed to simulate the terminal operations based on user input and generate results that allow the effect of this input to be assessed.

In the terminal ships are assigned to a berth and cranes are assigned to a ship. The assignment procedures is use today are straightforward. The effect of these assignment procedures on the performance of the terminal will be determined by implementing alternative assignment procedures in the simulation model. This performance is measured by the key performance indicator, the average ship waiting time.

The simulation model was built and run. It was used to compare alternative procedures for berth and crane assignment to the assignment procedures that are currently used. The results show that the KPI is negatively influenced by implementing a dynamic crane assignment procedure, a procedure in which cranes are constantly being assigned to the ship at which they are needed most. The model revealed that the extra productivity achieved while actually unloading does not compensate for the time lost to travelling, resulting in a lower average crane productivity.

The alternative procedure for berth assignment, however, shows an improvement of 12.5% of the KPI compared to the current assignment procedure, based on the average of the generated results. The standard deviation of the generated results is too large, however, to accredit this improvement to the alternative assignment procedure.

Reports on Transport Engineering and Logistics (in Dutch)

Cytaty

Powiązane dokumenty

The works of the 2010 campaign were conducted in two places: the defensive trench was cleaned; the residen- tial buildings and defensive structures along the western limit of the

Foucaulta heterotopie kryzysu (np. miejsca uprzywilejowane, święte lub zakazane) oraz heterotopie dewiacji, w których umieszczane są jednostki uznane za odbiegające od

In fact, his collected works (Carroll, 1956) contain only one article devoted to the subject with only one specific explanation of what the term meant to its author.

Naast het toevoegen van de genoemde functionaliteiten kan het model ook worden gevalideerd aan de hand van real-life data door het simuleren van een bestaande bulk terminal..

A generic model that simulates bulk terminal operations has been developed, verified and validated with rules of thumb.. The basis of the simulation has been implemented and

Spillage and accidental releases in dry bulk materials handling industry not only produce the materials losses, but also are the source of potential hazardous

De onderzoeksvraag zal daarom ook zijn: “Welke transportmiddelen voor bulkgoederen zijn beschikbaar om bulk goederen te transporteren binnen of buiten een bulkhaven

Given the current terminal configuration and capacities the average ship waiting time would increase from 36.6 hours in 2007 to 129 hours in 2015.. This is unacceptable and may lead