The paper presents the basis for selection of
the TLP concept for development of the
Snorre field, and outlines important aspects of the design and operational philosophy for the selected TLP concept.Furthermore, lessons learnt from the design, fabrication, installation and operational phases
are summarised, together with
recommendations for design improvements
and simplifications. For the operational phase,
emphasis is put on the liP-specific aspects sucti as influence of platform motions, weight
management and design-feedback from the instrumentation system for monitoring of platform responses.
The paper also includes a description
ofcurrent and planned modifications
of the
Snorre TLP to accommodate new functional requirements.Finaly, status on a recent development of a
deep water TLP is given.
INTRODUCTION
The Snorre Field is located in the blocks 34/4 and 34/7 in the Norwegian sector of the North Sea, 170 km west of the Norwegian coast, close to the UK border. The water depth at the field ranges from 300 to 350 meters, and the soil conditions are characterised by soft clay. The field is located close to other large oil fields such as Statfiord and Guilfaks.
The history of the Snorre field started in 1979 when Saga Petroleum was awarded the
production license on block 34/4. Initial
'SYMPOSIUM
BY
Stein Fines, Saga Petroleum a.s
Oddvar Alfstad, Saga Petroleum a.s
ABSTRACTTHE TEXAS SECTION OF
ThE SOCIETY OF NAVAL ARCHITECTS
AND MARINE ENGINEERS TI.? TECHNOLOGY SYMPOSIUM; 1995
Mekalwog 2. C Deft
TeL 015.. 7b OlSe 781835'
exploration indicated existence of a promising oil field extending to the south into block 34/7.
In 1984, Saga Petroleum was granted
production license also of this block, and an agreement was later established between the license owners of the two blocks for a joint development of the unitized Snorre field with Saga Petroleum as operator for both development and operations.
In 1984, a' three year work program was
launched, comprising extensive explorationwork and field development studies.
This phase was concluded by submittal of 'the Plan for Development and Operations (PDO) to the authorities for approval on September 1, 1987. Pre-engineering was started in December the same year,and the PDO was formally
approved in May 1988. Major fabrication work started
early 1989, and the platform and
subsea production system were installed inMay 1992. First oil was produced ahead of plan in August 1992, and the full production
was reached less than half a year later.
CHALLENGES
The selection of a development scenario for the Snorre field, Included' a lot of challenges. The developments so far in the North Sea had taken place in moderate water depth less than 200 m, and with good soil conditions.
As stated earlier, at the Snorre fleld we were faced with much deeper water and very soft
soil. Another complicating factor was the very
complex reservoir, which required a large
number of wells over a relatively large area.it. should also be mentioned that a relativelylarge percentage of the recoverable oil was
located in Lunde formation in the northern part
of the field,
where no
prior productioninformation was available. Thus a staged
development, where the major part of the
development of the Lunde formation could be
done in a phase 2 of the project, utilising
production information from a small number of wells in phase 1, was selected.The biggest
challenge was however of
economical nature. Since the oil activity started in Norwegian waters, the oil price had been high, with oil pricesup to
35-40 USD/barrel. At the time of development of the Snorre field, the oil price had fallen to 20-25 USD/barrel, and analyses indicated that the price could fall as low as 10-15 USD/barrel. It was therefore essential to establish adevelopment scenario that could sustain
periods with low oil price. The problem was, however, that the technology and the mode of operation were aimed at a much higher oil price, such that new and innovative solutions had to sought.
Another challenge was that Saga Petroleum was a young oil company, and that the Snorre field was the first development project for the company in Norwegian waters. This Situation could also be looked upon as a large asset, as the óompany was willing and able to introduce new technologies and modes of operations,
and was not 'tied down' by old traditions.
CONCEPT SELECTION
The concept selection was driven by the
fundamental functional requirement in terms of number of wells and total production capacity, matched with the need for reduction of the investment cost due to the low oil price. A large number of concepts for substructuresàid production systems were evaluated, in
cOmbination with possibilities for utilisation of exiting;infrastructure at nearby fields. Large
efforts were put into evaluation of extension of existing technology beyond the current state of
art with regard to functional requirements,
environmental criteria and safety requirements. The most promising concepts were selected based on both technical and economical criteria.
On pure
economical analyses, it was concluded that a developmentwith two floating production units (semis or shipshaped) combined with subsea
production facilities, was the most attractive scenario. However, considering the project risks and the necessary development work needed to facilitate a development with up to 100 subsea wells, it was concluded that this scenario was too futuristic to be launched as
our first
field development project , sincefeasibility could be questioned in some areas within the time frame set for the project.
Based on a balance between economical potentials, the amount of development work involved, and evaluation of project risks, the Tension Leg Platform (TLP) was selected as
the basic concept for development of the
Snorre field.It was also concluded that a
staged development of the field Should be performed, in order to reduce project risks.Due to
limited informationof the Lunde
formation, the first phase of the developmentshould consist of a TLP placed on the
southern part of the field draining the Stathord formation, while the Lunde formation should initially be drained with a limited number of
wells from a subsea production system placed
some 6 km north of the TLP. The second
phase of the deveiopment should eitherconsist of a relocation of the TLP to the
northern part of the field after some 15 years service in the southern location, or adevelopment with further subsea production systems in the north. The TLP was therefore designed for relocation, and with connection points
for hook-up of
flexible risers andumbilicals for the possible subsea production systems. Later it has been concluded that
further development should be performed with subsea developments, i.e. the TLP will not be relocated. The reason for this is that increased oil
reserves have been discovered in the
south, making it more profitable to keep theTLP at the southern location longer than
originally planned. Furthermore, the resentdevelopment in subsea technology, where the
cost per subsea well has been dramatically reduced over the last
years, makes this
solution much more attractive. As aconsequence, the Snorre TLP is now being used as a 'field centre' when planning further development of new oil fields in the area. This will be discussed more in detail later in this
paper.
It was chosen to install process equipment for
only two stages of processing onboard the TLP. The final processing of the oil and gas
would be performed on
the Stat! iord A platform, where also offloading ofoil and
export of gas would take place.THE SNORRE TLP
To select
a TLP concept
for the first development project, could seems as a very risky decision for a relatively inexperienced oil company. At the time of selection, only one TLP. projecthad been
realised, namelyConoco's Hutton project, a TLP which was much smaller than the Snorre TLP in size,
production capacity and investment. However, as operator we established a program for risk management early in the planning phase. This program was called 'Major Technical Element Program', and was established as a joint effort between Saga Petroleum and Esso (Exxon) who was our technical advisor on the project, and one of the owners in the Snorre licenses.
This program was actively used by both
management and engineers to follow up all issues that could have an adverse effect onthe project cost and schedule until they were closed.
The selé ted TLP concept was in general
based, on. design principles that were wefi known from the Hutton TLP and other North Sea offshOre projects. New technology was only introduced where significant investment or operational cost reductions could bedocumented, and after in.depth qualification of the technical solutions.
The hull of the Snorre TLP is a four-column
steel
structure based on well
established design principles from ship design. The deck is a conventional integrated deck well known from the Norwegian concrete platforms. Thisdeck design was chosen for
its cost andweight benefits. The main structural girders comprise a combination of longitudinal truss girders and transverse plate girders. This solution provides a safe segregation between 'hazardous and non-hazardous areas, and provides flexibility for pipe and cable routing within the different areas. The fully equipped deck was mated to the hull structure inside a sheltered fiord.
The selected tether system was a multi-piece system, where the indMdual components were connected by threaded pin and box
connectors, and deployed through tether conduits from a mooring compartment inside each of the platform columns. The tethers
were equipped with flexible articulations in 'the anchor connectors in the foundations, and in the cross-load bearings in the lower part of the
hull. The tethers have dry tie-off at the
mooringflat some three meters above sea level. The design of the tether system is more or less identical to the Hutton TLP, except thatthe diameter was much larger and the wall
thickness smaller.
Also for the riser system, the design sOlutions were more or less as for the Hutton TLP, i.e. top-tensioned steel risers for all export- .and production risers. For tie-in of the subsea production station, freehanging flexible risers
were selected. The pretensioned risers were supported by hydraulic tensioners at the deck level, and the riser joints were made up by threaded connectors or flanged and bolted connectors depending on the fatigue loading on the actual riSer joint All production risers and the gas export riser were terminated at the. seabed with a steel stressjoint, while the larger diameter oil export riser and the high pressure drilling riser were terminated with
elastomeric flexjoints.
The key-parameters of the Snorre TLP is as
follows:
Displacement 104900 tonnes
Column diameter 25.Om
Column c-c distance 76.0 m
Pontoon dimensions 11.5x 11.5 m
Platform draft 37.5 m
No of tethers 16
Tether pretension 25000 tonnes Hull steel weight 24000 tonnes Total deck weight 39500 tonnes
Deck payload 25000 tonnes
Risertension 3500 tonnes
No of well slots 44
INNOVATIVE SOLUTIONS
As mentioned earlier, the need to reduce cost and weight led to introduction of new
technology and innovative solutions in some
areas. Some of the major ones are listed
below:Aluminium living quarters. By introducing a stress-skin aluminium living quarter it was possible to save about 800 tonnes of weight compared to a traditional steel structure.
Water injection system. Probably the best example of weight and space reduction within the deck itself is the water injection
system. By
using. new
technology,comprising cartridge filters, a Hydro Minox deoxygenation .package, and vertical
pümps it was possible to save some 560
tonnes of .weight compared to a conventional system.
Guyed flare stack. Compared to a conventional flare tower, a weight reduction
of 50% (80 tonnes) and cost reduction of
80% was obtained.
Large diameter tethers. By making the
diameter of the tethers so large that theyare close to
neutrally buoyant, it was possible to reduce the effective load on thehull structure, and therefore also the
required displacement of the TLP, with
about 2000 tonnes.
Concrete suction anchors.. By selecting
concrete suction anchors for the tether
foundations, significant cost . savingscompared to piled steel templates were
obtained. Specially for the soft soil
conditions at the Snorre field, the foundation solution was very cost effective.
Other areas where new technology was
introduced, were in the drilling area with fully hydraulic drawwork. All these elements involved cost savings either on the investmentside or with respect to reduced operational
costs or improved operational regularity.
FABRICATION AND COMMISSIONING
The hull structure was fabricated in sections at different sites and transported to Stavanger for assembly. The ring-pontoon was assembled across a dry dock, lifted off by a submersible barge, and brought afloat outside the dock.. The column sections were lifted in by
shearlegs and welded together in the floating
condition. This proved to be a very cost
effective assembly method.Major parts of the deck structure were built in Finland and transported to Stord where it was assembled
across a
dry-dock. After the prefabricated equipment assemblies andmodules were lifted in and hooked up, the deck was transported out into the fiord on a
barge and mated with the deck structure. After the deck mating, the platform remained in the mating mooring system for more than
half a year, while the
final hook-up and commissioning were performed. During thisperiod, the platform was operated as an
offshore installation, where the personnel livedon the platform for periods of 14 days at a
time.
During this period extensive testing and
training activities were performed. This included among others:
Inshore drilling test, including running of
risers and drilling of a well into the sea
bottomTether deployment system trials and
training. This included deployment of tethers from atl conduits fbr verification of
procedures and training of personnel in an around the clock operation for 14 days. Inshore production tests, involving testing of the process facilities at full flow rates with a mixture of diesel oil, water and nitrogen. TFL system trials, invoMng pumping of TFL tools trough the
topside systems and
hardpipe risers.
In addition an extensive testing of the water injection plant was performed prior to the plant being lifted onto the deck at the assembly
yard.
For all tests there were positive effects
in training of personnel and inuse of the
operational procedures. In addition, the tests
uncovered errors and faulty equipment that
otherwise would have caused delays and extra costs. offshore.
INSTALLATION
The fully commissioned platform was towed out by 7 tugs to the field in the middle of April
1992,
one month ahead
of the original schedule. Arrivingat the field,
the SSCV M7000 was at the location, moored with 12 mooring lines. The TLP was connected to M7000 by two interconnecting mooring lines, which were kept tight by the 7 tugs in a star-formation. After waiting for a few days on an acceptable weather forecast, the two firstrounds of tethers were deployed with the TLP some meters off the location of the foundations. The TLP was then brought in
position by the station keeping spread, and the first tether in each corner was stabbed into the
foundation receptacle, using the
Tensioner-Motion Compensator (TMC). When all the four tethers were stabbed and locked, the heave-suppression Was performed using the TMCs. The platform was now tethered with only four tethers, and it was essential to stab, lock-off and 'perform deballasting such that the TLP could survive a 1 0-year seasonal storm. This
work was performed timely and efficiently
without any kind
of problems. After this, however, the operation had to be interrupted for more than a week due to bad weather.Finally, on the May 11, the platform was safely moored with all
16 tethers, and the final
preparations for start-up of production could commence.
One lesson learnt from this operation is that April and early May is not the ideal period of the year to perform weather-sensitive marine operations in the northern North Sea. However, in the periods with acceptable weather conditions, the operations were performed timely and safely without any kind of problems. Another experience from the operation was that the stationkeeping could
have been performed effectively with tugs
only, i.e without the use of the large.and costly SSCV.
START-UP AND PRODUCTION
The hook-up of the export risers, and
completion and hook-up of the first of the pre-drilled
well was completed such
that oil production started August 3,1992. By the end of the year, all the six pre-drilled wells werecompleted and hooked up with a stable
production of about 160,000 barrels/day, versus the design capacity of 190,000
barrels/day At the end of 1992, the subsea
production station should also be put on
stream, but this was delayed due to a failure inthe electrical power circuit on the subsea
production station. This resulted in half a year delay of the start-up of the production from the subsea system, as a new by-pass system had to be installed. ThiS was successfullycompleted by mid 1993, with only diverless
operations,
and was
perhaps the most challenging technical taSk in the whole Snorreproject. By the end of
1993 the subsea production station was producing from fourwells, without any kind of problems.
Since the production Started up in August 1992, there has only been three incidents that have resulted in shut down of the production due to bad weather. One occurred in January 1993 when one of the burner booms were
damaged due to wave run-up. The Wells were shut in and the production temporarily stopped
until the burner boom was secured and the extent and consequences of the damages
quantified. Even in this storm, which
corresponded to a return period around 10
years,, the performance of the process facilities did not require a shut-down.
The two other occasions with
production shutdown due to weather has been caused by liquid motions in the separators.As mentioned earlier, the design production
capacity was specified to 190,000 barrels/day. The:;' ptattcrm has however performed much better than this. In periods with no operational problems, it has been possible to maintain a stable production above 215,000 barrels/day, or more than 10% above the design capacity. The maximum weekly production so far was reached in week 43 of 1994, with an average production per day of 227,300 barrels, while the maximum daily production is 235,000
barrels.
There has of course been some technical
problems on the pletform that have influencedthe production regularity, but none of the
problems are caused by the fact that the
platform is a TLP. As an example it can bementioned that the production was reduced for
some time due to failure of one of the gas compressors, resulting
in an average daily
production of about 135,000 barrels for that period. During the winter with long periods of bad weather, it is experienced now and then that that the production has to reduced or shut down due to limited oil storage capacity at the Stafford field, as the shuttle tankers are notable to load the
oil. Other reasons for shutdowns have been shutdown and alarms at Stafford A , which also trigger a similar actionat the Snorre platform, as the final processing is performed at the Stafford a platform.
In general it
can be concluded that the
production regularity is very good. In average for 1994 the daily production, including periods
with planned shutdowns, is above 170,000
OFFSHORE VERIFICATION PROGRAMME
The Snorre TLP is instrumented for measurement of platform responses. This is part of a verification program
that was
established early in the engineering phase. The intention was that the information from
these measurements should be used
to validate design, update inspection programs and operational criteria, as well as providing information of value for design of future TLPs. The system is set up to record 34 minutes of measurements every third hour with sampling frequency 1or 4 Hz. The system will be
trigged for more frequent measurement in case some predefiried values of certainparameters are exceeded, or a logging is
initiated by the operator on board.
The. system includes measurement of the
following parameters:
Environmental data, i.e. wind, waves, current, atmospheric pressure and dynamic water pressure at selected hull points
Platform motions, i.e. platform position, linear accelerations, angular velocities and airgap
Strain in selected points in hull and deck Skirt pressure, tilt and settlement of
concrete foundations
Tension in all tethers, as well as strain, accelerations and inclinations at selected points for some tethers
Top tension for all rigid risers, as well as strain and accelerations at selected points for some risers.
In general the system has functioned satisfactorily except for a few areas. The field instrumentation has in general been very
reliable, except for some areas were we have had problems. The biggest problem has been the -wáve.. measurements, an area which shoUld héve been the most trivial part of the system, as long time experience with such
systems existed.
For the wave measurements, a wave buoy
moored about 400 m from the TLP was
selected in order to give time histories as well as spectral information. For the purpose of the
verification activities, the time histories were essential. However, the buoy has been lost
twice due to failure of the mooring system, and
damaged once due to
collisionwith the
standby vessel or a supply vessel. In addition, there has been problems with hardware and software compatibility. The net result of this is that at present very little wave data is availablefor the most interesting time periods, i.e. the winter seasons, which reduces the value of all the good quality platform response data. We have tried to. compensate for this by using wavedata from other platforms in the area,
and by using the airgap data to get wave
information. The airgap data is diffióult to use due to large diffraction effects from the hullstructure. To improve the situation for the
fUture, a wave radar is planned to be installed on the platform deck to give spectral information.Another area where there have been problems
is the instrumentation on the risers. Most of
the instrumentation packages which were
placed at two locations on some Selected risers, failed shortly after installation due to
short-circuiting. New and improved instrumentation has been fitted to one of the latest installed production
risers, and this
instrumentation is giving high quality reliable.d.ata.
Except for the above problems, a
large amount of good qualitydata has been
collected, and is of large value for operationsof the
Snorre TLP
and for increased knowledge of TLP-technology as such.Below are given some of the preliminary
conclUsions from analysis of measured data from the Snorre offshore verification program. TLP motions are analysed in terms of wave-frequency motions, low-wave-frequency motions andstatic offset. The maximum total TLP offset
observed to date is 17.0 m,
while the
maximum calculated offset for the 100 year
storm (excluding load factors) is 32.9 m. When
the maximum observed offset is compared
with the calculated offset for the corresponding environmental conditions, it agrees reasonably
well.
Based on preliminary analysis of the TLP
motion data the following conclusions may bedrawn:
Observed wave-frequency motions agrees well with the calculated values. However, it
is important to include wave shortcrestedness and the correct spectral shape in the calculations. It is a tendency
that the motions is not as co-linear as
predicted by the calculations.The full
scale measurements show a
significant scatter compared to thecalculations and model test results. For
spectral peak periods less than 10
seconds, the measured low-frequency
motions in terms of standard deviation of the response normalised with H is only 0.2 to 0.5 of the model test results. For the longer wave periods, the measured response is scattered around the predicted values. The scatter of the data is believed to be caused by Wave shortcrestedness and differences in spectral shape, while the low response in the short-periodic range is believed to be caused by increased
The ratio between the maximum observed
and the standard deviation of the
low-frequency response is impossible toestablish from the time-histories
of 34
minutes duration. For this purpose, time historieS of 6 hoUrs duration have been
extracted. Analyses of this is still ongoing. Tether tension is perhaps the most important response to verify. The preliminary conclusions in this area is as follows:
The measured wave-frequency tether tensions are smaller than the design values. This is rriainly. due to the fact that the actual COG of the TLP is lower than used in the design calculations. If this is corrected for, together with corrections for spectral shape and wave shortcrestedness, the calculated wave-frequency tether
tensions agree well with the observed
values.
At the time of design of the Snorre TLP, no reliable computer code was available for
calculation of high-frequency tether responses. The design was therefore based on a conservative interpretation of model test results. The measured high-frequency tether tensions agree well with the model test results, indicating that the design is conservative in this area. The
major part of the high-frequency responses for the considered seastates are recognised as tether springing (sum-frequency excitations).
The theory
for calculation of such responses has been improved, and reasonable agreement with the observed values is obtained.damping due to current
nd wave drift
COMPARISON OF MEASURED VERSUS effects. Calculations with measured wave PREDICTED DATA spp1ra show a systematic overpredictiOn ofTether ringing received little attention when designing the Snorre TLP simply because it
was not recognised as a problem in the-industry at that time. Later re-analyses has shown that ringingwill not contribute to the extreme loads in the tethers the high
wave-frequency loads dominated the extreme loads, much because of the favourable location of the TLP COG. However, up to now the COG has been significantly lower than originally designed for, such that the TLP has been more subjected to ringing response. Significant ringing response has been observed in high, steep seastates, but with no risk of exceeding the design tether tension.
WEIGHT MANAGEMENT
Correct weight management is essential for the safety of the TLP. For operation of the Snorre TLP, so-called 'Weight Management Curves' have been established. These curves are determined by the reserves in the tether system design
wit
overstressing andminimum acceptable tension. For the intact platform, the optimal platform weight is 77200 tonnes. In this condition, the horizontal centre of gravity of the platform can accept to vary with +1- 0,7 m, and if the centre of gravity is correct, the weight can vary with +1- 1900
tonnes and still be within the acceptable limits. On Snorre, the weight management is based on 'logged weights'. This means that the total weight is establiShed from logging of weights and COG information for variable loads in addition to the weight and COG of the TLP structure itself. The logging, is performed by level measurement in all tanks, and weight cells for bulk tanks. For small tanks, or tank
where degree of
filling ismore or
lessconstant, an average value of tank content is used in the calculations. For the risers, the actual measured top-tension is used, and for weight of miscellaneous equipment and
materials on the deck, the weight status each
week is obtained by manual registration. All this information
is gathered in the ballast
control .computer, which displays the actual weighUaiid COG relative to the weight controlcurve.
The only operations that require adjustment of the weight or COG by ballasting operations, are skidding of the drilling derrick, or if large quantities of materials are taken on board in connection with drilling operations.
The ballast control computer also displays values for 'measured' weight and centre of
gravity. This is calculated based on the tension
measurements on each tether. To Obtain correct COG, corrections have to be included from static wind and current actions based on measured wind and current velocities. In calm water, the measured weight and COG should be quite accurate. It is important to note that the measured weight and COG is not used for management of the platform. This is different from some of the other TLPs. Our experience is that the logged weights and COG are more reliable than the corresponding measured values. Of course, if the measured values
should be used, the weight management
shOuld be replaced with tension management. To rely on such a system, a very robust and reliable system has to be developed.OTHER OPERATIONAL EXPERIENCE Of other operational experience related to the
platform as a TLP we may mention the
following:
Material handling onboard the TLP was not paid sufficient attention to in the layout of the deck. Direct visual insight
by the
craneoperator should be planned for
all majorlanding areas. The landing areas should be designed with bumpers, such that containers etc. can be landed against the bumper before it is put down on the deck. More attention has to be put into layout of the surrounding of the
r
landing areas to avoid damage to vulnerable eqi.iipment. The crane operators should have more realistic training on beforehand.
Experience from a floating
vessellike a
semisubmersible drilling rig is of no value, due to the large difference in motion behaviour. Human comfOrt. There has been Occasions when personnel on board has felt uncomfortable in stormy weather. This isbelieved to be caused by quite significant
vibrations in the lMng quarter due to waveinduced vibrations (ringing) or due to vibrations
caused by the
wind. Thesevibrations may be attributed to the special
design and support of the lMng quarter,
cantilevered at one end of the platform.The main problem associated with human comfort is the lack of TLP-knowledge. With a baSic course about TLP motion-behaviour and design basis, it is believed that these problems are easily sorted out. Sea-sickness has never been a problem.
Personnel safety. The platform motions have to be considered when planning maintenance operations etc. Maintenance work may take longer time on a TLP than a fixed platform due to
the need for
securing personnel andequipment. The motions are felt as
unpredictable, and very different from the
motions of a floating vessel where the motions are more harmonic.Riser protection. The Snorre TLP was
originally equipped with riser protection nets of synthetic fibre ropes on all four sides.
However, the nets were subjected to local
damage from wave action,
and frequent maintenance work was needed. Based on risk analysis, it was concluded that two of the nets could be removed. It seems as design of such nets is not adequate to sustain the loads and wear they will be exposed to, so either the design need to be improved, or the operations with supply vessels close to the TLP changed, such the riser protection nets can be avoided.Riser system. In the riser area there has
been number of minor incidents. Shortly after installation of the risers, some reduction in the top-tension occurred, due to leakage of nitrogen from the accumulators in the tensioner system. This was easily corrected,but could had led to serious consequences if it had happened in bad weather. There has also
been reported wear problems wit the nickel
plating on the
hydraulic cylindersof the
tensioners. More effort should be put into
simplifying the design of the tensionersystems.
Another area where damages have occurred, is related to antifouling sheeting put on the risers in the splash zone. This sheeting is
baked into the passive fire protection, and has fallen
off due to insufficient quality of the
bonding. This has been corrected for the new riser by improving the manufactunng procedure.On the drilling riser, all joints are connected
with bolted connections. To ensure that such a connection is functioning, it is essential that bolts get correct pretension. For this purpose,
each bolt were quipped with a devise to
monitor correct pretension. However, thisdetail was too vulnerable to damage when handling the riser joints during running and retrieval, such that a lot of the bolts had to scrapped after short use. The system is now modified such that hydraulic tensioning of
each bolt to correct tension can be performed, before they are locked off. The introduction of this tool will also shorten the installation time
of the drilling riser, which was said to be a
problem.
Wave run-up. As mentioned earlier, one of the burner booms was damaged by wave run-up. There has also been other minor damages
related to wave run-up. It is believed that a TLP with relatively large diameter vertical columns, will be more subjected to wave run-up than other types of offshore structures.
motion-behaviour of the TLP, as ft. often is moving 'towards' the waves. This should be taken into account when arranging equipment-close to the columns. This is specially important with respect to location of lifeboats and other life-saving equipment.
MODIFICATIONS OF THE SNORRE TLP
Since the Snorre TLP was installed in 1992, its has been through two large modifications. The
winter of 1993/94 a module for Alternating Water and Gas (WAG) injection was installed on the platform. The primary reason for this was to increase oil recovery. An Other reason was that it was limitations on the amount of
gas that could be sent to the Statfiord A
platform, and this was limiting the oilproduction.
Right now a more comprehensive modification
has
started. The Snorre TLP has been
selected as the platform for processing of oil and gas from the Vigdis field, a field that is located some 10 km away from the Snorre
TLP, and which will be developed with 12
subsea wells.. For this purpose a new 3 stage processing module will be installed on theTLP, with an oil production capacity of 113.000
barrels/day. The total capacity of the Snorre TLP after this modification including some additional debottlenecking will be more than 350.000 barrels/day. Not bad for a platform
that was
originally designed for 190.000barrels/day!
In addition there will also be a lot of other
modifications On the platform includingincreased water- and gas injection facilities and a number of new risers. All together the
operational weight of the deck will be
increased with some 3750 tonnes. How is it possible to install so much additional weight
on a such weight-sensitive structure as a TLP, and specially when the weight is installed so high up and out on one corner of the platform
as is the case with the Vigdis modifications? The answer to this is threefold:
The Snorre TLP had some built-in weight margins due to very strict weight control
during engineering and construction phases.
The foundations were installed well within the specified tolerances, and by using the as-installed position of the foundations it is possible to gain some additional weight
capacity.
The design basis for the Snorre TLP was conservative. By using 'state of the art'
criteria for design against minimum tension,
it is possible to gain significant weight
margins. (by state of the art is understood SLS criteria for checking of minimum
tension rather than ULS used in the original design).
After this modification, there is still capacity for the planned Snorre phase 2 modifications, and
maintaining the same operational flexibility
wrt. weight and COG variations as built into
the original design.
TLP FOR THE FUTURE
Based on the experience from the Snorre TLP, Saga Petroleum together with Aker
Engineering have started development of a
TLP for deep water applications. The development is based on environmental conditions typical for the deep water locations on the Norwegian continental shelf, and the water depths used in the studies so far have been 800 and 120Dm. The first phase of this development is now finished, and the aim was
to develop a cost-effective TLP for a deck weight of 39500 tonnes, i.e. the same deck
weight as for the Snorre TLP. The work has so
far been concentrated on the
hull, tether system and marine operations.After screening a number of concepts, both steel, concrete and hybrid solutions, a steel TLP with three columns was selected as the
most cost-effective solution. The tethers are au-welded steel tubulars, and are tied off externally. The deck is supported by an open. truss structure in the wave-zone.
In
development of the concept, we have
disregarded the traditional 'niceto hav&
design requirements which normally are introduced for a TLP because it IS physically possible to achieve. Examples of such 'deterministic' design requirements are:Damage conditions like one tether missing and on tether floOded
Requirements for change-out of tethers Monitoring of tension in all tethers Access for internal inspection of tethers. It is generally recognised, that there is no other offshore structure that is so well documented as
a TLP
wrt. full scale measurements, model testing, and otherresearch. It should. therefore be possible to design a TLP with sufficient reliability without introducing such 'deterministic' design requirements. Based on this, and the fact that the triangular TLP is a statically determined structure wrt. the loads in the tether groups, it has been possible to design a very simple
tether system, and establish
very siffiple installation procedures. For the 800 m water depth case, it has been estimated that the costof the instalJed tether System will be in the order of 60 mill USD, while the corresponding
coSt fat Snorre was nearly three time this
amount, with a much smaller water depth.Also, for the hull and deOk structure, it has been possible to considerably save weight
compared to Snorre, of 2000 and 6000 tonnes
respectively. The weight saving in the deck structure can be utilized for additiotial riser
tension that will be required in deep water.
Based on the work that is petfrmed up to
now, the triangular TLP looks as a very
promising concept, and we are continuing the development work together with Aker
Snorre Field Develpment Project UK SECTOR MUrch I ThistIe Dunlin Cormorant
\
Hutton Ninian Co'umbia Reserves per Well (MSm3) C BrentRecoverable reserves pr. Well for Snorre and other Norwegian fields
2°E NORWEGIAN SECTOR Statfjord 4.9 Snorre QTordis 3Vigdis Guilfaks Osebe 3.9 40 EOseberg
GuUfaks 1.8 Srtorre 1.3 620 N -61 °NSTATOI L 41.4000% NORSK HYDRO 8.2658 %
SAGA PETROLEUM 11.2559 % ELF 5.5106 %
ESSO 10.3323% AMERADA HESS 1.4559%
DEMINEX 10.0348 % ENTERPRISE OIL 1.4559%
IDEMITSU 9.6000% DNO 0.6888 % 210 120 46 75 117 96 Recoverable Reserves (MSm3) Area (km2) Total Wells 197 78 51 482 81 98
Water depth I Soil conditions
(m) 0 50 100 150 200 250 300 350Total Investment per Unit of Produced Oil
400 300 200
-
100-0 U (ft) 0 -200 -400 -600 -800 1000 1200 - 10-B
6
-4
2
0Oseberg Statfjord Gulifaks Snorre
1989 1976 1990 1992
Total Investment per Unit of Produced Oil
NOK/Sm3 (1988 value) USS /Bl.
500 - - 12
Statfjord Oseberg Guilfaks Snorre Snorre
Snorre field screening evaluation
z
UI>
z
UI U) UI I-Uiz
I-UI00
-SHM (1).SJ4M (1) TLP(1)ReJoc GT (1).GTSnorre TLP
GT(3)+GT(1) SP-3 (3).SP-3 (1) GT(1).SS MT (1)#SS GT (3).SS P.3 (3)+SS (1)+SP.3 (1) eloc SHM (1)4SS 2xFPS.Tanlcer (3) S S PROJECT ECONOMICS INCL DEVELOPMENT COSTS PROJECT ECONOMICS EX. DEVELOPMENT COSTSSnorre TLP Hull and Deck
Snorre Tether Mooring System
CROSS LOAD BEARING
TLP installations
300 500 600 700 800 900Oil Production Snorre TLP 1994
250 200- 150- 100- 50-1984 HU7TON 63300 ton
13579
1989 1992 1993 1995JOLUET SNORRE AUGER HEIDRUN
16600 ton 106 500 ton 66200 ton 292 000 ton
I-636m -310m -872m
--t71/
11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 5 Week no. -345m,,,,,,,,,,,, ,,/,
Snorre TLP Weight
ManagernefltQUrVe
HCG(m) 0.8 0.6 0.4 0.2Design Conditions for tether system
I1 (m) 10-5. 76000 77000 78000 79000 TLP weight (tonfles) Max offset Max tension 10 .1.5 20
100 year design curve Mm teflsion
Max weight
SnOrre TLP weight rnanagemnt
78000 77800 77600 7740Q C C . 17200 77000 76800 76600 76400Measured and logged weight December 93
Storm of 04.01.93
20- 19- 18- 17- 16- 15- 14- 13- 12- 11-10-
9-
8--7-
6-
5-10 000 yearLycar
Actual seastate 0 I - - - i 0 5 10 15 20 25 30 Tp (see) 0 10 Date Measured LoggedTLP motionS 04.0193
TLP Position trace 20 15 10 E 5 -5 -10 -5 0 5 metersTLP motions 04.01193
Total motion North
500 1000 1500 2000 2500 Time (sec) LE moon Nrth 500 .to_0o 1O0 2000 2500 Time (sec) 20 10 15
Snorre Offshore Verfication program
Wave frequency surge and sway
(St. devils)
Spectrum peak period (sec)
irreQffslore Vertication program
Low frequeny surge ad sway
(St.deviH2)
0.20 0.18 0.16 0.14 0.12 0.10 -0.08 0.06 0.04 0.02 -U I U a C C Co Ii_-C a C iD I--Arialveis D Full scale -0.00 50 I 6.0 I 7,0 ! 8.0 9.0 _I-10,0 11.0 12,0 13.0 14.0 15,0 16,0 17.0 18,0 19.0 6 7 9 10 11 12 13 14 15Spectrum peak period Cs)
0.12 0.10 0.08 0.06 0.04 0.02 0.00
Snorre Offshore Vertication program
800- 700- 600-500-P 400- 300- 200- 100-0 250 200 150 100 -50 0 5 5 6WF Tension in heaviest loaded corner (St. dev. I Hs)
9 10 11
Spectrum peak period(S)
Sflorre Offshore Vertication program
High frequency tether tension
(St. dev Iifs2) 12 13 14 15 Model tests C Full scale Design C
-- ---I
- _ -6 7 8 9 10 11Spectrum peak period (a)
15
13 14
Tether ringing Snorre TLP
190
High frequency tether tension (tonnes)
TLP wave frequency sway motion (m)
Water surface elevation W (m)
Water surface elevation N (m)
200 210 220 230 240
Time (sec)
250 260 270 280 180 190 200 210 220 230 240 250 26Ô 270 280