• Nie Znaleziono Wyników

Supersonic combustion studies I: Design, construction and performance of a high-enthalpy facility

N/A
N/A
Protected

Academic year: 2021

Share "Supersonic combustion studies I: Design, construction and performance of a high-enthalpy facility"

Copied!
30
0
0

Pełen tekst

(1)

CoA REPORT AERO NO. 200

THE COLLEGE OF AERONAUTICS

CRANFIELD

SUPERSONIC COMBUSTION STUDIES

DESIGN, CONSTRUCTION AND PERFORMANCE

OF A HIGH-ENTHALPY FACILITY

by

(2)

THE COLLEGE OF AERONAUTICS CRANFIELD

Supersonic Combustion Studies I. Design, Construction and Performance

of a High-Enthalpy Facility

by

Roy A. Cookson, B.Sc. , P h . D . , M . A . I . A . A .

SUMMARY

The alternative methods of providing a high-enthalpy stream of air for supersonic combustion studies are discussed, and the reasons given for the decision to design and construct a pebble-bed heater at Cranfield.

Much of the report is given over to the design of the facility and nec-e s s a r y instrumnec-entation. Thnec-e limiting mass-flow and tnec-empnec-eraturnec-e opnec-erating conditions a r e outlined, and details of a typical supersonic combustion t e s t -section a r e included.

Operating experience and problems a r e discussed and the calculated performance of the facility is compared with that actually obtained.

(3)

CONTENTS PAGE Summary 1. Introduction 1 2. Pebble-bed Heater 2 2.1 General Description 2 2.2 Choice of Ceramic Material 2

3 . Heat Exchanger 3 3.1 Size of Facility 3 3.2 Refractory Lining 3 3.3 Support Grate 4 3.4 P r e s s u r e Vessel 4 3.5 Heater Burner 4 3.6 Exhaust Cooling 5 4. Instrumentation 5 5. Operating Precautions 6 6. Test Section 7 7. Operating Experience 7 7.1 Performcuice 7 7.2 P r o b l e m s 8 8. Concluding Remarks 9 9. Acknowledgements 9 10. References 10 1 1 . Appendix 1. Air Mass-Flow Calculations 11

12. Appendix 2. Heat-Transfer Calculations 13 Figures

(4)

1. Introduction

The advantages of employing supersonic combustion as the mode of heat r e l e a s e in hypersonic propulsive systems have been much publicized in recent y e a r s , and it is generally recognised that the scramjet (supersonic combustion ramjet) is the only feasible air-breathing propulsive system for high flight Mach n u m b e r s .

Since the scramjet becomes clearly superior to other air-breathing systems in the flight speed range of Mach number 8 to 10, it is assumed that this will be the o r d e r of flight velocity of any first generation transport employing supersonic combustion. Hence, assuming optimum diffusion of the f r e e -s t r e a m a i r , the Mach number at entry to the combu-stor would be 3.0 to 3 . 5 , although combustion at lower values is obviously of great interest since the scramjet is likely to be in operation from the upper limit of the first stage system ( e . g . turbomachinery), up to optimum conditions. Similarly it can be shown that for the likely operating altitude (100,000 feet to 140,000 feet), the static p r e s s u r e within the combustor will be of the o r d e r of atmospheric.

F r o m the above it is possible to specify the range of test conditions required, in o r d e r that conditions within the scramjet combustor be r e a l i s t -ically simulated. Briefly, these test conditions indicate the need for combustor inlet air with the following properties,

(a) Mach number from 2.0 to 3.5

(b) Static p r e s s u r e of about 15 to 30 p . s . i . a b s .

(c) Static t e m p e r a t u r e greater than that required for the auto-ignition of the fuel ( e . g . 580°C for hydrogen).

The combination of the above properties indicates a need for a supply of a i r at a stagnation t e m p e r a t u r e of at least 1800°K, and if possible several hundred degrees higher, and at a stagnation p r e s s u r e of at least 120 p . s . i . a b s . To produce t e s t - a i r at these stagnation temperatures and p r e s s u r e s , there a r e four main types of installation possible:

(a) A r c - h e a t e r (b) Shock-tube

(c) Vitiated-air system

(d) Regenerative heat exchanger.

At first sight the use of an a r c - h e a t e r for producing high-enthalpy air is very attractive, for example, the process is clean and easily controlled. Unfortunately, the existing power lines at Cranfield would not c a r r y the added burden.

In considering the shocktube, one is faced with a choice between t r a n s -ient and steady-state testing conditions, that i s , between running times of

milliseconds or minutes. In view of the type of r e s e a r c h programme envisaged and of the excellent r e s e a r c h facilities available in the Propulsion Department at Cranfield (for example the c o m p r e s s e d - a i r supply), a steady-state type of facility was decided upon. This would obviously set an upper limit on the t e m p e r a t u r e to which the supply a i r could be raised, a limit not imposed

(5)

t r a n s f e r and mechanical integrity will play so large a part, the view of ref-erence (1) is supported.

In the vitiated-air system, fuel is added to the a i r - s t r e a m and ignited, and the heat so released r a i s e s the enthalpy of the total flow. Oxygen is l a t e r added to the s t r e a m to replace that consumed during combustion. The resulting high-enthalpy gas s t r e a m can then be said to be a mixture of air and combustion products (for example, water vapour). In this particular application where t h e r e a r e so many unknowns, it was thought that the introduction of further complexities, such as the determination of the t h e r m o -dynamic properties of the mixture, would make the use of the vitiated-air system undesirable. The final choice therefore was for a regenerative heat exchanger of the pebble-bed type.

2. Pebble-bed Heater

2.1 General Description

The layout of this type of regenerative heat exchanger is shown in F i g u r e 1. As can be seen, the facility consists of a p r e s s u r e vessel lined with several grades of refractory materials and with a bed of randomly packed refractory pebbles at its centre, as illustrated by Figures 2a and 2b,

The ceramic elements a r e heated by means of the kerosine burner shown mounted in the roof of the h e a t e r . The combustion products from this burner a r e blown down through the pebble-bed and a r e then exhausted to atmosphere. The heating cycle usually l a s t s three to four hours until the required t e m p e r -ature distribution is obtained. At this point the kerosine burner is closed off, the exhaust valve closed and t e s t - a i r , supplied from the compressor house at the required p r e s s u r e , is passed upward through the bed. This t e s t - a i r , heated by the pebbles during its passage through the bed, is then discharged through the appropriate t e s t - s e c t i o n .

2. 2 Choice of Ceramic Material

It is obviously desirable for the air entering the test-section to be at the highest possible stagnation t e m p e r a t u r e , since it is the available stagnation t e m p e r a t u r e which is likely to limit the operating Mach number at the t e s t

-section. With this consideration in mind this facility was originally envisaged as utilising zirconia elements. The maximum operating temperature of

zirconia is in the region of 2500OC. Unfortunately, it was found that the cost of zirconia bricks and pebbles for the size of facility contemplated, would be prohibitive.

The obvious alternative to zirconia was alumina, for although alumina has a maximum operating t e m p e r a t u r e of only 1800°C, the cost of producing the lining and pebbles in alumina was found to be only about one-third of the cost in zirconia.

Several manufacturers were approached for their estimate of cost and recommendations with regard to the design of a pebble-bed heater. It soon

(6)

3. Heat-exchanger Design 3.1 Size of Facility

In considering the size of facility required, it is n e c e s s a r y to take into account both the m a s s flow of air which is to be heated and the temperature to which it must be r a i s e d . The limit in air mass-flow which can be heated in any particular facility is reached when the aerodynamic lift force acting on each pebble exceeds the pebble weight and the pebbles "lift-off". This limit-ing m a s s flow of a i r can be calculated in the manner indicated in Appendix 1, but it is obvious that all other things being equal, the limiting m a s s will be proportional to the bed a r e a .

The t e m p e r a t u r e to which the air is raised during its passage through the bed is obviously a function of the residence time within the bed ( i . e . bed depth), and the physical properties of the bed such as the pebble diameter. This consideration is dealt with in the section on heat-transfer, Appendix 2.

The bed dimensions decided upon from economic as well as performance considerations, were a diameter of 30 inches and a bed depth of 90 inches. This volume gave a pebble m a s s of 2 tons. The bed diameter was later modified to 28 inches when it was discovered that a considerable saving in cost could be made by accepting this dimension. This was due to the fact that moulds for the brick lining of a 28 inch diameter bed were already in existence. Once this inner dimension was fixed, calculations for the heat t r a n s f e r away from the bed in a radial direction could be made, and r e q u i r e -ments for the outer l a y e r s of refractory, and for the shell dimensions fell naturally into place.

A pebble diameter of 0.5 inches was finally decided upon from all of the considerations listed above. Obviously, improved heat transfer could be obtained with a s m a l l e r diameter pebble but possibly only at the expense of mechanical integrity. The pebbles were purchased from the Aluminium Company of America (ALCOA) as supplied in this country by Hydronyl Ltd. The Alcoa pebbles were considerably cheaper than those supplied by any other manufacturer.

3.2 Refractory Lining

The insulating lining is made up of individual units in three layers as shown in Figure 1. The inner layer is constructed of Norton RA 5190 high density alumina in small interlocking shapes. The lower half of this layer is self-supporting from the floor and the upper half is supported from the steel ring welded inside the p r e s s u r e v e s s e l . Thus the lower elements do not have to support all of the weight of the roof lining. The RA 5190 is backed by a layer of Norton RA 4058 bubble insulating alumina, and behind the RA 4058 is a layer of low-temperature firebrick.

(7)

4

-Allowance for the appreciable thermal expansion of the lining is left between the third layer and the steel shell, and this space is filled with a resilient cement Detrick MW 711.

Figure 3 gives an overall impression of the size and layout of the facility.

3.3 Support Grate

The support for the pebbles is shown in Figure 4 . This consists of 1" diameter Incaloy D . S . round b a r s supported by four Incaloy D.S. support b a r s bolted together in the configuration shown. This total assembly is mounted into a support ring which in turn is set in a cast base of Norton 33-1 castable cement, and through which the load is transnaitted to the p r e s s u r e v e s s e l . Stress calculations made on the Incaloy support b a r s indi-cate that they will withstand the load at temperatures up to 1000°C. More importantly, creep calculations indicate that the bars have a life expectancy of up to 10,000 hours operation providing that their temperature does not exceed 900°C.

3.4 P r e s s u r e Vessel

The p r e s s u r e vessel was designed to encompass the pebble-bed and the three l a y e r s of refractory brickwork with a necessary allowance for thermal expansion. Although the heater was to be used at a p r e s s u r e of 165 p . s . i . a b s . for the early supersonic combustion t e s t s , the steel shell was designed to withstand a p r e s s u r e of 265 p . s . i . a b s . which should be the available air supply at a later date. The p r e s s u r e vessel was constructed to B.S.1500 1958 Class 1, and the steel used in the construction was to B . S . 1501-151, Grade C. Heat transfer calculations indicated that the shell would operate at 450°F, which value is well within the 700°F limit specified. F r o m Figure 1 it can be seen that a steel support ring is welded to the inside of the shell to support the roof b r i c k s .

The large support ring required to hold the Incaloy grate bars was transported to the shell manufacturers ( M e s s r s . A . J . Riley Ltd. of Batley) and was located within the vessel before it was completed,

3. 5 Heater Burner

Reference (2) describes a regenerative heat exchanger and a h e a t e r -burner which utilizes propane as a heating fuel. Propane is obviously a very

good fuel for this type of use, as it is easily ignited and easily controlled. Unfortunately, propane is expensive to burn in the quantities required by the above facility. Added to t h i s , there is an existing kerosine supply to each of the test cells in the Propulsion Department. Thus it was decided to construct a k e r o s i n e / a i r burner capable of heating the mass of pebbles and lining. This burner was based upon the '^Shell' toroidal burner design as shown in reference (3). With this type of burner a proportion of the inlet a i r is passed outside the burner head with an imparted swirl. The remaining a i r is passed through the burner head and is used to atomize the fuel.

Ideally, the resulting flame should be intense and toroidal in shape, but in practice it was found that the machining and location of the atomizing slit was

(8)

very critical, much more so than in the original kerosine/oxygen toroidal b u r n e r , A mock-up of the combustion space in the pebble-bed heater was built and extensive t e s t s carried out on burner adjustments and flow r a t e s . The usual kerosine flow-rate is within the range 12 to 18 gallons per hour.

The burner design currently being used is illustrated by Figure 5. The

whole construction is of b r a s s which i s , of course, heavily cooled since it is left within the pebble-bed heater at all t i m e s .

The kerosine burner is ignited by means of a spark-ignited propane torch which is withdrawn after a kerosine flame is initiated.

3.6 Exhaust Cooling

Towards the end of the heating-up cycle the hot gases leaving through the outlet at the bottom of the unit a r e at a temperature near to 900°C. However, as the control valves used in the existing a i r - l i n e s will not tolerate t e m p e r a t u r e s higher than 200°C, it is obvious that the exhaust gases must be cooled. This is brought about by means of cooling water sprays inside the exhaust pipe. Cooling water is forced at 150 p . s . i . , through two fuel atom-i z e r s whatom-ich produce two conatom-ical sheets of coolatom-ing spray, one poatom-intatom-ing upstream, and the other downstream. The exhaust gas temperature is monitored by means of two thermocouples, one a s a probe in m i d - s t r e a m and the other as a surface plug in the wall of the exhaust pipe,

4. Instrumentation

The t e m p e r a t u r e s of the pebbles, brickwork and grate support a r e monitored by means of the five platinum/platinum-13% rhodium and twenty-one chromel/alumel thermocouples, located in the positions indicated by F i g u r e 6. Two chromel/alumel thermocouples a r e welded to the outside of the steel shell and two further chromel/alumel thermocouples a r e used to indicate the exhaust duct t e m p e r a t u r e during the heating-up cycle.

The platinum thermocouples a r e cemented into holes, drilled ultrasonic-ally, in alumina pebbles. It is expected that these thermocouples will fail cifter a few runs but it is hoped that sufficient operating experience will be gained during this period. After the thermocouples have failed, an indication of the operating temperature can still be obtained from the Land optical pyrometer which m e a s u r e s the pebble surface temperature and which is l o c -ated as shown in Figure 6.

The optical pyrometer and thermocouple readings a r e all recorded by means of a Honeywell multi-point potentiometric chart r e c o r d e r . The full cycle of this r e c o r d e r takes approximately 2 | minutes to complete, but this period is quite reasonable in the context of the several hours taken to heat up the facility.

As failure of the cooling water to the several cooled points would be likely to lead to the failure of the complete r i g , care has been taken to indicate the cooling water p r e s s u r e at each point. P r e s s u r e switches have

(9)

6

-also been fitted to these points so that a warning light will indicate failure of the cooling water p r e s s u r e , and as a further safeguard a Klaxon has been installed to indicate the failure of the water p r e s s u r e at any of the cooled sections.

The h e a t e r - b u r n e r air supply, both atomizing and secondary, and the kerosine supply, a r e all monitored in the usual fashion with the aid of mano-m e t e r s , orifice plates and r o t a mano-m e t e r s ,

Air at high p r e s s u r e for test runs is metered by means of an orifice plate and the mass-flow is indicated both by manometer and by a transducer giving a permanent record on a chart r e c o r d e r .

Some difficulty has been experienced in accurately assessing the t e m p e r -ature of the outlet t e s t - a i r . At the high temper-atures experienced, the cor-rection for radiation, conduction and velocity for a probe thermocouple is quite l a r g e . Even at the relatively low temperatures (~ 1850°K) produced for

our early experiments, the recommended maximum for the continuous use of

platinum/platinum-13% rhodium has been exceeded with a resulting drift in calibration. Work is going on in constructing a l i n e - r e v e r s a l pyrometer for use when the maximum thermal potential of the facility is realised. A sodium injector and quartz viewing windows have already been incorporated into the existing transition section between the heater outlet and the test section. This pyrometer will utilize a photomultiplier as the sensing device and the final ^ reading will be taken as the point of balance between the radiation at 5890-6A from the background continuum provided by a tungsten strip lamp, and the intensity of radiation from the sodium injected into the s t r e a m . Unfortunately this technique cannot be used for our e a r l i e r t e s t s since the air temperature for these runs is below the lowest level at which the l i n e - r e v e r s a l system will o p e r a t e . In the meantime a further thermocouple pair a r e to be tried, namely iridium-40% rhodium/iridium. This thermocouple has a recommended maxi-mum continuous operating t e m p e r a t u r e of 2000°C but is unfortunately very expensive and very brittle.

5. Operating Precautions

In the last section there is a description of precautions taken to warn of the failure of the cooling water to the various cooled points. Two further safeguards against the failure of the facility a r e described below.

a) Blow-Off Valve

With the water-cooled kerosine burner remaining within the pebble-bed heater at all t i m e s , there is some danger of a rapid r i s e in heater p r e s s u r e if the burner cooling jacket failed and cooling water was suddenly discharged on to the hot pebbles. As a safety precaution, a blow-off valve has been installed at the bottom outlet from the bed, and the result of such an

(10)

b) Stand-By Air

If the air supply should fail, for any reason, at a time in the heating-up cycle when the thermal storage approached a maximum, there would be a very r e a l danger that the support bar temperature would exceed the maximum allowable, before some of the energy could be blown away. To allow for this possibility, provision has been made for the storage of a quantity of a i r to be used as blow-down a i r .

6. Test Section

This particular facility obviously has a number of applications to comb-ustion or high-speed flight r e s e a r c h , and the number of useful experiments which r e q u i r e a s t r e a m of high-enthalpy air increases from year to y e a r . However, the purpose for which this pebble-bed heater was constructed was to c a r r y out r e s e a r c h into supersonic combustion, and the first test section is shown in Figure 7.

This test section is in the form of a Mach 2 convergent-divergent axisymmetric nozzle with a central fuel injector. The nozzle runs choked at a stagnation p r e s s u r e of 113 p . s . i . a. and discharges at a static p r e s s u r e of 14.7 p . s . i . a . Fuel, hydrogen or methane, is injected into the hot Mach 2 a i r s t r e a m and ignites spontaneously. Studies are then made of the mixing, ignition and combustion of the mixture.

The problem of cooling the stainless steel nozzle and injector presented some difficulty. In particular, boiling occurred in the central injector until the cooling water p r e s s u r e was increased to 400 p . s . i . The heat-transfer r a t e in the region of the throat has been calculated and found to be at the high value of 1.8 X 10 B . T h . U ' s / f t / h r .

In these early experiments a water-cooled transition section has been used, reducing the exit diameter from 5 , 5 " diameter to the 3 " diameter of the test section. Because of the obvious heat loss to this section an altern-ative transition section is being cast from high grade alumina and will be positioned within the outlet branch of the heater. A simple calculation indicates that this alternative should result in an increase of approximately 50°C in the outlet air t e m p e r a t u r e ,

7. Operating Experience 7.1 Performance

T r i a l runs were begun at relatively low temperatures of approximately 1400°K and for heating-up periods of only about 1 hour. However, as

(11)

operating experience was gathered and the facility was seen to function well, the operating temperature and the heating-up times were increased. The full potential of 2070°K has still not been reached, firstly because this is not n e c e s s a r y for our early t e s t s , but chiefly because this temperature cannot be reached without either pre-heating the kerosine burner a i r or operating for part of the heating-up cycle on oxygen instead of a i r .

Air outlet t e m p e r a t u r e s of approximately 1850°K have been attained, and have proved to be sufficient to achieve ignition of hydrogen at the nozzle exit. Figure 8 is an example of the air outlet temperature obtained during a

typical run, and of the variation of outlet temperature with running t i m e . The t e m p e r a t u r e - t i m e profile shown in Figure 8 is for the case where the bed is heated up from cold. If the pebble-bed was warm at the beginning of the heating-up cycle, the t e m p e r a t u r e distribution in the pebble matrix would be severely modified, and this would probably result in a reduced out-let air t e m p e r a t u r e . The temperature gradient shown at the beginning of the test run is due to heat loss by radiation frona the top layers of pebbles during the period between the end of the heating-up cycle and the beginning of blow-down,

The running times shown a r e for an air mass-flow of 1.7 l b / s e c , obviously the running time available at any particular temperature would be increased if the mass-flow was decreased. Similarly if a greater mass-flow was passed through the bed (implying an increased operating p r e s s u r e ) , then the tenaperature-time gradient would be steeper,

A comparison of the actual bed temperature distribution and air outlet t e m p e r a t u r e with the calculated values, shows a reasonable agreement, The difference shown is due to the thermal storage capacity of the brickwork which has not been taken into account in the calculations.

7.2 Problems

The first problem connected with the operation of the facility a r o s e when a local maximum in the shell t e m p e r a t u r e was observed at a point about mid-way down the shell. Although this maximum did not exceed the allowable t e m p e r a t u r e for the shell, it was nevertheless thought to be undes-i r a b l e . It was found to correspond to the posundes-itundes-ion of the steel support rundes-ing welded to the inner surface of the vessel and was obviously due to the enhanced conduction of heat through the support ring. To reduce the shell t e m p -e r a t u r -e locally, a narrow wat-er cooling jack-et was attach-ed to th-e outsid-e of the heater shell in the region of the support ring. This m e a s u r e was found to be effective but as an added safeguard, two more thermocouples were spot-welded to the outside of the steel shell.

Our second cause for concern a r o s e when the pebbles "lifted off" at the beginning of one of the fullscale t e s t s . This occurrence was as m y s t i -fying as it was drastic since the bed p r e s s u r e was well below the operating p r e s s u r e at the t i m e . Upon investigation it was found that water, which had been used to cool the exhaust g a s e s , had been trapped in the outlet pipe. Thus, when the cycle was reversed this water was carried into the bottom of the pebble-bed by the flow of t e s t - a i r . The resulting sudden expansion of

(12)

steam so produced was equivalent to a mass-flow far g r e a t e r than the maxi-mum allowable. Fortunately the annular throat of the test-section has a dimension less than the pebble diameter, so that pebbles were not blown over the surrounding countryside. Even so, the outlet pipe of the heater was choked by pebbles, and this meant that the test section had to be removed and the pebbles pushed back into the main body of the heater before the test could continue.

The most recent of the problems associated with the operation of the facility still lacks a solution. This takes the form of severe cracking of some of the lining b r i c k s . This phenomena is in no way connected with over-heating of the bed, but has all the appearances of thermal shock. The man-ufacturers a r e still investigating this occurrence but have stated that it has not taken place in any of the U . S . A . facilities for which they have supplied the c e r a m i c s . The bricks shown cracked in Figure 9 a r e not load-bearing m e m b e r s and have been replaced as they a r e , for further test r u n s. If this problem is due to thermal shock it is surprising, since the bricks lower down the bed a r e subject to greater tenaperature gradients yet remain undam-aged.

8. Concluding Remarks

A regenerative heat exchanger has been designed and constructed, and has been used successfully for r e s e a r c h into supersonic combustion.

The facility has been operated at conditions of 1850°K, 120 p . s . i . and at an air mass-flow of 1.7 l b / s e c , and there would appear to be no reason why these conditions should not be raised to 2050°K and 250 p . s . i . with an a i r mass-flow of at least 2 l b / s e c when required.

The performance of the heat exchanger in t e r m s of the t e m p e r a t u r e - t i m e curve actually obtained, has been compared with the predicted t e m p e r a t u r e -time distribution ( i . e . temperature "droop"). It is seen that the heat exchanger performance obtained in practice is close to the theoretical value for short durations, but that the temperature droop is far l e s s than that predicted for runs of longer duration. This bonus in performance is assumed to be due to the thermal storage capacity of the alumina lining to the pebble-bed,

9, Acknowledgements

Acknowledgement must be made of the considerable assistance given at every stage by Shell Research Ltd. , of Thornton, Cheshire, and in particular by D r . C,G, Haupt of that establishment,

(13)

10 -References SWITHENBANK, J . TROUT, O . F . J r . BAGGE, L . P , SPIERS, H . M . STEWART, P . A , E , , & BARRATT, B . M , SPIERS, H . M . SCHUMANN, T , E , W , LANCASHIRE, R . B . , LEZBERG, E . A , , & MORRIS, J , F , JOHNSON, J , E .

"Experimental Investigation of Hypersonic Ramjets".

Third International Congress of the Aeronautical Sciences, Stockholm, August, 1962.

"Design, Operation and Testing Capabilities of the Langley 11 Ceramic Heated Tunnel".

N . A . S . A . Tech. Note D-1598. February, 1963. "Development of the Shell Toroidal Oxygen-liquid Fuel B u r n e r " . Journal of the Institute of Petroleum, Vol. 48, No. 468, December, 1962. "Technical Data on F u e l "

5th Edition, p . 100.

"A Design Manual of Pebble Bed Regenerators for a Hypersonic Facility"

Bristol Siddeley Engines Ltd. , Ramjet Test

Engineers Department, Report No. 119, April, 1964. "Technical Data on F u e l "

6th Edition.

"Heat Transfer; A Liquid Flowing through a Porous Medium". Journal of the Franklin Institute, Vol. 208, 1929.

"Experimental Results of a Heat-Transfer Study F r o m a FuU-Scale Pebble-Bed Heater"

N . A . S . A . Tech. Note D-265. Lewis Research Centre, March, 1960.

"Regenerator Heat Exchangers for Gas Turbines" R. & M. 2630, A . R . C . 1952.

(14)

1 1 . A P P E N D I X 1,

A i r M a s s - F l o w C a l c u l a t i o n s

A s t h e c o m p r e s s e d a i r supply in t h e P r o p u l s i o n D e p a r t m e n t i s m o r e t h a n a d e q u a t e f o r t h e p u r p o s e of t h e p r o p o s e d s u p e r s o n i c c o m b u s t i o n s t u d i e s , t h e p r e s s u r e l o s s , a s s u c h , t h r o u g h t h e p e b b l e - b e d i s of no i m m e d i a t e c o n c e r n . H o w e v e r , t h e p r e s s u r e l o s s p e r unit depth of t h e bed is a l s o an i n d i c a t i o n of t h e lift f o r c e s o p e r a t i n g on t h e p e b b l e s , and t h e r e f o r e l i m i t s t h e a i r m a s s - f l o w which can p a s s t h r o u g h t h e bed without pebble "lift-off" o c c u r r i n g . R e f e r e n c e 4 g i v e s t h e p r e s s u r e d r o p p e r foot, t h i c k n e s s of a g r a n u l a r bed a s : -48p V^ P = o T s " Pounclals/ft /ft , . (1) dp(Re) • w h e r e p = p r e s s u r e d r o p p e r foot ( a l s o w r i t t e n a s —f-) p = g a s d e n s i t y S , . j_ 1 -J. /Volume flowing p e r s e c , V = a p p a r e n t g a s v e l o c i t y ( r—r °—*- ) D 6 Q cljr6cl d = pebble d i a m e t e r P R e = Rejmolds n u m b e r b a s e d upon p e b b l e d i a m e t e r , T h e a b o v e c o r r e l a t i o n h o l d s f o r a s o l i d s content \ = 0 , 6 , w h e r e A. i s defined a s t h e '—,———^ — ^ . F o r g r a n u l a r m a t e r i a l s with i r r e g u l a r bulk d e n s i t y ^ ^ s h a p e s t h i s v a l u e of 0 . 6 i s found t o b e r e p r e s e n t a t i v e , but f o r s m o o t h

s p h e r e s t h e bed will s e t t l e down to a v a l u e of X a p p r o a c h i n g t h a t e x p e c t e d f o r " p e r f e c t p a c k i n g " , i . e . X = 0 , 7 , R e f e r e n c e 4 i n d i c a t e s t h e u s e of a c o r r e c t i o n f a c t o r to allow f o r t h e c h a n g e in X. T h i s i s t a k e n to be equal t o 3 . 3 f o r t h e p u r p o s e of t h e s e c a l c u l a t i o n s , E q u a t i o n (1) i s a l s o l i m i t e d t o t u r b u l e n t c o n d i t i o n s , f o r t h i s c o n f i g u r -a t i o n t h i s i s i n t e r p r e t e d -a s b e i n g f o r flows with R e y n o l d s n u m b e r g r e -a t e r t h a n 4 0 0 . T h e c a l c u l a t e d R e y n o l d s n u m b e r b a s e d upon t h e pebble d i a m e t e r w a s found to be 450 f o r t h i s f a c i l i t y .

(15)

12

-P V d p

and since Re = —° where M is the dynamic viscosity of the g a s . '^^ g , 7 . 6 7 . W ^ • « ^ , 0 - ^ ^ L „ 3 . 7 , 1.15 p .D .dp g (3)

This method is described in g r e a t e r detail in Reference 5 which also contains plotted curves of the various power t e r m s ,

F r o m a consideration of the p r e s s u r e drop per unit bed depth, an

evaluation of the ratio of the lift force to pebble m a s s must be made, since it is at the point where these two quantities become equal that fluidization will occur,

F o r perfect packing it can be shown that the ratio lift force = Ag 1.655 pebble m a s s L p . lift force ^ g g ,c\ •• pebble m a s s , 1.15 ^ 3 . 7 * ' ^ ' p . p .d .D P g P

In practice a value of 0.5 for the lift/mass ratio has been found effect-ive and Figure 10 is a plot of the allowable a i r mass-flow for varying p r e s s u r e s and t e m p e r a t u r e s with the value of the lift/mass ratio taken as equal to 0 . 5 .

Reference 6 quotes an alternative correlation by Leva which appears to have a wider range of application than that given above. However, for this particular application mass-flows calculated from both correlations a r e s i m i l a r .

In general the various assumptions made all tend to be on the conserv-ative side, which is as it should be, considering the enormous stored energies involved.

(16)

12. APPENDIX 2.

Heat-Transfer Calculations

Two types of heat-transfer calculation were n e c e s s a r y for the design of this high-enthalpy facility; (a) s t r u c t u r a l , and (b) performance. The first set of calculations were of the orthodox conductivity type, and were n e c e s s a r y for an estimate of the thickness of insulation to be made, in o r d e r that the work-ing t e m p e r a t u r e of the steel shell could be maintained within reasonable bounds. This form of calculation is straightforward and need not be recorded h e r e . It is interesting to note however that the shell t e m p e r a t u r e did not reach the calculated value. This is most probably due to steady-state heat-t r a n s f e r condiheat-tions being assumed.

The second type of heat-transfer calculation required was n e c e s s a r y for deriving the rate of heat-transfer from the pebble matrix to the a i r flowing, and hence for calculating values of the outlet air temperature as a function of the blow-down t i m e . It is possible to treat this problem in t e r m s of finite-difference relationships as in Reference 5. However, this method is laborious and a reliable approximation known a s the Schumann method is available in Reference 7. Lancashire et al in Reference 8 have used an extension of the Schum.ann method, together with calculated p a r a m e t e r s from Reference 9, in o r d e r to determine the heat-transfer coefficient h for

particular sets of conditions.

In the design of this pebble-bed heater realistic values of h were assumed and used in the Schumann method to calculate t e m p e r a t u r e - t i m e variations at certain points down the bed and to determine the t e m p e r a t u r e -time relationship for the outlet a i r . By comparing the calculated relationship with that derived experimentally, the accuracy of the assumed heat-transfer coefficient can be determined.

SCHUMANN METHOD

This method is based upon several simplifying assumptions; (a) Homogeneous pebble matrix

(b) Incompressible flow

(c) Constant fluid specific heat

(d) Constant and uniform fluid velocity

(e) Conduction in the radial direction is infinite (f) Conduction in the direction of flow is negligible

(g) Thermal diffusivity of the matrix is assumed large and hence the only resistance to heat-transfer between pebbles and air will be in the film.

(17)

14 -„ h A x and Z = . . :j- . . (7 m j Cp^ L w h e r e h = h e a t - t r a n s f e r coefficient A = h e a t - t r a n s f e r s u r f a c e a r e a in bed m = m a s s of p e b b l e m a t r i x a m , = m a s s of fluid r e s i d e n t in t h e bed m . = m a s s - f l o w r a t e of fluid Cp = s p e c i f i c h e a t of solid Cp = s p e c i f i c h e a t of fluid t = t i m e e l a p s e d f r o m b e g i n n i n g of blow-down X = d i s t a n c e f r o m p l a n e of e n t r y L = t o t a l bed depth F r o m c o n s i d e r a t i o n of a n e l e m e n t of t h e m a t r i x , an e n e r g y b a l a n c e which i n c l u d e s t h e c o n t r i b u t i o n due to c o n v e c t i v e h e a t - t r a n s f e r , l e a d s to t h e following d i f f e r e n t i a l e q u a t i o n s . . . (8) aTg 8 T ö T j dz = ^ f -= '^B ^B - ^ i . . (9) w h e r e T i s t h e b e d t e m p e r a t u r e a and T , i s t h e fluid t e m p e r a t u r e .

T h e s o l u t i o n of t h e above e q u a t i o n s i s q u i t e lengthy but l e a d s to t h e following e x p r e s s i o n , T - T ^ 1 ^2 -z - ( Z + T ) » f = e + e h_ h ^ B i - '^^1 . ^=0 B=l B r + s z T s l ( r + s ) l (10)

w h e r e t h e s u b s c r i p t s 1 and 2 i n d i c a t e c o n d i t i o n s at t h e beginning and end of t h e t i m e i n t e r v a l r e s p e c t i v e l y ,

If 0, = T R - Tf

(18)

^B, - T ,

1 ^2 ^ T

^ ^ ~ \ • ' • ^ - • • < " '

Solutions of the above expression have been calculated for a range of Z and T values and a figure has been constructed with coordinates of T and AT^

- — and with lines of constant Z . ^1

Hence for a particular set of conditions and predetermined time intervals ATf

T and Z values can be calculated and by interpolation, —r— can be d e t e r m -med,

Calculation of the gas outlet t e m p e r a t u r e involves some advanced know-ledge of the t e m p e r a t u r e distribution in the pebble matrix, o r at least the need to make a good guess. F o r the t e m p e r a t u r e - t i m e curve given in Figure 8 the matrix t e m p e r a t u r e distribution was approximately constant at 1850°K for the top 5 ' - 5 " of the bed, with a linear variation from 1850°K to 350°K for the bottom 2 ' - 0 " of the bed,

F o r the purpose of the above calculations the pebble-bed is considered to be divided into convenient sections, in this instance l*-0" deep, and the gas t e m p e r a t u r e at the inlet and outlet of each section is calculated, up to the point where it emerges from the top of the bed. This process is repeated for time intervals from 1 to 20 minutes.

The calculated t e m p e r a t u r e - t i m e distribution, determined in the manner outlined above, is compared with the measured distribution and the process repeated for different values of the heat transfer coefficient h, until a r e a s o n -able agreement is obtained. Figure 11 shows a comparison of the measured outlet t e m p e r a t u r e with the calculated distribution based upon a value of 10 CHU's/ft C for h. The calculated distribution is not strongly dependent upon h but the agreement shown in Figure 11 is the closest which could be obtained.

This value of 10 CHU»s/ft °C is considerably l e s s than that determined from the correlation suggested by Reference 8,

2 / 3 _ r. . r> - 0 - 4 3 7

S^P^ "^ = 0.4 Re

where S^ is the Stanton number ( / O . C p )

P is the Prandtl number ( — 7 ^ — ^ )

r k g

2 G is the specific m a s s flow (lb/ft s)

(19)

16

-k is the thermal conductivity.

2

F r o m this correlation a value of 15.8 CHU's/ft °C is obtained for the Conditions under consideration.

2

The value of 10 CHU's/ft °C for h is a mean value for the bed and must contain some contribution from the surrounding alumina lining. It is suggested that it is this contribution from the lining which leads to a smaller measured t e m p e r a t u r e droop over the longer running t i m e s , than that which was calcul-ated.

(20)

TOP OF BED WATER COOLING SUPPORT RING THERMOCOUPLE OUTLET TEST SECTION RA 5190 RA 4058 PIREHRICK FIREBARS GRATE SUPPORT

C0I.IBUSTI0N PRODUCTS EXHAUST AND TEST AIR INLET

(21)

F I G U R E S 2a and 2 b . VIEWS O F T H E CERAMIC LINING O F T H E P E B B L E - B E D H E A T E R AND O F T H E P E B B L E MATRIX

(22)
(23)
(24)
(25)

OPTICAL PYROMETER NOTE NQ2 THERMOCOUPLE POSITION AT 9CP TO NQI A N D 3 AND AT SAME LEVEL. KEY n ft/ft. i3%Rtv O TIVT2 POSITION OF THERMOCOUPLES

(26)

COOLING WATER OUTLET

"0" RING SEAL

HYDROGEN INJECTOR

COOLING WATER INLET

HYDROGEN INLET

(27)

1900

1800

1700

1600

^

r

-r

. t .1 .

^

TBDE REQUIRED TO REACH M/OOO.IUl,!

OPER/iTING TEMPERATURE, DEPEI-DING

UPON DELAY BE'.l'WlffiN HEATH^IG-UP

AND BLOW-DOM CYCLES

^ ^ ^

OPERATING CONDITIONS f ^'^SSUEE 113 p.s.i.

l MASS-FLOW 1.7 Ib/a

1 X . 1 . > i 1 1 . 1 • 1 . • . , 1 . 1...

^

1 1

6 8 10 12 llf RUNNING TBIE (MINUTES)

16 18 20

FIGURE 8. VARIATION O F O U T L E T AIR T E M P E R A T U R E WITH BLOW-DOWN TIME

(28)
(29)

;^

e

^.0-co

2.0

400 800 1200 1600

AIR TOTAL TEIffERATURE (K)

2000 2400

FIGURE 10, MAXIMUM ALLOWABLE AIR MASS FLOW THROUGH BED

(30)

1600 _

OPERATING CONDITIONS

[

PRESSURE 113 p.s.i. MASS-FLOW 1.7 Ib/s

-i ' • L. _i L.

8 10 12 14 16 18 20

RUNNING TBIE (MINUTES)

F I G U R E 1 1 , COMPARISON O F CALCULATED AND MEASURED AIR O U T L E T T E M P E R A T U R E S

Cytaty

Powiązane dokumenty

Mit społeczny kresów wschodnich we współczesnej prasie polskojęzycznej na Ukrainie: analiza

Wildlife Strikes to Civil Aircraft in the United States 1990–2016; Federal Aviation Administration National Wildlife Strike Database, Serial Report Number 23; Federal

(Gn 1, 31): in Psalms we see that all created things glorify their creator. And yet this idyllical picture is put to question by the fact of the persistence of evil in the

Fundusze przedakcesyjne oraz fundusz wsparcia Unii Europejskiej miały dotychczas jasno sprecyzowany, niezmienny w dłuższym okresie charakter dla dotych- czasowych

De reinigingperformance van een bandschraper wordt gemeten door de hoeveelheid vastgeplakte mors aan de band te meten, nadat de band de beide schrapers is gepasseerd.. Dit wordt

Trzeba pamiętać, że dyrektor generalny poczt był podporządkowany Komisji Rządowej Spraw Wewnętrznych, a później Departamentowi Poczt w Petersburgu, a więc był zara­

With external data we mean data external to the GOCE gradiometer, not necessarily external to the GOCE satellite: the GOCE SST data is data independent of the gradiometer and

This test facility provides the possibilities to test different blade scraper designs with different operating conditions like varying belt speeds, moisture contents, different