Design of an ultra deep-water cdrillship
with crude oil storage capacity type II
t
It Delft report nr. OvS 98/10
I
Design of
an ultra deep-water drillshipi
with crude oil storage capacity
Till, Delft
Type 2
--
-a
GUSTO
TU Delft, Mar'itieme Techniek
Supervisor: Jr. H. Boonstra
Professor: Prof. Ir. A. Aalbers
Report nr. OvS .98/10
Schiedam, 1998
mks
TU Delft
Design of an ultra deep-water drillship
with crude oil storage capacity
TYPE II
ii
M. Spilker
E.F.J. van Leeuwen
IHC Gusto Engineering BY
Supervisor: Jr. J. Lusthof
-7
GUSTO
Preface
This report forms part of our graduation work at TU Delft, Maritieme Techniek. The
entire work is performed by order of IHC Gusto Engineering BV.
This report contains a design study of a modern drillship.
We acknowledge the many engineers at Gusto Engineering, particularly those of the
naval architectural design department for their enthusiastic support. We clearly
wouldn't have come so far without them. Much credit goes to Jr. Boonstra from Delft
University of technology for running the offshore department at the faculty where
offshore belongs: Maritieme Techniek!
Schiedam, June 25 1998
E.F.J. van Leeuwen
M. Spilker
Introduction
As a response to the huge demand for deep-water drillships, this report contains the
design of a DP drillship with storage capacity.
Special attention was paid to the logistics of pipes and riser joints. The vessel is
equipped with two box-type drilling masts. One is dedicated to make hole, the other
one can be used to assemble joints.
This ship has a working name Drilling mast.
In chapter one some design considerations are given, accompanied by a rough
description of lay out and performances. In the other chapters all relevant aspects of
the design, such as stability, DP-system and hull strength are discussed.
The design is based on specifications formulated by IHC Gusto Engineering By and
TU Delft. Those requirements can be found on the following pages.
GUSTO
ENGINEERING
Order
Fax no
Date
Page
:6204
4-Jun-98
2
De afstudeerders zullen ieder afzonderlijk een dynamisch gepositioneerd diep water boorschip
met olie opslag capaciteit ontwerpen met inachtneming van de relevante gedeeltes van het
cursuswerk.
Het ontwerp zal de volgende scheepsbouwkundige aspecten omvatten:
Ontwerp aspecten:
Weerstand en voortstuwing
Electrisch vermogen
Downtime (vereenvoudigd)
Grootspant
Veiligheid
Bouwprijs berekening
Omgeving condities
Waterdiepte
Boordiepte
single line diagram
elektrische balans
scheepsbewegingen
indeling / lay-out
De te ontwerpen schepen moeten voldoen aan de volgende eisen:
Gemeenschappelfike ontwerpeisen:
Klassificatie
Operationeel gebied
DNV
DP notatie Dynpos AUTRO
Wereldwijd, nadruk op:
GOM
Brazilie
West-Afrika
Max. drilling
Hs
6.0 m
Tp
10-13 sec
V,nd
25.0 m/sec
Vcurrent 1.1 m/sec
Stand-By (Riser disconnected)
Hs
10.0 m
Tp
15-18 sec
Vwind30.0 m/sec
Vcurrent 1.1 m/sec
Transit, wereldwijd
10.000 ft
30.000 ft onder rotary
Stabil iteit berekening
intact
lek
Langsscheepse sterkte
Dynamisch postioneren
thruster lay-out
omgevingskrachten:
wind
stroming
golven
GUSTO
ENGINEERING
Order
Fax no.
Date
Page
3
Afzonderlijke ontwerpeisen:
Schip 1
Derrick
conventioneel (54' x 54' x 190')
hookload 726 t
Vrij dek opperylak
500 m2
Bij het ontwerp van schip 1 zal speciale aandacht besteedt worden aan een minimale
hoofdafmetingen vergroting ten gevolge van de vrije dekoppervlak eis.
Schip 2
Derrick
nieuw ontwerp, by. Huisman
ltrec Dual Mast
hookload 726 t
Vrij dek oppervlak
geen eis
Bij het ontwerp van schip 2 zal speciale aandacht besteedt worden aan de logistiek m.b.t.
riser, en drillpipe handling en opslag.
Crude Oil
100.000 bbls
Brine
2 x 700 m3
Mud
1750 m3totaal
Silo's
12 x 60 m3
Base Oil
300 m3
Drilling Water2000 m3
Bulk (zakken)
400 t
Risers, tubulars, casing, drillpipes volgens
water- en boordiepte
Setback
-
650 t
Riser tensioning
8 x 2 tensioners, totaal 1162 t
.
Crude Oil Productie
-
20.000 bbls/dag
Crude overslag
stern offloading
Accommodatie
-
150 man
min_ 12.5 kn, proeftocht
Opslag capaciteit
Consumables voor 90 dagen operatie
Scheepssnelheid
TABLE OF CONTENTS
1 Design considerations
3
1.1 Principal dimensions
3
1.2 Hul!form
3
1.3 General arrangement
4
1.3.1 Lay-out
4
1.3.2 DP system
4
1.3.3 Accommodation
51.3.4 Production facilities
51.3.5 Engine rooms
51.3.6 Deck cranes
51.3.7 volumes
51.4 Drilling equipment and logistics
6
2 Intact stability
7
2.1 Introduction
7
2.2 Stability requirements
7
2.3 Loading conditions
8
2.3.1 Summary of loading conditions
9
2.4 Wind heeling moment curves
9
2.4.1 General
9
2.4.2 Calculation of wind heeling moment curves
9
2.4.3 Results
102.5 Results of intact stability calculations
10
3 Damage stability
11
3.1 Requirements
11
3.2 Results
12
4 Resistance and propulsion
15
4.1 General
15
4.2 Resistance
15
4.3 Thrusters for main propulsion and DP
15
4.4 Results
15
5 DP Station keeping
15
5.1 DP-requirements
15
5.2 Thruster system
15
5.3 Environmental forces
16
5.3.1 Wave drift forces
16
5.3.2 Current forces
17
5.3.3 Wind forces
185.3.4 Riser force
19TYPE H
15.4 Thruster forces and consumed power
19
5.4.1 General
19
5.4.2 Environmental conditions
19
5.4.3 Intact thruster system
70
5.4.4 DYNPOS AUTR failure
5.4.5 DYNPOS AUTRO failure
20
5.4.6 Total power balance
21
6 Power generation and distribution system
22
6.1 Power generation
22
6.2 Power distribution system
22
6.3 Load balance
23
7 Down time
24
7.1 Motions
24
7.2 Downtime
25
8 Hull strength
26
8.1 Loadings
26
8.2 Midship section
26
8.3 Results
27
8.3.1 Material
27
9 Hull weight
28
10 Building price
30
Appendix
31
TYPE II
2
DRILLING MAST
20
1 Design considerations
1.1 Principal dimensions
The principal dimensions are determined by using a concept exploration model. A full
description of this model can be found in report "Design aspects of an ultra
deep-water drillship with storage capacity". By selecting a large breadth, possible future
modifications of the vessel are accounted for in ways of stability.
This leads to the following main dimensions:
1.2 Hul !form
The following choices have been made regarding the hullform:
Large midship section to reduce fabrication costs.
Pram-form aftship, which will provide a good flow to the main propulsion
thrusters.
V-form foreship to obtain good motion characteristics.
Wide cylindrical bow to accommodate the fore thruster.
appendages:
Scheg to increase directional stability and to ease dry-docking of the vessel.
Bilge keels to restrict roll motion.
On the following pages a body plan and a lines plan can be found.
TYPE II
3
DRILLING MAST
Length overall
202,0 m
Length between perpendiculars
188,8 m
Breadth
35,6 m
Depth at side
17,6m
Design draft
9,0 m
Displacement
48.000 tnj
drilling mast
FL 0
5.0
-drilling mast
0. 0
5.
In
10.0
is. 0
4
a
2
4
6
Ilan deck Ical MI et
Lnos
pa
14 15 1.6 17 18 19 2 C,Principal dimensions
Length between perpendiculars188.8 Length overall 202.0 no Breadth 35.6 m Depth 11.6 m Draught 'ranter 8 re Lb at transit draught 0.78 21.1m 7 8
9
10 11 12 13 31.3 General arrangement
1.3.1 Lay-out
For 'drawings of the general arrangement, reference is made to appendix 1 and
drawing nr. 6204.0001.501
6204.0001.503.
As drilling is the main activity of the vessel, positioning of all' drilling equipment has
been given first priority. Short lines and free access to the drilling area benefits
to
high drilling efficiency. All piping is stored above main deck, in front of the drillfloor.
'Consequently, the moonpool is situated relatively far aft. Below deck level, two crude.
al tanks occupy the space between the drilling area and the accommodation
area..
These tanks have a total capacity of over 100.000 bbls. For reasons of safety, the
accommodation is placed at the fore ship, the power generation set, production
module and ground flare are placed downwind of the drilling, area.
Drilling section
Accommodation
Production
platform
Pratioratimi
ir.uranionnoil
rr
VA
Power generation
Crude oil storage
113.2 DP system
The vessel will he dynamically positioned by means of two azimuthing thrusters at
the stern and four azimuthing retractable thrusters below keelplane level.
All thrusters'
,are installed in containerised units (appendix 1) with a retraction system to retract
'them above waterline level or even main deck level for major overhaul.
The deck
above the thrusters has been kept free.
The DP system fulfils DNV DYNPOS AUTRO requirements.
A 'complete redundant
system for power generation, power distribution', controls and thrust generation is
applied.
TYPE II
DRILLING MAST
1.3.3 Accommodation
The accommodation block is designed to quarter a total of 150 persons. The cabins
are divided over six decks. The most upper deck accommodates the navigational
bridge. Furthermore, two decks are in use for supporting services and equipment, such
as: mess room, offices, stores, galley, recreation room, laundry, etc.
The accommodation will be situated in the foreship just aft of the collision bulkhead.
The length of the accommodation block is 24m, the maximum breadth 26m.
1.3.4 Production facilities
The production facilities, intended to perform extended well tests and early
production, will be accommodated on a raised platform on top of the main deck, near
the stern. The dimensions of the platform are: 20m x 25m. It is designed for a
throughput of up to 20.000 bbls/day. At this flowrate, the vessel is able to produce
five days uninterrupted, before offloading.
The production platform is able to cover the following functions:
Separation of crude oil, produced water and gas.
Treatment of oily water to satisfy the applicable code requirements for dumping.
Export metering.
1.3.5 Engine rooms
The vessel has two completely separated engine rooms, to satisfy DYNPOS-AUTRO
requirements. Each engine room contains 4 generator sets of 5200 kW each
(alternator output at MCR).
1.3.6 Deck cranes
Three pedestal cranes will be installed on the vessel on main deck level to load,
unload and handle drillpipes, casing, risers or other weights. The capacity of all three
cranes is 20 ton at 35 m, or 75 ton at 25,5 m.
1.3. 7 volumes
TYPE II
5
DRILLING MAST
Volume (m')
Mud
2.000
Brine
1.400
Drilling water
2.300
Base oil
400
MDO
4.600
Crude
1.8068
S loptank
1.025
Potable water
1.095
water ballast
17.000
-'1.4 Drilling equipment and logistics
The layout of the drilling section is optimised for ultra deep-water applications. For
this purpose, two mast-type drilling derricks' are installed just behind the drillfloor.
The main mast, which is located at centerline, is suitable to perform all operations of
a
conventional drilling derrick. The rotational action will be provided by a topdrive.
The auxiliary mast, which is located 6,5 m. starboard of the main mast, can be used to
remove operations out of the critical path, which reduces completion time
considerably. Examples of such operations are:
Building up casing assemblies
Preparing riser joints
Making up bottom hole assembly
Another feature that will speed up the drilling process, is the use of drillpipe cassettes.
One cassette can hold 40 stands of 5- drillpipe. All drillpipes can be stored in triples.
Furthermore, the entire cassette can he lifted into the setback area. Consequently 120
pieces of 5" drillpipe are handled in one action, rather than in 120 actions, not to
mention the uncalled-for screwing and unscrewing. An impression of such a cassette
is given in figure 1.1.
Figure 1.1
Drillpipe cassette
All pipe handling will be taken care of by means of overhead
cranes and dragways.
The overhead cranes pick up the pipes, riser joints, casing and cassettes from their
horizontal racks and lay them down onto either the main mast dragway,
or the
auxiliary mast dragway. This system provides high operability with regard to ship
motions. Overview pictures of the pipe area can be found on the next
pages.
Design specifications as from Huisman ltrec's mast design.
TYPE II
6
Pipe rack capacity
Pipe deck layout
Drillpipe cassettes
8 *
drillpipe
3 * 5" landing string
4 * 3" workover
IV workover riser
07" completion riser
Casing 30"
200 in
Casing 20-
800 in
Casing 13"318
2000 m
Casing 9"5/8
3500 m
Drillpipe 5"
9000 m
Drillpipe 5" landing string
3000 m
Drillpipe 3" workover
9000 m
Drillcollars 7-
1000 m
Riser 10" workover
3000 m
Riser 7" completion
3000 m
Free space
2000 m (7"equiv.)
Free pipe rack
flFree pipe rack
Drillcollars
20" casing
9"5/8 casing
13"318 casing
30" casing
5"
IIt
rittent/
-
,#1
rg
2 Intact stability
2.1 Introduction
The intact stability of the vessel is investigated for seven relevant loading conditions.
Three fundamentally different operations can be recognised:
Transit operation
Drilling mode
Testing mode
Furthermore, a loading condition is defined to examine the stability characteristics
during survival conditions.
2.2 Stability requirements
The applicable stability criteria of the vessel have been summarised below. The
criteria are as per the DNV Rules for classification of Steel ships, DNV Rules for
Mobile Offshore Units and the IMO MODU CODE.
The applicable stability criteria are:
I.
The maximum righting arm should occur at an angle of heel preferably exceeding
300 but not less than 25°.
2. The righting lever GZ should be at least 0,20 m at an angle of heel equal to or
greater than 30'.
3.
The area under the righting lever curve (GZ) up to an angle of heel of 30° should
not be less than 0,055 mrad.
The area under the righting lever curve (GZ)up to an angle of heel of 40° should
not be less than 0,090 mrad. or the angle of flooding Of if this angle is less than
40°
The area under the righting lever curve (GZ) between the angles of heel of 30° and
40° or between 30° and Of if this angle is less than 40°, should not be less than
0,030 mrad.
The initial metacentric height GM° should not be less than 0,15 m.
The area under the righting lever curve (GZ) to the second intercept or
dovvnflooding angle, whichever is less, should be not less than 40% in excess of
the area under the wind heeling curve to the same limiting angle.
The range of the righting lever curve (GZ) should be at least 30°.
The angle of second intercept between wind heeling lever and righting lever
should be at least 30°.
TYPE II
DRILLING MAST
2.3 Loading conditions
Relevant loading cases are drawn from a typical well program. The following stages
can be recognised:
Move vessel on to location
Drill 36" hole to 1.000 ft below seabed
Run & cement 30" casing
Drill 26" hole to 2.000 ft below seabed
Run & cement 20" casing
Install 18-3/4 BOP and riser
Drill 16" hole to 9.000 ft below seabed
Run & cement 13"318 casing
Drill 12"1/4 hole to 15.000 ft below seabed
Run & cement 9"5/8 casing
Drill 8"1/2 hole to 20.000 ft below seabed
Run & cement 7- liner
Disconnect BOP and riser
Run X-mas tree & 7" completion riser
Well testing
Plug & suspend well
Sailing home
Emergency disconnect LMRP during drilling or test
The following loading cases are defined:
TYPE II
DRILLING MAST
Condition
Well program stage
1
Sailing 90% consumables
12
Sailing 10% consumables
Drilling, BOP connected, 90% consumables
7- 17
4
Drilling, BOP connected, 10% consumables
7 _ 17
5
Testing 90% consumables, 98% crude storage
13,14,15
6
Testing 50% consumables, 50% crude storage
13,14,15
7
Testing 10% consuMables, 98% crude storage
13,14,15
8
Survival condition, 10% consumables
18
3..
'9.
a17..
2.3.1 Summary of loading conditions
In all loading conditions taking in ballast water has minimised the trim of the vessel.
2.4 Wind heeling moment curves
2.4.1 General
The wind heeling moment curves are based on the guidelines presented in the IMO
MODU Code and DNV Rules for Mobile Offshore Units (part3, ch.2, sec.6).
In the guidelines two wind conditions are defined for intact stability. For offshore
service conditions a minimum wind velocity of ve = 36 m/s should be applied, and a
minimum velocity of vc = 51,5 m/s is defined for severe storm conditions. For loading
condition 1 to 7 (sailing, drilling, testing) the wind velocity of 36 m/s is used and for
survival conditions (cond.8) the wind velocity of 51.5 m/s is used.
2.4.2 Calculation
of
wind heeling moment curves
The wind heeling moment curves as required by the rules have to be transformed in
such a manner so that they can be implemented in PIAS.
The wind heeling moments in PIAS are based on the wind contour of the vessel.
Because the only input required for the calculations is the windpressure, this value has
been adjusted for the shape and height coefficient to obtain the wind heeling moments
defined by the Rules for the various sections. In appendix 2 the windpressures at the
different levels for the different conditions used in the stability calculations are
presented.
For the various draughts formally the change of the height coefficient has to be taken
into account. PIAS takes the influence of the change of the area for the hull for the
different draught into account but neglects the change of the height coefficient. The
deviations due to this method are very small and neglected. At smaller draughts the
wind heeling moment will be calculated a bit too small and for larger draughts a bit
too high.
The calculation of the heeling moments can be found in appendix 2.
TYPE
DRILLING MAST
Loading condition
12
3
4
5
6
7
8
Displacement (t)
44725
35797
47794
40908
54034
51454
48641
36221
Draught (m)
8,23
6,78
8,72
7,61
9,74
9,31
8,87
6,85
Trim (m)
-0,43
-0,04
-0,70
-0,53
0,91
0,03
-0,04
-0,19
VCG (m)
12,98
13,91
11,85
12,51
12,58
11,52
13,31
13,75
LCG (m)
95,75
97,76
94,88
96,00
97,06
95,82
96,03
97,37
GMsolid (m)
5,10
6,10
5,78
6,28
4,26
5,61
4,17
6,151
GM' (m)
3,99
3,97
4,35
4,24
2,37
3,15
2,12
4,455
' "2.4.3 Results
The wind heeling moments, as calculated according to MODU code and DNV Rules.
are translated into wind pressures for the contour as defined in PIAS.
Wind pressures for PIAS
2.5 Results of intact stability calculations
All loading conditions comply with the stability criteria as stated in § 2.2.
A summary of the stability calculations can be found in appendix 2.
TYPE II
10
DRILLING MAST
Moment (kNm)
Displacement (t)
Lever (m)
V = 36 m/s
82.937
43.243
0,195
V = 51,5 m/s
169.729
43.243
0,400
V = 25,8 m/s
42.597
43.243
0,100
Pressure (kg/in-')
Elevation (m)
V= 36 m/s
V = 51,5 m/s
V = 25,8 m/s
0-15
128
268
67
15 - 30
145
292
73
30 - 45
160
320
80
45 - 60
170
340
85
60 - 75
180
360
90
75 - 90
190
380
95
90 - 105
200
400
100
Attained value per loading condition
rit
Req.
12
3
4
5
6
7
8
125,0
33,7
29,7
34,5
33,3
32,9
33,5
32,1
30,9
2
0,20
2,52
2,01
2,75
2,49
1,73
2,16
1,65
2,29
3
0,055
0,621
0,579
0,672
0.643
0.402
0,510
0,375
0,648
4
0,090
1,060
0,899
1,159
1.073
0,691
0,883
0,641
1,026
5
0,030
0,439
0,320
0,488
0,429
0,290
0,373
0,266
0,378
6
0,15
3,99
3;97
4,35
4,24
2,37
3,15
2,12
4,46
7
1,4
7,8
4,7
8.1
6,8
6.4
7,9
5,2
2,6
8
30,0
61,4
53,3
65,4
60,0
55,0
59,4
52,1
56,5
9
30,0
60,8
52,3
64,9
59,3
54,3
58,8
51,4
54,5
,--3 Damage stability
3.1 Requirements
Regarding the fact that the vessel is subdivided in many small compartments, no
difficulties are expected in meeting the damage stability criteria. Nevertheless, the
most critical damage cases will be examined.
IMO MODU Code regulations are to be satisfied for all loading conditions, MARPOL
regulations only apply to conditions with oil in cargo tanks (conditions 5,6 and 7)
IMO MODU Code
Requirements:
The metacentric height in the flooded position is positive.
The area under the righting moment curve shall be at least equal to the area under
the wind moment curve up to the second intercept of the curves.
The extent of damage to be applied is the flooding of any one compartment.
The wind moment curve should be based on a wind velocity of 25,8 m/s.
MARPOL
Requirements:
In flooded condition the angle of inclination < 300
In flooded condition the righting lever has at least a range of 20° beyond the
position of equilibrium in association with a maximum residual lever of at least
0,1 m within the 20° range.
The area under the curve within this range shall not be less than 0,0175 mrad.
Longitudinal extent of damage:
10,97 m
Transverse extent of damage:
7,12 m
Vertical extent from baseline upward without limit.
The wind moment curve should be based on a wind velocity of 25,8 m/s.
TYPE II
113.2 Results
For the requirements as stated in § 3.1
,the maximum allowable VCG' is calculated at
several drafts. The outcomes are represented in figure 3.1. The maximum allowable
VCG' for the individual damage cases can be found in appendix 3.
Maximum allowable VCG'
Figure 3.1
Maximum allowable VCG'
The characteristics of the loading conditions that were used for the intact stability
calculations are plotted in this graph. It becomes clear that all requirements are
satisfied. As a reminder, a summary of loading conditions is given underneath.
TYPE II
12
DRILLING MAST
Condition
1
Sailing 90% consumables
2
Sailing 10% consumables
Drilling, BOP connected, 90% consumables
4
Drilling, BOP connected, 10% consumables
5
Testing 90% consumables, 98% crude storage
6
Testing 50% consumables, 50% crude storage
7
Testing 10% consumables, 98% crude storage
8
Survival condition, 10% consumables
24 22 20 18 E9
>
16 14 12 108e
4
1IMO MOD U C ode
7
3.
56
MAR P DL
4 5 6 7 8 9 10 11 12Intact draft lm I
3
4 Resistance and propu Ision
4.1 General
The propulsion consists of two azimuthing thrusters above keel level at the stem. For
the sailing condition a transit speed of 12,5 knots is considered. This transit speed is
regarded as a trial speed.
4.2 Resistance
The resistance is calculated according to Holtrop and Mennen
"A statistical Re-analysis of Resistance and Propulsion on
Data". Ordinary moonpool designs have a great impact on the
overall resistance. Model tests at MARIN showed that
alternative moonpool designs could reduce the added resistance
due to the moonpool by as much as 25%. For this vessel an
alternative moonpool is selected with a wedge on the upstream
side and a cut-out on the downstream side of it. According to
MARIN model tests on ships with similar thruster and
moonpool configurations, a resistance increase of 52% of the
bare hull resistance is estimated (12% due to the moonpool and
40% due to thruster headboxes).
Ordinary moonpool
Alternative moonpool
4.3 Thrusters for main propulsion and DP
For the two main propulsion/DP thrusters at the aft LIPS fixed pitch thrusters type
FS3500 are selected.
Technical data:
MCR 5000 kW at 600rpm
Prop. diam. 3500nun in nozzle
w = 0,15
Design speed 7 knots
Thrust at bollard pull 790IN
TYPE II
13
4.4 Results
For five drafts the resistance is calculated and the main propulsion azimuthing
thrusters are selected. In the following figure the relation between required and
delivered thrust is shown. In trial condition the draught will be approximately 9m
(loading condition: sailing, 90% consumables).The output of the resistance
calculation can be found in appendix 4.
9
10
ill
L213
14
15
V(1{4
t=6m
sit=7m
t=8m
--x t=9m
t=l0m
2 x 5MIN ithrusL
TYPE II
414,DRILLING MAST
1400
1200
80001
800
600
400
200
5 DP Station keeping
5.1 DP-requirements
For the assignment of DYNPOS-AUTRO notation, the following general
requirements are to be complied with:
An automatic positioning system with redundancy in technical design and physical
arrangement. This is to compensate for incidents of fire and flooding in addition to
technical failures.
This leads to:
Installation of an independently operating automatic and manual control system
Redundancy of position reference systems and sensors
Redundancy of thrusters and power generating- and distribution systems
5.2 Thruster system
The vessel will be equipped with the following thruster layout:
This system will secure maintenance of position and allows the vessel to keep its
heading in a range of plus or minus 400 around the optimum heading, at the worst
scenario.
The power generation system consists of two separate engine rooms. Each engine
room delivers 17,7 MW at 85% MCR.
TYPE II
DRILLING MAST
Power
(kW)
Thrust
(kN)
2 azimuthing thrusters for DP and main propulsion (1 & 2)
5000
790
4 retractable azimuthing thrusters below keelplane (3, 4, 5, 6)
3300
590
T4
T6
,T5
T1
T3
T,
5.3 Environmental forces
The environmental forces acting on the vessel during DP operations consist of:
Wave drift forces
Current forces
Wind forces
Riser forces
5.3.1 Wave drift forces
The wave drift forces are calculated using Gusto's computer program
FACET-DRIFT, a wave drift program based on a pressure integration technique. The panel
model of the vessel is presented in figure 5.1.
Figure 5.1
Panel model for calculation of drift & current forces
TYPE II
16
53.2 Current forces
The current forces acting on the vessel are calculated using Gusto's computer
program CURRENT. This program determines the flat plate friction resistance and
the pressure resistance of an arbitrary hull-shape. The program was validated against
model-test experiments with large tankers.
The same pallet model was used as for the calculation of drift forces (see figure 5.1).
Results for a current of l' mis
,C n tiosces,F LON), 1019 MO san 35,kNI 200,
OM*
Ulf
avow
26011111111.11nrii iiTAwn,00
250 **r Al
vt41
10 0 00 240 a Current forces Fy (kN) f-loimor = 161 3 kN 20AUS
210Miss
60 140 220 70 100 30 10 50 ea 70 BOTYPE II
17
DRILLING MAST
290 310 320 270 200 05.3.3 Wind forces
The computer program WINDOS is used to determine the wind forces on the vessel.
The computational model is based on a so-called building block approach. This means
that a structure is thought to be built up by standard components with known force
characteristics. The model is represented in figure 5.2.
Figure 5.2
Block model for WINDOS
Results for a wind speed of 1 m/s
310320
3.30
liliro..30
10134$3.W ind force s (kN1 40 50 300-4111111"4-
60 290IIINO
"40
70Ira& ,'
Alr
. 000
11111:1*--,v4gIntigfil
suagw---
--..-4Imalw
06._*411q ii
i 424
WWA
'May.
rMIL
0 IV
220 210/111110%.
150 140 211.11111
10 1 0 0 180 280 270 280 250 240 230 13o 120 110Fa
Fy
TYPE II
DRILLING MAST
80 90 1005.3.4 Riser force
The riser forces are calculated according to the following formula:
*I seawater *
V2current* Cd * L* D
The current profile is derived from Gulf of Mexico data.
For the capability calculations of the intact thruster system, a high current of 1,1 m/s
is applied, resulting in a riser force of 170 IN.
For a DYNPOS-AUTRO failure, a low current of 0,75 m/s is applied, resulting in a
riser force of 80 kN.
5.4 Thruster forces and consumed power
5.4. 1 General
For several environmental conditions DP power plots are prepared. Furthermore, the
thruster use of all thrusters at each heading is calculated for these conditions. For both
intact and damaged condition (DYNPOS AUTRO) a capability plot is prepared. This
data can be found in appendix 5.
5.4.2 Environmental conditions
DP calculations are performed for several environmental design conditions.
Condition I and 2
Max. drilling
Condition 3 and 4
Stand - by
Condition 5 and 6
DYNPOS AUTR
Condition 7 and 8
DYNPOS AUTRO
condition
Hs
(m)
Tp
(s)
. Wave dir.
(deg)
Vwind
(m/s)
Wind dir.
(deg)
Vcurrent
(m/s)
CUT. dir.
(deg)
16,0
11,5
180
25
180
1,1
180
2
6,0
11,5
180
25
90
1,1
180
3
10,0
16,5
180
30
180
1,1
180
4
10,0
16,5
180
30
90
1,1
180
5
6,0
11,5
180
25
180
1,1
180
6
6,0
11,5
180
25
90
1,1
180
7
5,8
10,3
180
20,6
180
0,75
180
8
5,8
10,3
180
20,6
90
0.75
180
TYPE II
19
DRILLING MAST
' I5.4.3 Intact thruster system
For the intact system the following results are found:
5.4.4 DYNPOS AUTR failure
For DYNPOS AUTR operations, regulations are such that during any single failure,
the total system shall not lead to critical situations caused by loss of position or
heading. The most onerous situation is the lost of one of the stern thrusters. The
results are then:
5.4.5 DYNPOS AUTRO failure
In case of a DYNPOS AUTRO failure, one engine room or one main switchboard
room is out of order. The DP arrangement is such that in this case either thruster 1 and
5 or thruster 2 and 4 are out of order. The calculated power consumption is then:
TYPE II
DRILLING MAST
Environmental
condition
Required power (MW)
Available thruster
power (MW)
Heading 180° off stern
Heading 150° off stern
1
5,8
11.8
23,2
7
10,2
7,4
23,2
3
7,2
14,6
23,2
4
14,4
11,6
23,2
Environmental
condition
Required power (MW)
Available thruster
power (MW)
Heading 180° off stern
Heading 150° off stern
5
5,7
11,6
18,2
6
10,1
7,3
18,2
Environmental
condition
Required power (MW)
Available power
(MW)
Heading 180° off stern
Heading 150° off stern
7
4,9
8,9
14,9
8
6,9
4,6
14,9
20
,
5.4.6 Total power balance
For drilling operations a power balance is made. Consumed power for drilling and
hotel is estimated at 7 MW. For the most onerous situations the power balance is
made up.
Intact (envir. 3&4)
The amount of available power (35,4 MW) is sufficient in intact condition.
DYNPOS AUTRO (one engine room down, envir. 7&8)
The amount of available power (17,7 MW) is sufficient to satisfy DYNPOS AUTRO
regulations.
TYPE II
21
DRILLING MAST
Power consumption (MW)
Heading 180° off stern
Heading 1500 off stern
DP
14,4
14,6
Drilling & hotel
7,0
7,0
Power consumption (MW)
Heading 1800 off stern
Heading 150° off stern
DP
6,9
8,9
Drilling & hotel
7,0
7,0
TOTAL
21,4
21,6
TOTAL
13,9
15,9
I
6 Power generation and distribution system
6.1 Power generation
The power generation will be diesel electric. Two separate engine rooms are situated
near the stern of the vessel. This secures that no exhaust gas will run over the drilling
area or heli-deck, thereby improving workability. Each engine room contains four
Wartsila 12V32 engines and alternators. The total power supply is 41,7 MW at MCR.
Technical data Wartsila 12V32
TYPE II
22
DRILLING MAST
Engine output
5400 kW (MCR)
Alternator output
5210 kW (MCR)
# revolutions
720
rpm
Fuel consumption
180
g/kWh
6.2 Power distribution system
The power distribution system is presented in the key one-line diagram on the next
page.
The power from the alternators is directed to two main switchboards. Each
switchboard is connected to three thrusters. Redundancy is built in by application of
tie lines, circuit breakers and change-over switches at two thrusters. Primary power
for main consumers will be generated and distributed at 6,6 kV, 3phase, 60 Hz.
Secondary power for auxiliary consumers and emergency power will be distributed at
440 V. 3phase, 60 Hz. Lighting and small power will be 230 V. single phase, 60 Hz.
Main drilling equipment will be fed by 600V DC.
main switchboard 6,6 kV - 60 Hz Thruster 1 Thruster 3
r--iuxil:airy swtchtinard 1 440V 230 V ighting Thruster 5 SCR switchboard 1 tie-line he-lineX
shore connectionmain drilling equipment
600 V
230 V emergency lighting
SCR switchboard 2 emergency generator
1200 kW Thruster 2 emergency switchbo:, 640 V 230 V I ghting
KEYPLAN
Thruster 4r-clean supply switnboard
440 V
460 V for navigation equipment and radio station
switchboard 2 :.4 V Thruster 6 ; man switchboard .7 6 6 wV - 60 tie _ T T3
SYMBOLS
4
0
10
1,\I 1MDiesel engine
Frequency converter AC Generator AC Motor Change-over switch circuit breaker
X
8 MAIN GENERATORS
6510 kVA
5210 kW
11" 01-..111 , !720 rpm
60 Hz
engine room;KEY 0\E-LINE DIAGRA V
1
-tie-line0
14 16 156.3 Load balance
For five conditions the electrical loading by thrusters, 'drilling equipment, hotel
facilities and auxiliary equipment is presented in an electrical load balance.
The five conditions are:
Harbour
Sailing
Drilling moderate weather (thruster loading 15%)
Drilling rough weather (Hs = 6m, V, = 25 "Vs, Vc = 1,1
mis,heading 200)
is
DNV DYNPOS AUTRO
(115= 5,8m, V, = 20,59 "Vs,
Ve
= 0,75 "Vs, heading 30,
(one engine room and two thrusters out of order)
The results of the DP-calculation have been used for the loading from the thrusters.
The total load balance can be found in appendix 6, the results and the loading on the
generator sets are presented in table 6.1.
Table 6.1
Load balance and loading on generators
TYPE II
23
DRILLING MAST
harbour sailing i i drilling moderate weather drilling rough weather (condi) DYNPOS I AUTRO (cond7) thrusters 0 9474 I..
9879 I 9401 Ship's auxiliaries 1265 1490 2819 3410 3410 SCR Drilling system Drilling auxiliaries 0 n v o I 76 ' 4967 1930 4967 2006 4967 2006 . [otal required
1265 ' i i 11040 133801 20263 I 19785I rated power power power power power
power at (MCR) (MCR) (MCR) I (MCR) (MCR)
power supply MCR
on/off
(kW) 11
on/off (kW)
on/off
(kW)Ion/off
(kW)on/off
(kW) Engine room 1gen.sel ill 5210 I 5210 1 5210 F 5210 li 5210 out 0
gen.set 2 5210
0
0 0 10 1 I 52101 1 II 52(0 outa
gen.set 3 gen.set 4 5210 5210 0 0 '0 0 o 0 o o0,
o o o 1 o o o o out out 0 0 Engine room 2 1 gen.set 5 5210 0 0 I I' 5210 I 5210 1 1 5210 I 5210 gen.set 6 5210 0 o It 5210 0 0 1 5210 1 5210 gen.set 7 I 5210 0 o o o 0 o I 1 5210 ill 5210 gen.set 85210,
0 0 o 0 oo
o ' o 1 5210emergency! harbour generator I 500 0 0 0 0 0 0 0 0 0 0
7 Down time
7.1 Motions
For a typical drilling condition with a draught of 8,5m the motion behaviour is
determined. The program "Seaway" is used to calculate the motion characteristics.
The "Seaway" output and RAO's can be found in appendix 7a. For the downtime
calculation the motion behaviour in several specific seastates is needed. The Jonswap
wave spectrum for eleven zero crossing periods with peak enhancement factor 2 and a
significant wave height of lm. is used. Since Seaway output is in significant values,
all values are transformed into maximum amplitudes by multiplication of 1,86. The
motion behaviour in those eleven seastates is suitable for implementation in the
program "Downtime". In the following graphs the motion behaviour is presented. The
unit on the y-axis is m/m for heave and deg/in for roll and pitch.
1 40 1 20 1.00 0.80 060 0 40 0.20 0.00
Heading dialdeg
5 10 15 20 25 30 35 T, (a) heave oach 1.40 1.20 1.00 0.80 0.80 0.40 0.20 0.00 Heading 150 deg 5 10 15 20 25 30 35 T. heave roll [oh 1.40 1.20 1.00 080 0.60 0.40 0.20 0.00 Heading 165 deg 0 5 ID 15 20 25 30 35 T. Is) 4. heave
I. roll
TYPE II
24
DRILLING MAST
4
a
7.2 Downtime
The motion behaviour in those eleven seastates is suitable for implementation in the
program -Downtime". This program linearises the relation between wave height
and
motion behaviour by multiplying the wave height from the wave scatter diagram with
the Seaway output for Hs = 1m. If this value is larger than the criteria downtime
increases. Downtime is calculated for three headings (150°,165°and 180°)and for
three sets of criteria. The wave scatter diagram of the Golf of Mexico (area 15) is
used.
The following criteria are used (maximum amplitudes):
The results of "Downtime" are tabelised below. Downtime plots are in appendix 7h.
The yearly downtime is estimated by simulating a typical drilling program. This
method is described in report 6204.1000.301, page 102-103. The results are below.
criterium
# 3 hours int.
downtime
hours
Heave
Roll
Pitch
Running casing
1,5 m
1,5 °
1,5 °
Drilling
3,0 in
2,5 °
2,5 °
Tripping
3,75 m
3,5 °
3,5 °
Heading
Casing
Drilling
Tripping
180°
3,37%
0,26%
0.11%
165°
3,37%
0,26%
0,11%
150°
6,54 %
1,38 %
0,22 %
drill eval. pilot
2 167%
3.48
reenter and open
2 167%
3.48
run &
cement
1 828%
6.61open pilot
224
11%7.57
run&
cement
120
18%11.00
run riser
120
18% 11.00land BOP
1 8 28% 6.61BOP test
2 84%
0.90
tripping
336
1%0.85
drill 2
48
1% 1.39log&open 2 62 7% 13.09
run
&cement
1 16 15%7.20
test stack
2 84%
0.90
tripping
3 150 1%3.55
drill 2200
1% 5.81 log 140
4%
4.80
run 124
22%
15.51test BOP
2
84%
0.90
tripping
3 72 1%1.70
drill 2 96 1%2.79
log 140
18% 22.01disconnect
2 3 1%0.13
pull riser
1 13 36%14.02
plug and abandon
224
11%7.57
total
2880
5.31%
152.90
Annual downtime
20.44 days
TYPE II
25
DRILLING MAST
L
I
8 Hull strength
The longitudinal strength is calculated according to DNV regulations. A midship
section is designed following the rules with respect to local and global strength.
8.1 Loadings
The stillwater bending moments and shear forces are calculated for all typical loading
conditions, as defined in chapter 2. The maximum bending moments and shear forces
occur at condition "Sailing, 10%" and "Testing 98% crude, 90% consumables"
respectively for bending moment and shear force. The calculated values are compared
with the design stillwater bending moments and shear forces as stated in the rules. A
plot can be found on one of the following pages. The shaded area on the plot
represents the deck opening in the moonpool area, with longitudinal extension. For
the bending moment the design value is applied, for shear force the calculated value.
8.2 Midship section
The most awkward location is around the moonpool area. Figure 8.1 displays the
cross section in this area. The black members are considered effective; the red
members do not contribute to the longitudinal strength.
Figure 8.1
Cross section
The dimensions of stiffeners are dictated by local strength requirements. Plate
thickness is dictated by global strength requirements. For details of the calculation,
reference is made to appendix 8. A drawing of the cross section can be found
on one
of the following pages.
TYPE II
26
AbsoLute shear force curves
loading condition testing 98% crude, 90% consumables
DNV
31)81 h19
from loading conditions
Bending moment curves
loading condition sailing 10% consumables1184964 kNm
from loadin onditions
45258 kN
Str ctura[ Loading co parson between
I 1 1 14 14 3500 4100 3950 6250
vidship section
HP 220e10 t HP 180x10 HP 240x12 HP 240x13 HP 180x10 I HP 220x10 HP 240e13 HP 1E1000 L 11 rnCLASS
DET NORSKE VERITAS
Principal dimensions
Requirements
Midship section mudulus about the neutral axis14,24 ml
Midship moment of inertia about the neutral axis
103.26 in'
Combined thickness lbhd & side plating far shear
19,27 mm
Attained values
Material
All transverse plating and slit fenersin
midship area NV-NS, yield stress 235 N/mm2 All longitudinal plating and stiffeners in rrodsImp area NV-32. yield stress 315 NM&
Rule length 188.8 in Breadth 35,6 m Depth 17,6 m
Draught for rules scantlings
11,0 in
Neutral axis from keelplane
8,11 in
Section modulus at main deck
14,37 ins
Section modulus at bottom
16.80 m3
Moment of inertia about the neutral axis
136 31 mi.
BaSIE
rs_o
s
pha
iiids
section
HP 201 HP 240x12 22 Ip
W8.3 Results,
Due to the lack of effective material in the upper region of the cross section, the
section modulus at main deck is a critical requirement. In order to minimise the hull
steel weight, the neutral axis is raised as much as possible, to 8,11 m from keelplane.
JResults' from strength calculation:.
8.3.1 Material
All longitudinal plating and stiffeners in the midship area will' be high strength steel
NV 32, yield stress 315 N/mm2.
All transverse plating and stiffeners, as well as all material outSide the midship area,
will be mild steel, NV NS, yield stress 235 N/ nun2
In this context, the midship area runs from the fore engine room bulkhead to the aft
accommodation bulkhead. In the weight calculation, this area is referred to as section.
2
5.
4.1.=
TYPE II
27
DRILLING MAST
Required
Attained
Section modulus about neutral axis
Z
14,24 m3
Zdeck
14,37 m
Zbottom
16,80 m
Maximum stress
-
°deck
222 N/mm
°bottom
190 NA=
Moment of inertia about neutral axis
I
103,26 m
] 1136,31 in
Combined thickness lbhd & side plating
for shear requirements
19,27
9 Hull weight
Based on the midship cross section as derived from the strength calculation the basic
hull weight is calculated. The ship is longitudinally subdivided in six sections with a
more or less similar cross section. The objective is to get a cross sectional area and
multiply this with the length of the section. The area of the midship section as
calculated in the strength calculation is directly used in this weight calculation with a
reduction for the fore and aft ship. For each section, steel in decks and longitudinal
stiffeners, which is not accounted for in the strength calculation, is added to the cross
sectional area of that section. Transverse stiffeners (bulkheads, webframes and floors)
are added to the longitudinal members and the total volume of steel can be calculated
with an additional 5% for brackets. In figure 9.1 the sectional subdivision is
presented, the outcome is presented in table 9.1.
The total hull steel weight is 8899 ton of which 46% is made of high strength steel.
The total hull steel weight of 8899 ton is close to the estimated value by the method of
Johnson, Hagen and Ovrebo (8881 ton).
Table 9.1
Hull weight calculation
TYPE II
28
DRILLING MAST
Longitudinal
P...0 7.85 kElern'section 1 section 2 section 3 section 4 section 5 section 6
A A A A A A
(cm') (cm') (cm2) (cm') (cm) (cm')
strength 29857 strength 29857 strength 29857 strength 29857 strength 29857 strength 29857
dock 3200 deck 3200 moonpool 4186 deck 3200 deck 3200 deck 3200
bottom 2000 bottom 2000 cofferdam 5632 bottom 2000 bottom 2000 bottom 2000
tanktop 1750 tanktop 1750 tanktap 1750 tanktop 1750 tanktop 1750
center girder 371 center girder 371 center girder 371 center girder 371 center girder 371
deck 1 4576 deck/ 4576 deck 1 4576 deck 1 4576
deck2 4576 deck/ 4576 deck2 4576 deck2 4000
reduction -11583 deck 3 3500
reduction -9851
Iota tote , 11 tote Iota V. tote t Iota
volume
section A Length A x L Weight LCG moment
(cm') Intl (MI/ Id Irn)
1 34747.5 38.80 135 1058 13 13758 2 46330 34.40 159 1251 50 62054 3 39675 12.80 51 399 73 29182 4 46330 13.60 63 495 86 42735 5 37178 60.00 223 1751 123 215734 6 39403.2 41.80 165 1293 174 225100 transverse tt I-) Main bulkheads 88.53 7 620 95 58874 Small bulkheads 50.35 8 403 95 38263 Webtrames 4.97 75 373 95 35438 Floors 1/.11 75 833 95 7914-8
total 8475 94.42
Total hull steel weight iincl 5%)
8899I
3414/.b 494031
anj
ii
'ran
Erfln
Is
a
raltaliZIPMEN.P.20161111.1minn"
Iir
EMI
tel.
I I wlknri WOW 11Figure 9.1'
Sectional subdivision
TYPE II
29
10 Building price
For the estimation of the building price, the ship is subdivided in groups (same as
those used in the weight calculation), a sample of such a group is shown in table
10.1.,
Two large posts are steel and drilling equipment. The primary steel costs are
estimated to be 2,5 $/kg for mild- as well as for high strength steel (included
manufacturing), since the price difference for mild and high strength steel is very
small, hfl 0,79 for mild steel and hfl 0,90 for high strength steel. The price of
secondary steel is estimated to be 8 $/kg. The group steel weight is presented in table,
10.1. The other large post is drilling equipment. Total drilling related equipment is
estimated to cost 75 min $
For the other posts a price per kg is estimated or manufacturers are consulted
for exact
prices. In table 10.2 the weight and price of the weight groups is summarised. The
total building costs are estimated to be 183.6 mm n S.
Steel weight
Table 10.1.
Steel weight group
sn put
1 n rW-
vcg Mg
Tcosts/t
(t)
(m) (m)
costs
primary
steel hull
8899
9.5
94.4
2.5 22,24g
sr econdary steel
400
10.6
94.4
/8.0
310d
,_
I
reinforcements thrusters
4
80
5.0
120.01
8.0
6401reinforcements main thrusters
2
50
5.0
0.01
8.0
400
crane pedestral
3 5117.6
80.01 191.0
57j
engine foundation
208
6.3
17.618.0
1,666
shale shaker house
.115
27.6
66.01' .8))0920
ubstructure
&
drillfloor
funnels
500
50
24.9
23.6
73.4'
25.0
3.5
.1,750, 1 I3.5
175 ,skeg50
1.5 17.0; ,3.5
175.contingency 2,5%
260
10.7
94.41118:0
2,081)
output
weight.
10663
meg10.4
lcg
90.6
costs
33,821
TYPE II
30
DRILLING MAST
Table 10.2
Building costs
TYPE II
31
DRILLING MAST'
Lightship
group
weight
portion
It)VCG
L CG ,Ord
Cm) 1,01;01.000
Casts
1Drilling
Steel weight
10,663 52.84% significant
10.44 '90.63
33,821
equipment
2
Major rig equipment
11,1455.67% significant
46.45
65.14
3
Mud system'
675
3.34% significant
20.17
56.83
4
Subsea equipment
1,250
6.19% significant
21.92
74.89
75c004
Marine riser system
5
.215
1.07% significant
20.67 127.40
6
Pipe handling
210
1.04% significant
19.70 111.32
7
Substructure piping
95, 0.47% not significant
23.00
73.20
Systems
8
Diesel engines
830 4.11% significant
'9.40
18.00
8,400
9
Mooring & SK systems
490 2.43% significant
10.65
80.15
18,2561
10
Electrical system
375
1.86% significant
12.40
87.27
15,0001
Auxiliary systems
11
1750 8.67% significant
10.64
95.00
2
Topsides
.300
1.49% significant
23.60
15.0015,100
13
Crude handling
283
1.40% significant
18.84
36.0814,500
rersonel
14
Accommodation
1,305
6.47% significant
,27.111 165.77
18,280
5
Material handling
350
1.73% significant
36.10
78.20
3,750
6
Lifesaving & rescue
245
1.21% significant
23.17 162.04
1,500
Appendices
Appendix 1
General arrangement
Thruster retrieving system
Appendix 2
Wind heeling moments calculation
Hydrostatic particulars
Tank arrangement
Intact stability calculations
Appendix 3
Damage stability
Appendix 4
Resistance calculation
Appendix 5
Capability / feasibility plots
Appendix 6
Load balance
Appendix 7a
Seaway output
FtA0
plots
Appendix 7b
Down time plots
Appendix 8
Appendix 1
General arrangement
Longitudinal section
centerline
narlans
product..., plateare
116 ..1*.".7.:!
twice, heard room man env.
essie ancear engme noon ad( store 114 e ece nin scar se mod woman;
foundation [Sells" ases aunts led Lc moos
e canons
'alarm
iklf21:11 ottlare SCI 11111111112111111111t 11,1I II Iller1.11111111 el ell211111. llekle 1121 17/11/1111 1110111 1111U112112-1111 J!Mew 1.11.21111 IILW_ILJE111111t111111111122111111111111.111111111111I elle
111111111WHISeHt11111111111112111 ,1111111S2/ 11112$1111111111111a= -3 -10 rs 6 21 -SS CO 71 /I is IS in II ill MS no ins an la so us so Ise .15 .10 05 Mo as se se log Its Ill CIS us NI 71 115 ICI
II
1141 HI Ill from yang",I4l01I.I.
Longitudinal section
prf sidecans I on" now
1,21 i
I (mama 11111311/1111,1111111111.11111,1
t 111,111 1101111 iIIIl111ItiIIIII!I li011IIIllIlI IIIII111IIII111111111111111/11111111.11111
ev
0so
0fl es yes IC 144 Si ell VI 65 1. M " VS MI M 245 T1 M Ins na 00 nt 21.1 a11S. Sae 'siege wont,Main dimensions
Length between PP
Breadth moulded
Depth at side
Operating draught
9ct a co sin I
/
nes s" , cons wan coon a cannon room i ef COP 1 1. th'ke ? 12S11 end roo stores Iwintry I gyre compressor rep ..1nun
flee we Irene ---man1QL_
-nay bredne deck
-deal -deck
B - deck A - desk
mon deck Ian A B
tween deck I
1449 A
Swoon
deck? MOO A_I3
Caen deck 3 1300 A B 5209 A 1110 000 2650 A-13 lase trays do puma 5
/
0,11,79 warJ
3d 40%35,6
17,6
9,0
/
50411130 1 - - -Bproduction platform 20600 above base
product.. pl at f orm 70.'75 11111i1111111 11111 MO- AS-4 a4:0
000 090
storeokaaa S alt memfold Inning teals
BHA
Topview
Top view
main deck 17600 A B. 11/11/11,1 1.1111 ell 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 I(Ill 1 1 1 1 1 II ttl 1-1 1 1 ILI 11it' 1 1 1 1 1 tett 1 1 1 1 1 1,1 1111111111101114114411111111111/11tVil 11111111171141111.111141 Sm Id is
iu,c
---arbcns
Ms no A 511 in na us no ne Vt itt lit Loo 145 AC 755ill
enn ell ea-C
thrwat r hal mud treatment workshop 1LL14.11.1_1t1111111ltitrilkirtkrtil/11$1.111
11.11145 1111111 1111,11111111. II n iI De es 'Q ti is II-r21 12, .3a in an 045 Or in tyl no Or leo rraatrarrorN.,.
1111killtt111.111,11 I In NS ill 74 en o teedeck 20600 above deck
pip
drillt[oor 27600 above base
his .5 IS 45 55 II 43 10 IS ill Ill 20 ton. 35m .35m + hatch
/
I II I 111 I I I I I '1,01.0111 5/
+ + + + + shale shaker mud unit + + + + + + + + ++ \\_+
+ + + + + + + + Lt4RP+\
+ + + + + + + + .-....± cround flare + +4-N
15 ton. 25.5tween deck 1
14500 above basetween deck 2
111.00 above basetween deck 3
8300 above base---Pass age way
& table trays passage may & cable trays passage way & cable trays
mess room 1 recreation room
/stores
switch board room
VIVA! auxhavy rOOm agitators mud Pump room ....kop APV . compressors 0000000000000 0000000000000 BOP control units
0
silos\
7/
/
/
\
/
/
\
1 .s. `../
/
e// /
1 MaVer , thruster frequency j converter !I li slop tank . ... ' thruster thrusterswitch board room
attain
v
mud vamp.
foundation being masts
7/
\
7
\
/
/\ \
\
\ \
.\
/ \
./ / . 1 -_i 1 -ea...Qv
1 recreation/ room /stores auxhairy erllneroom thruster 1 I l / 0000000000000 0000000000000 workshop A-PV - compressors thruster exhaust & ventilationpassage %ray IL cable trays
passage way I cable tray
passage way L cable frays
--.:,,. nide -- --cabins prop roomman envie room 2
Mr= 4=1
engine auxiliairy roam active nod tanks rucl pump room APV . compressors 0000000000000 000000000000o Mu er thruster workshopa2=
1115=4ii
r
'
...1----thruster h Laler engine artIve mud tanksMud pump room
foundation drilling masts
r
4
1
/
silo cabinsUMI=11
.,...a..1,.. IrTra MI.,
vIi au
re
iv fowl tanks mud pro r.00foundation drilling mans