Removal and Abandonment of Offshore
Platform Topsides including the Toppling
Alternative and Costs
N. G. Boyd
Taylor Woodrow Offshore Ltd
SYNOPSIS
There are in European Waters approximately 215 fixed steel platform installations. many of which are quite
small and weigh only hundreds of tonnes. There are also 18 concrete platforms. At some time in the future
these installations will have to be removed partially or totally. The first part of thispaper reviews the extent of
work necessary to remove the 'topsides' of such platforms. It describes the work involved in
preparation for
removal and abandonment and the details of executing the work. The paper also briefly considers the
possibility of demolishing steel platforms at their installed site by toppling them to the sea bed, where water
depth permits this kind of operation. The final part of the paper gives an indication of the costs that will be
incurred in removing and abandoning a platform.
INTRODUCTION
The topsides of platforms generally comprise a varying
number of modules or packages put into place by large crane
vessels at the offshore location. A module support frame or
deck is placed on top of the substructure to support the
modules. Recently super-heavy-lift vessels are becomingavailable and integrated decks are now being designed weigh-ing 5000t and more.
Some concrete base platforms were constructed in a
differ-ent manner and these will be dealt with later.
During the course of several extensive studies for a major
North Sea operator, my company investigated several
methods of removing modules and packages. The conclusion was that the simplest and most cost-effective method was to
remove them in exactly the manner in which they were
installed, using a similar crane vessel. A further study iscurrently underway to determine if the new super-heavy lifting vessels can be used to reduce the cost of topsides removal.The
early indications are that it may be possible to reduce costs
significantly by removing a small topsides installation complete in a single lift.
All the expertise necessary for the removal and abandon-ment operations is currently available in both the oil
com-panies and the offshore industry contractors. There
are. however, many aspects that will require more detailed study and several universities and companies are investigating cer-tain specific areas.All work offshore must be car-ied out in accordance with the various regulations to ensure safe working. It is unlikely that
such work will be carried out by demolition contractors,
Norman Boyd is Manager of Engineering with Taylor Woodrow Offshore (formerly Taywood-Santa Fe). In1978
he worked on the first major study of Removal and Aban-donment and has since been involved in further studies and update reviews of the original one. He was a member of the Working Group for the British Committee for ECOR report and has worked on the North Cormorant and
More-cambe Bay Projects. He has also presented papers on
other subjects.
Trans IMarE(TM) Vol. 99, Paper l0
although there may be advantages in including some demoli-tion expertise in the team.
The operation of removal and abandonment can be divided into two stages, preparatory and execution.
PREPARATORY STAGE
In common with allmat ol projects an extensive preparatory stage is necessary to identify, prepare for and plan all the work
involved in removing the platform topsides. Much of the
required work will be similar in nature to the preparation and engineering work carried out when installing the platform.
Engineering
A considerable amount of engineering work will be required and will include the few examples described below:
I. A detailed weight and structural survey will be necessary
for each module and package. Much of the original lifting
support steel may have been removed and replacements must
be designed. Many changes may have been made to the
equipment in the module and the weight and centre of gravity must be determined.
The integrity of pad eyes must be checked and. where
necessary, replacements designed.
Protruding external vents, pipe spools, walkways etc. will
be burnt off and stored inside modules. The details must be
determined.
Selection of a suitable lifting vessel must be made at an early stage. The exact method of lifting must be checked and slings and other lifting aids procured.
The type of cargo barges required must be determined
and the method of mounting removed modules and packages designed.
The types of supporting vessels, numbers, length of hire and start of hire must be determined. Such vessels will include
supply boats, accommodation vessel, tugs. cargo barges,
safety vessel etc.
An early decision will be required on whether removed
modules and packages are to be transported to shore
ordumped at sea. In this connection there will generally be little
intrinsic value in the removed topsides and everything will be treated as scrap value only. If being transported to shore then
sea-fastening details for each removed piece must be
engineered. A suitable disposal site must be found that canbreak up the modules quickly, in order to achieve a quick turn around of the cargo barges. If dumping at sea is required then the dumping site must be agreed under the London Dumping
Convention. Engineering must determine the details for
'launching' the packages off the barge and also ensure that no vessels, tanks etc. can float free.
8. A Certifying Authority will need to be appointed and
Government Regulatory Authority Approvals will be
required. These authorities require to be satisfied at the outset
that the working procedures and methods comply with the
existing regulations and codes in regard to safety, navigation and pollution control.
Many procedures must be developed at an early stage. out-lining the methods of executing various sections of the work. Some examples of the types of procedures required are well plugging and abandonment, removal and disposal of toxic and
hazardous chemicals and materials, and shutdown and
de-commissioning of hydrocarbon process systems.
Once the outline procedures have been produced and
agreed, then detailed procedures can be developed, wherein
the detailed sequence of operations is determined for each
process and utility system on the platform. Arrangementsmust be made for temporary electricity supplies and safety after the platform utilities are shutdown.
During the engineering work there will be a need to examine
alternative proposals for various aspects of the work and to
make detailed cost evaluations in order to permit selection of the most cost-effective methods. Further details of the
engin-eering work are indicated in the section dealing with the
execution stage.
Procurement and contracts
A Procurement and Contracts service will be required to purchase additional materials, fabrication and consumables
for the operation. Contracts must be entered into for the hire of all the supporting vessels and services.
A supply boat and base service will be required to be
established in a similar manner to that required for a hook-up and commissioning contract. Contract documents and speci-fications must be developed for the many and various aspects
of the operation. Planning
A great deal of detailed planning will be vital to the success
of the operation. Detailed work packages must be prepared
taking full account of the sequential nature of the work. The
manpower requirements must be determined for each work package and the time allowed for the work established.This is
then incorporated into the overall plan.
The plan must allow for optimization of all vesselh i ringsand manpower, and due allowance must be made for the weather factor in all the offshore operations.
EXECUTION STAGE
The execution stage marks the start of the actual work
offshore. Much of the work will be of a sequential natureand it can be broken down into several clearly defined activities:
Shutdown
Well plugging and abandonment Decommissioning
Deconstruction
Lifting and sea fastening Disposal
Shutdown
The first activity at the start of platform removal and
aban-donment is to shut down the production process systems in conjunction with the shut-in of wells. All life-support and utilities systems will be maintained fully operational until
completion of well abandonment.
Preparation will provide for the examination of engineering
documents such as process, flow, instrument and electrical diagrams. Detailed shutdown procedures will be prepared
providing for the sequencing and safe execution of work. The
extent of the work will he dependent on thenumber of wells
and the number of process and utilities systems. Process shutdown will include:
Switching power generation to imported fuel.
Begin the shut-in of production wells one by one by
closing control valves, except for the final well. The final wellis
used to supply fuel to and allows for the orderly and gradual
shutdown of the heating. glycol, dehydration and cooling
systems.
Shut-in final production well as requirement for fuel is
terminated.
Shutdown glycol circulating pumps. condensate pumps and cooling water pumps.
Shutdown and isolate production export pipelines. Some depressurization and draining of hydrocarbon systems
may be started at this stage by venting to flare headers and
draining to sea pumps.
Well plugging and abandonment
This phase provides for the permanent plugging and sealing of all wells associated with a particular platform. The opera-tion will require a full drilling crew plus addiopera-tional equipment such as a cement pumping unit. It will be necessary to ensure
that a drilling or workover rig is available and fully
opera-tional. Full platform services, utilities and safety systems will
be maintained operational.
The preparatory work will provide for the preparation and
approval of a detailed procedure, taking specific account of
whether the wells are producing, with or without artificial lift. Additional equipment requirements will include cement pum-ping unit, casing cutting tools and spears. Schlumberger unit, plug setting tool, wireline unit, blowout preventersand rams,
drill pipe and collars, and tubulars handling tools and
accessories.
The operation will start with pulling the downhole safety
valve and any flow-control devices, rigging up the cement unit to swab valves and establishing pumping rates down
produc-tion tubing with seawater. Further operaproduc-tions provide for removing production tubing and casing and laying cement
plugs at predetermined levels in accordance with the agreed
procedure. The final plug will extend up to the sea bed.
The plugging and abandonment operation will require about 7-10 days per well, therefore assuming a 30 well platform the time required will be from 210 to 300 days. It is possible that some decommissioning can be carried out during this time but
all life-support and safety systems must be maintained fully operational and the amount of spare accommodation may be a limiting factor.
Decommissioning
This activity will provide for leaving the platformtotally shutdown, clear of all hazardous materials and certified safe for deconstruction to proceed without recourse to a permit to
work system. The extent of the work is dependent on the number of separate systems on an installation.
During the preparatory stage detailed work sequence pro-grammes and procedures will be developed and approved for the decommissioning of all production and utilities systems. Any additional equipment and material requirementswill be
8
established and provided. The extent of the work will depend
on the number of separate systems on each platform. An
accommodation vessel will be required to provide, in addi-tion to accommodaaddi-tion, temporary power supplies, communi-cation facilities and workshops. Additional short-term storage
will be required for diesel fuel, other materials and equipment. There are generally four principal categories of systems on a
platform: hydrocarbon systems, non-hazardous sytems, toxic
and hazardous chemical systems, and electrical power systems.
The hydrocarbon systems include well-head and test pro-duction, main propro-duction, dehydration and metering, sphere launcher, receivers and slug catchers, gas compression, re-injection or water re-injection, fuel gas, relief and flare systems, drain, diesel fuel, jet fuel. chemical injection, hot oil, lube oil,
and pipelines.
The non-hazardous systems include cooling water, fire
water, washdown, potable/fresh water, instrument and utility air, and steam.
The toxic and hazardous chemical systems include glycol, injection chemicals, hypochlorinator, acids, caustic soda. and paints and thinners.
The electrical power systems include main power, emerg-ency power, and battery power.
Until all hydrocarbon has been purged and removed all work must be carried out under a permit to work system.
Hydrocarbon Systems will require seven stages to purge fully all hydrocarbon. The seven stages are as follows:
Depressurization. A specific system will be isolated from
other connecting systems. Valves, connecting system vessels to flare header, will be gradually opened. All relief valves must be
in the normal operating condition and the depressurization
must be monitored by line and vessel gauges. The flare system
oil burner and sea sump must remain operative until disposal of all hydrocarbons is complete.
Hydrocarbon drain. Residual liquid hydrocarbon is
drained directly to the flash tank, or sea sump. Vapours from the flash tank are vented to the low-pressure flare header.
Water flush and drain. The system is flushed with sea-water whilst maintaining venting to flare headers. Flushing water is drained to the flash tank or sea sump.
Steam purge. Steam is used to purge residual
hydrocar-bons. Each vent and drain is monitored until the level of
hydrocarbons present is reduced to an acceptable level. Water fill. Steam is replaced by water fill in a manner which avoids the formation of a vacuum.
Nitrogen and water drain. Nitrogen is introduced at high vent points and the water is drained.
Isolation. On completion of filling the system with
nitro-gen the final step is to close all drain valves and all major system valves.
All safety equipment must remain operational until the process systems are inert and safe.
Non-hazardous systems are depressurized. flushed with water, drained and isolated.
Disposal of toxic and hazardous chemicals will depend on
their nature. Generally, they should be removed in their
original containers, observing normal safety precautions and regulations. The exact details will depend on the particular substances and the installation.
The decommissioning of electrical power systems is a
planned sequenced shutdown of all switchgear. motor control centres, distribution and generators, observing all necessary
safety procedures.
Complete and detailed logs of all decommissioning activities
must be kept so that certified clearance may he obtained to
permit further work to continue without the necessity of
operating a permit to work system.
Deconstruction
This activity covers all work to prepare the topsides modules
and packages to enable them to be removed. There is little
doubt that they should be removed in exactly the same manner as they were installed, ie each module or package installed as a separate lift is removed as a separate lift by a crane vessel with
at least the same capacity and reach.
The execution of the work will start only after the total
platform has been certified safe and free from hydrocarbons
and toxic materials and all systems shut down. Piping and ducts
will be cut a minimum of 3 ft from module walls. The short cut lengths so removed, together with other loose equipment, are tack welded down inside the module. Cable can be cut, rolled back and tied down. Walkways and platforms will be cut and the short sections removed and secured. Flare booms can be prepared for removal by cutting all process piping and cables. Any interconnecting bridges will have all piping cut.
Replacement of pad eyes will require extensive welding under controlled conditions followed by radiographic or ultra-sonic examination to prove the integrity of the replacement.
Modules will be cut free from their supporting structures. Module weights and centre of gravity will be checked by survey
and by weighing if practicable.
A final check will be made to ensure a module or package is
free from all connections and all temporary equipment and supplies removed. Decks and the module support structure
will be divided into sections, general!), by cutting through
original field splices and through the top of jacket legs.
Extreme care and detailed planning will be required to
ensure the safety of these operations. The final cutting of flare booms, towers or bridges can only be performed when the crane vessel is in position supporting the item.
The sequence of preparation for lifting will depend on the lifting sequence determined during the preparatory work, but will generally start with upper level modules and packages
followed by lower level packages. bridges, flares etc. and
finally decks and support frames.
The preparatory work and preplanning will have deter-mined the economical and practical time for the heavy-lift vessel to arrive. Such vessels will have sufficient
accommoda-tion to permit release of the accommodaaccommoda-tion vessel that will have been required during decommissioning.
The newer super-heavy-lift vessels appear to offer the
possi-bility of lifting the complete topsides of some of the smaller platforms in one lift. This application is currently being stu-died, but in this case some of the deconstruction work will not
be required, although alternative work will be required to prepare for the single lift and it will be necessary to establish a
reasonable centre of gravity.
Lifting and sea fastening
Many of the lifts will be of large but low-weight components such as flare towers or booms, bridges, helidecks etc. The
preparatory work will have established in detail the lifting sequence, and procured the necessary slings, equipment, addi-tional structural bracings, spreaders and rigging. The lift vessel
contractor will require verification of weights and centres of gravity.
Special rigging arrangements used for installation of flare
booms, cranes etc. will require similar arrangements for removal. If modules were installed on a skid beam and skidded
into final location, the reskidding operation will be extremely difficult and may require special preparation.
Although damage to a module during lifting may not be critical and installation bumpers and guides need not be replaced. it is essential that all the normal safety precautions be
taken. A serious accident at any stage of the operations will cause at best a few days' delay.
All the lifting and sea-fastening operations require good weather and reasonably calm seas. In hostile environments such as the North Sea this limits these operations to a period from about April to September with a risk of some days being lost. This aspect will therefore decide the starting point for working back the planning of the whole operation.
Disposal
The disposal alternatives of onshore or dumping at sea were
mentioned earlier, and whichever method is selected the
operation of towing a cargo barge load of modules or packages must be conducted safely. Onshore disposal requires the selec-tionofa suitable breaker/scrapyard, capable of receiving cargo
barges with large quantities of material which need to be
removed quickly.
The alternative of disposing of a platform topsides at the
on-site location is dealt with later.
TOPSIDES OF CONCRETE
SUBSTRUCTURE PLATFORMSSome concrete platform topsides were constructed
com-plete. mounted on two special purposes barges and then mated with the substructure by floating the barges over the
submer-ged concrete substructure. The substructure was then
refloated to support the topsides clear of the barges and thebarges were removed. The complete platform was then towed
to its operational location as a complete unit.
The reverse of this process can be performed, providing the complete platform can be refloated, in which case it may then be possible to dump the complete platform in very deep water. The alternative, should refloating complete be impracticable,
will be to remove the topsides piecemeal in a manner similar to that described earlier.
In either case the activities of shutdown, well pluggingand
abandonment and decommissioning must be carried out
before refloating commences.
DEMOLITION OF PLATFORMS IN PLACE
The possibility of disposing of a steel platform on the on-site
location has been investigated for platforms in 230 ft water depth, with a requirement to provide Soft of clear water
above any part of the demolished structure.
Total demolition of the platform by explosives was con-sidered and is a practical possibility. It was however not
considered further as there was no guarantee that a steel famed structure would collapse completely to leave the required clear water depth. Should explosive demolition fail, remedial work to correct the situation could well be prohibitively expensive. This then led to the development of the 'toppling' operation. Most of the platforms studied were of the eight-leg jacket types, which are ideal for toppling by cutting into two four-leg halves and toppling each half outwards at the same time. The
centre section of the topsides, above the centre line ofthe platform, must be completely cleared and cut right down to the
module support frame. The central bracing tubulars of the
jacket must be cut in order to separate the two four-leg halves of the platform.
Controlled explosive charges would then be placed to cut the base of the four inner legs and to remove completely a portion of the four outer legs, causing both halves of the platform to
topple, like a tree being felled, to the sea bed. It was not
considered necessary to remove the main bulk of the topsides, although some work would be required to ensure that they did
not break free before entering the water.
A similar method of toppling a six-leg jacket platform may be possible. but toppling of the very large four-leg structures
with a square topsides plan appears to require considerable
study to determine its practicality and cost effectiveness.
REMOVAL AND ABANDONMENT COSTS It will by now have become obvious that the removal and abandonment of a fixed platform installation will be a very
costly operation.
During the course of my company's studies, detailed costs
were developed for individual platforms. From these costs,
guideline figures were produced on a cost per short ton basis.
The costs indicated below take account of all cost factors
from the preparatory stage through to disposal. They include
allowances for lost time due to bad weather and include all
supporting services such as supply boat operations, consum-ables. catering, helicopter services and the hire of all necessary vessels.
Obviously each specific platform will have its own peculiari-ties which will affect costs, but the following guideline figures
serve to indicate the magnitude of theoperation.
Topside modules, decks and packages removed and
trans-ported for disposal onshore as scrap will cost from £3500 to
£4500 per short ton. This figure does not include well plugging
and abandonment. The similar costs per short ton for steel
jackets cut piecemeal and removed to shore is from £4500 to £5500.
The plugging and abandonment of wells will cost between £350000 and £500000 per well. This figure will be dependent
on any problems that may be met during the operation. The potential saving by use of the new super-heavy-lift vessels appear to be of the order of 20% compared with the
figures quoted above. Dumping of topsides at sea after
removal may not, in fact, result in any significant savingsbecause of the loss of the small scrap value and the time that
the cargo barges and rugs will be needed on hire, with the
added costs of design and procurement of the launching
facil-ities that will be required on a cargo barge.
The toppling of a platform in place with very little of the
topsides removed is the cheapest method of disposing of a
platform and in the eight-leg jacket case could result in savings
ofsome 50-70% of the cost of removing the total platform. Partial removal, ie removing the topsides and removing, rather
than toppling, the top portion of the jacket to give the clear water depth, will result in savings amounting to some 20-30% ofthe totalcosts.