r
See note inside cover
SH R 6/62
A Station of the
Department of Scientific and Industrial Research
12th March, 1962
NATIONAL PHYSICAL
LABORATORY
SHIP DIVISION
A DESIGN STUDY FOR A
CIRCULATING WATER CHANNEL
by
Extracts from this report may be reproduced
provided the source is acknowledged.
Approved on behalf of Director, NPL by
Mr. A. Silverleaf, Superintendent of Ship
Division
RETURN
CONDUIT
DIFFUSER UPSTREAM
STILLING
.-SECTION
CONTRACTION
WORKING SECTION
WEIRSECTION
SUMP
PUMPScale Model
Circuit Stability
Velocity distribution in the working section
Flow conditions with and without an adjustable false floor
Comparison of two types of weir
Pump and sump
Comparison of two splitter type diffusers
Screening in upstream stilling section
Contraction
A DESIGN STUDY FOR A
CIRCULATING WATER CHANNEL
by
B.N. Steele
Ship Division, National Physical Laboratory
SUMMARY
The flow conditions about a model hull and its propellers are best studied in a circulating water channel. This consists of a channel containing flowing water in which the model hull is placed, the flow being observed through windows in the sides and bottom. The water is made to circulate at any desired speed by means of a pump.
Work has been carried out at the Department of Engineering, Cambridge University, on the flow in a range of water channels, the largest of which had a width of 114 inches and a depth of 11 inches, with the object of
elucidating the factors affecting the production of uniform, wave-free sub-critical flows in water in parallel channels0 A report on this work was written by Orkney in which he included a proposed design of a
circulat-ing water channel for testcirculat-ing model hulls up to 4 ft in length over a range of speed-length ratios having a maximum value of 17O
An extension of Orkneyt s work was carried out by Williams of NFL on the original contraction and channel which Orkney had used, on two NFL
-designed contractions with the same channel, and also on smaller and larger channels at the NFLO These experiments showed that the scaling laws that Orkney had adopted would not enable the higher velocities to be obtained with a level surface in the full-size flume. Consequently, a modified preliminary design for a circulating water channel was prepared by Williams 2 To investigate flow patterns and pressure distributions
around ship model hulls 8 ft in length, the channel requires a working section at least 12 ft wide and 8 ft deep; the maximum speed of flow
through the working section without stancLing gravity waves should be
about 8 fi/sec, but it is likely that 10 ft/sec may be achieved without
appreciable wave amplitude.
In this design (Fig.1) water is pumped from a sump through a return conduit and a splitter type diffuser to the upstream stilling section. In the stilling section any asymmetry of flow and turbulence is removed by allowing it to pass through a series of screens. The mass of water
then flows through the contraction where it is accelerated to the working section velocity, and downstream of the working section it is allowed to fall over a weir back to the suinp wre, after passing through more screens,
it is recirculated by means of the pump. The novel feature of this design is the installation of the weir fitted to prevent any disturbances created by the pump being transmitted back upstream to the working section, the water passing over the weir falls freely into the sump in which the water
level is below the bottom of the working section, and this is termed a
'free flooded' weir.
In order to investigate fully the characteristics of this circuit, a 1/lOth scale model of the prototype was built at the Ship Hydrodynamics
Laboratory of the NFL, and this report is a summary of the experiments
-3
I. SCALE MODEL
The circuit shown in Fig.1 was so constructed that each section was completely detachable and could be modified without alteration to the remainder of the circuit; it was thus a simple matter to study a variety of designs for each section. This report deals mainly with those designs which were ultimately found to be satisfactory.
The model had a total length of 30 ft and a width of 6 ft and was
sited in such a position that the quantity of water in the circuit could be changed with no inconvenience to other plant or equipment. The working section was 1.2 ft wide, 1.4 ft deep and 5 ft long, the sides being of
perspex slotted in to a in plywood floor. A horizontal datum surface was provided above this section in the form of machined brass rails. The
weir section had the same dimensions as the working section and was 2 ft
long; it was constructed of in plywood and covered with thin cobex to produce a smooth surface. The cascade weir, which consisted of five brass symmetrical aerofoil sections of approximately 2 in chord, was bolted to the end of the weir section. In order to test various pump and sump combinations, a large galvanised steel tank, 8 ft long
3.7
ft wide and3.9
ft deep was constructed, and various wooden sump shapes were built up within this shell. The variable speed, adjustable pitch, manganese bronzeimpeller was 1 2 in diameter and was fitted with pre-rotation and guide
vanes. This impeller was sited within an accurately machined, i in thick galvanised steel tube which was connected to the 1/8 in thick galvanised
steel return conduit. Three cascaded 900 corners were contained in the return conduit, and at the downstream end a short round to square transition
piece was introduced. In order to make the change from return conduit to stilling section velocity as gradual as possible a splitter type of diffuser
was fitted; this was mde of 1/8 in galvanised steel and was 4 ft long. For simplicity of construction the upstream stilling area was made of wood,
8 ft long, 4 ft wide and
2.5
ft deep, and had a series of slots throughout its length to acccmmodate stilling screens. The shell of the contractionwas .lso of wooden construction, but since frequent modification to the
internal shape was desirable the contraction profile was of paraffin wax which was contained within the wooden shell.
II. CIRCUIT STABILÏTY
General
Since the initial conception of the present desii of the circulating water channel, there had been concern over the possibility of any inherent
instability, or pendulation, in the circuit which might initiate a periodic movement of the surface of the water passing through the working section.
Consequently SHL consulted the Hydraulics Research Station, Wallingford, and were advised to build a 1/lOth scale model of the whole circuit in order
to study its stability. It was felt by the Hydraulics Research Station that if the model proved stable, the prototype would be satisfactory.
Experiment corH tior.s
Since the type of weir may influence the stability of the circuit, experiments with both a cascade and a tilting weir were performed.
Under normal conditions the weirs were completely free-flooded in operation, but in order to investigate the possibility of operation with the weirs partly flooded, a few experiments were conducted under these conditions.
In all the experiments, measurements of surge over a range of speeds at model working section depths of
9", 9-i-"
and lO" were taken.Method of measurement
Several methods of measuring the vertical oscillatory movement of the water surface were tried, the most suitable being a capacitance type probe
using a OQOI in diameter wire with shellac as the dielectric, the output
being recorded on a pen recorder. It. was found possible, using this method,
to repeat the calibration very well, this being done in the channel by movement of the probe relative to the still water surface.
Originally it was planned to use 6 probes (i.e. 2 each in the sump,
working section and upstream stilling section). Due to electrical interaction between the probes, however, this was not found to be possible, and it was decided to use only one probe which was placed in the working section at
mid-length and mid-width.
Experiment results
The records of water surface movement were analysed, and the results
-5-Although it was possible to repeat the probe calibration at various intervals throughout the experiments, it was not possible to repeat the records of the surface movements. This indicates that there is not a urìiue periodic movement associated with each set of operating conditions.
The results given in Tables i to 8 relate to the first experiment conducted
at each condition. The records obtained often displayed a random movement of the water surface, and analysis of the pump revolutions showed that they were fluctuating; it is felt that it was to this that such surface movements
could be attributed. From the pendulation aspect, neither the cascade nor
the tilting weirs showed any difference.
The experiments with both weirs partly flooded indicated that any small sump disturbance will be readily transmitted back upstream to the working
sect.ion, to an amount dependent upon the degree of flooding, the ideal case
being when the weir is completely free-flooded. There is very little
differ-ence between the cascade or the tilting weirs in this respect.
Conclusions
The model experiments suggest that providing the pump speed is maintained very steady and the weir is completely free-flooded, no pendulation should be
experienced on the prototype.
III.
VELOCITY IN THE WORNC- SECTION C-eneralWhen the circulating water channel is used for experiments on surface models, the draft of the models will seldom exceed 1/8th of the channel
depth. The velocity near the surface, together with its relation to the velocity at other depths, is therefore of extreme importance. The method of determining this on the 1/lOth scale model, together with the results,
is outlined below.
Experiment conditions
Since the type of weir may influence the velocity distribution, experiments with both a cascade and a tilting weir were undertaken.
Tables 9 and. 10 give the model speeds and corresponding prototype speeds
at which the experiments were performed. In all cases the model channel was run at a depth of
9.6
in, corresponding to a prototype depth of 8 ft.Method of measurement
It was not possible to use a miniature current meter for this survey, since experiments have shown such instruments to be unreliable near a solid boundary and in way of the air-water interface. Velocity measirements using small, buoyant particles were found to be more reliable. Since it was
required to take a record of velocity at all depths, it is obvious that free particles at different depths would have to be timed over a fixed length; the
particles used had to be neutrally buoyant and of a relatively small diameter. These particles were made at SRL from the adjoining spheres of a
'1poppit"
necklace coated with a sufficient quantity of lead base paint to make themneutrally buoyant, and. were approximately 0.1 in in diameter.
The particles were injected into the moving stream by attaching them to an arrangement of hypodermic tubing by means of a thin wax, and gently tapping the hypodermic to release the particles. It is obvious that the particles should all be released in the same vertical plane, but it was not found possible to achieve this, and therefore any experiment in which the spread of particles
exceeded I in was ignored, thus reducing the error to less than 1%.
The passage of the particles through the working section was filmed using a cina camera timed to film at 50 frames/see; the film was then analysed on
the A.R.L. film assessor.
Experiment results
The results of the experiments considered to be the most reliable (i.e.
where the spread of tim particles was the least) are given in Tables 11 and 12. Study of Table 11, at 3Q0 ft/sec, and Table 12, at 1.0 ft/see, indicates that the bottom boundary layer is fairly thick, since a considerable reduction
of speed is evident.
Table 12, at 1.0 ft/eec, shows a very erratic pattern but it is felt that
this Can be attributed to a larger spread of particles than was at the time noted.
7
Conclusions
A stuay of Tables 11 and 12 suggests that there is no fall in velocity near the surface, and that it is sensibly uniform throughout the depth
except in way of the bottom boundary layer.
IV. FLOW CONDITIONS WITH AND WIThOUT AN ADJUSTA.BT,F FALSE FLOOR
Ceneral
In order to operate the circulating water channel at various depths, it is necessary to add or remove large quantities of water from the circuit, and it was originally anticipated that this water should be stored in separate large tanks. Ministry of Works engineers suggested, however, that to save expense and simplify the operation of the channel the floor should be capable of
vertical movement, thus providing a means of adjusting the "effective depth" whilst maintaining the volume of water in the circuit constant. The 1/lOth
scale model of the circulating water channel was mofied to investigate this suggestion, and the results of the subsequent experiments are given below.
Experiment conditions
The false floor was constructed so that it was possible to incline it
through 2° and to vary the "effective depth" between
3.6
and 7 in.Experiments were conducted to investigate the
following:-Uniformity of velocity in the working section
Velocity traverses at entrance and exit to the working section at corresponding effective depths were made with and without the false
floor over a range of speeds. It was not considered necessary to do this for the maximum depth, since the conditions with and without
the false floor are identical. In the above experiments the false
floor was kept horizontal.
Slope of water surface over length of working section
The inclination of the false floor was varied, and over a range of speeds the fall in level over the length of the working section was
Stability of circuit with false floor
Measurements of surge were made with the false floor in place in the same manner as described in Section II.
Method of measurement
Measurements of velocity were made using a 1 cm diameter miniature current meter, but for reasons already explained it was not possible to make measurements very close to the surface, walls or bottom.
The fall in surface level was measured using a pair of pointer gauges which were zeroed in the channel in the still water condition.
Surge records were taken using the capacitance gauges previously
described.
Experiment Results
Velocity traverses
Study of Figs. 2 to 6 ini cates that with an effective model depth
of
3.6
in (prototype depth of 3 ft) the flow is very erratic both with and without a false floor, there being very little to choosebetween them.
Figs. 7 to 12 show that at t}üs increased model depth of 6.3 in (prototype depth
525
f t) the flow is far more stable, there onceagain being very little difference between the flow with or
with-out the false floor.
Surface level
The experiment corditions, together with the results, are shovvn
in Table 13, the accuracy of measurement being approximately ±0.005 in because of surface movements caused by slight
fluc-tuations in pump speed. It was estimated that it should be possible in certain instances to maintain a horizontal water
surface; this was tried and within the limits of accuracy of measurement was found possible.
(c) Circuit stability
It was found that the circuit exhibited no instability with a false floor, except, as noted previously, when changes in pump speed caused slight movements of the water surface.
Conclusions
It would appear that operation at a low working section depth may lead
to a bad velocity distribution in the working section, both with and. without
the false floor, but at increased depths the velocity distribution should be very reasonable0
There is an indication that inclination of the false floor will enable the water surface to be kept horizontal, but possibly not under all conditions. It is essential that the friction coefficient of the walls be kept as small as
i,
The inclusion of a false floor does not seem to give rise to any circuit
instability.
All the experimental evidence obtained from the model experiments indicates that the installation of a false floor is a feasible proposition,
and if it were not found. to be satisfactory on the prototype it would be
possible to lower the floor and operate the channel as originally intended.
V. COMPARISON OF TWO TYPES OF WEIR
C-e ner al
To prevent disturbances from the pump being transmitted upstream to the working section, it was decided to introduce a break in the circuit
between the working section and the suinp, in the form of a free-flooded
weir. Advice from the Hydraulics Research Staiion indicated that a tilting weir would be the most suitable, but it was suggested by Williams that a cascade weir may overcome some of the disadvantages inherent in a
tilting weir.
Hydrodynamically the three main factors governing the choice of a weir
are:-Stability
Drawdown characteristics
Influence on upstream velocity distribution
It was found from experiments described in Section II that (i) was satisfied with both types of weir, and therefore experiments were performed to
investigate (ii) and (iii).
Experiment conditions and results
Velocity traverses
In order to effect a comparison between the two weirs, complete velocity traverses were made along the òentreline of the channel
and weir sections. These traverses were made over a range of speeds at a fixed model depth of 9.6", and the results are shown
in Figs. 13 to
16.
Complete traverses were made adjacent to the cascade weir and at the working section exit; these results areshown in Figs. 17 and 18 respectively.
Drawdown
Measurements of surface level were made at various positions along
the length of the eir section. In the case of the cascade weir it was found that the divergence of the surface from horizontal was of the order of accuracy of the measuring equipment, and the
results are not shown. With the tilting weir, however, the
draw-down was considerable and is shown in Fig. 19 for a range of
speeds.
(o) Fall in surface level over working section
Whilst performing these experiments on the two types of weir, it. was decided to attempt to measure the slope of water surface over
the length of the working section for a range of speeds. Results
of this experiment are given in Fig. 20.
Discussion of Results
(a) Velocity traverses
Figs. 13 to 16 indicate that, as would be expected in the case of
the tilting weir, there is a considerable increase in velocity over
the length of the weir section; with the cascade weir, however,
this effect is almost eliminated. Figs. 13 to 16 also show that with both weirs and at most speeds there is an increase in velocity
of approximately 5% over the lgth of the working section. Fig. 17 shows that there is a variation in speed with depth
adjacent to the cascade weir, but at the working section exit the velocity distribution is quite reasonable.
(ò) Drawdown
Fig. 19 shows clearly the advantage of the cascade weir over the
tilting weir in this respect; the installation, it will be seen, can result in a substantial saving in length.
(c) Fall in surface level over working section
Fig. 20 shows the fall in level over the length of the working section, and suggests that the tilting weir may be slightly
superior in this respect; te differences, however, are within the limits of accuracy of the measuring equipment.
Conclusions
All evidence from these experiments favour a cascade weir, which would appear to have all the advantages of the tilting weir but none of the
dis-advantages. It would be advisable, however, to allow for the possibility of the installation of a tilting weir on the prototype in case the
apparently favourable characteristics of a cascade weir are not borne out
on a larger scale.
VI. PUMP AND SIThIP
Ceneral
It has been found by Denny that, contrary to expectations, the characteristics cf a sump do not obey the normal scaling laws, and that when using a model geometrically similar to the prototype it is necessary to obtain the same velocity at the pump inlet on both model and prototype in order to investigate the possibility of the formation of air-entraining
vortices. Denny also found that the flow into the pump should be free from any tendency to swirl, and to prevent this, it is desirable to site the pump casing hard against a wall0 For these reasons the sump proposed is as
shown in Fig. 21 Experiments were performed to investigate the air-entraining tendencies of this sump and pump combination0
Experiment Conditions
The maximum normal pump inlet velocity on the prototype is approximately
was fitted. and the walls of the channel throughout the circuit were raised
another 1 ft. However, the maximum inlet speed which it was found possible to achieve with this arrangement was
755
ft/sec, hence in order to simulate the prototype inlet ccnditions, it was decided to reduce the submergencediameter
ratio for the model. Experiments were made over a range of
submergence
ratios, the lower values being obtained by reducing the quantity
&iame ter
of water in the circuit.
Discussion of results
It was found that the water flowing over both types of weir entrained considerable quantities of air, and unless the screening arrangements between the weir and pump were very good this entrained air entered the pump inlet and travelled via the return conduit to the upstream stilling section, and
under some conditions was still present in the working section. It was
found possible, by the use of screens of rubberised hair 3" thick and
6 ozs/ft2 in the sump, to prevent this air entrainment almost entirely, and this is shown in Figs. 22 to
30.
There is a strong tendency for the water passing over the weir to flow
in the direction indicated in Fig.
31,
and the velocity of the water in the sump increases with increasing depth. Attempts to explore the flow pattern by means of dye injection were only partially successful, due to turbulencenear the pump inlet.
For each screen arrangement the water level in the surnp was varied, and
the pump run at full power. The surface in each case was carefully studied
for any sign of irregular flow or air-entraining vortices (they were noted.
with some screen arrangements). Table 12 gives details of each condition
run. The system of two screens close together was not tested at lower
submergence ratios than
2.67,
since it was at once seen that the arrangement of two screens far apart gave better results, the reason being that there was more time for the air passing through screen I to riseto the surface before entering screen 2.With no screens in place the water surface is very disturbed, and this tends to inhibit the formationof air-entraining vortices. When the screens are in place, they considerably still the surface and remove the air
entrained. at the weir, but a greater tendency to the formation of vortices
does appear. Floating a heavy wooden raft between the last screen and the pump casing may reduce the tendency to vortex formation and also act as a
The arrangement shown in Fig. 21 appeared. to be satisfactory; final
details of pump entry, however, would be left to the pump manufacturer.
VII. COPARISON OF TNO SPLITTER TYPE DIFFUSERS
Gene rai
The transfer of the water from the sump to the upstream stilling section involves its passage through a 12 ft diameter pipe, at a maximum speed of approximately 7 ft/sec. In an attempt to make the transition from this pipe to the upstream stilling section (where its maximum forward
velocity is I ft/sec) as smooth as possible it was decided to fit a
diffuser, and. in order to keep the angle of diffusion as small as possible
this diffuser is split into several compartments. A design was prepared
at SEL, but because of anticipated. difficulties of construction on the
prototype an alternative design was prepared by MoW, and experiments were carried out to compare these two diffusers.
Experiment conditions
Velocity traverses with each diffuser in place were made immediately
downstream of the diffuser. The conditions at which these traverses were made are given in Table 15
With each diffuser a set of velocity traverses were made in the working section at a model channel depth of
9.6
in, at speeds given in Table16.
Experiment results and. ConclusionsThe results of velocity traverses immediately downstream of the
diffuser are shown in Figs. 32 and
33,
and it is seen that the flow is extremely unstable, the fluctuations about a point amounting to as much as100%. The results given in Figs
32
and33
are the mean of 8 readings takenover about
loo
seconds. There would. appear to be a greater asymmetry inthe case of the MoW diffuser. The experiments were terminated at 12 in below the surface, since the flow was seen to be so bad that it was decided
to investigate the effectiveness of the screens (Section
viii)
13
complete speed range, although the velocity using the MoW diffuser
appears to vary with depth at 1
.5
ft/sec. Any very slight asymmetry which may exist at the exit from the upstream stilling section isobviously very successfully removed in the contraction. It is emphasised again that very little reliance can be placed on the results close to a boundary, due to the characteristics of the current meter.
VIII. SCREENING- IN TffE UPSTREAM STILLING- SECTION
G-eneral
After passing through the diffuser the flow is very unstable, and it is desirable to rectify this before it enters the contraction. To improve the flow, experiments were conducted to find a suitable screen arrangement. In order to prevent 'bagging' of the scrèens on the prototype, it may be necessary to support them with stiffeners, and therefore model experiments were carried out to assess the influence of these stiffeners on the down-stream velocity distribution.
Experiment conditions and results
Diffuser end of stilling section
It can be seen from Figs. 32 and 33 that the velocity distrib-ution before passing through the screens is not uniform in either width or depth, and experiments were conducted on various screen arrangements in an attempt to improve this. The operation
connUt-ions are as given in Table 15, so that direct comparison of velocity traverses downstream of the screens (Figs. 4-O and 4-1)
may be made with Figs. 32 and
33.
Downstream of screens
In the outline desi there were 10 screens in the upstream stilling section (4- of 0.5 solidity and 6 of 0.32 solidity), but a velocity traverse just downstream of the last screen indicated
15
-that although the distribution was vastly better than -that immediately after the diffuser, it was still not good.
Removal of several screens tended to improve the distribution, and it was found that about 4 screens was an optimum number. The velocity distribution was now satisfactory across the width but there was a decrease in velocity with increasing
depth; an attempt was therefore made to grade the solidity of the screens in the vertical direction, the arrangement shown in Fig. )2 finally being considered satisfactory; the
results of velocity traverses with this arrangement are shown
in Figs. 40 and 41.
Experiments to determine the effect of the relative position of the screens tended to confirm the work of Baines and
Petersen4 and Dryden and Schubauer5 in that their relative
pos-itions had little effect provided sufficient space is left
between screens for flow establishment.
(c) Effect of stiffeners
A set of stiffeners of aerofoil section were attached to the last screen of the arrangement shown in Fig. 42, but a vel-ocity traverse did not detect any "shadows" from these struts.
Conclusions
Comparison of Figs. 32, 33, 40 and J-i-1 indicate that regardless
of the flow on entry to the stilling section, it may be improved trem-endously by the careful use of screens. Any small variations in flow remaining at the downstream end of the stilling section are removed in
the contraction.
Experiments to detect any disturbances arising from the thin aero-foil struts proved negative, and it would appear that unless the struts are extremely thick they will have no adverse effects on the flow.
Since it was found possible to obtain a reasonable velocity dis-tribution downstream of the screens on the model scale, it was decided to investigate the effect of increasing the speed to the prototype value.
It was not possible to do this on the circulating water channel model,
and. therefore a series of experiments were conducted in No.2 towing
tank.
These experiments indicated that provided the nature of the
upstream disturbance is similar, the screens will have the same effect
on the downstream velocity distribution, irrespective of speed.
IX.
CONTRACTIONGeneral
The contraction was designed to give a contraction ratio of 9
: 1at the design condition of 8 ft channel depth and a channel speed of
8 ft/sec.
There is no exact theory for the design of a free surface
contraction, and the usual method is to assume that the major part of
the flow acceleration takes place in the first third of the contraction
length and that the transition to the working section velocity is very
gradual;
a smooth velocity curve is then drawn and from this the
sec-tion offsets calculated.
This procedure was adopted when designing
the contraction for the circulating water channel, and this was tried
on the model;
it was found, however, that a strong rotary motion was
set up in the contraction.
The contraction was subsequently momti Pied,
and, a sumniary of the experiments performed on this modified contraction
is given herein.
Measurements and observations made
The prmry object of these experiments was to study the flow in
the contraction by the injection of potassium permanganate dye into the
flow through hypodermics.
The screen arrangements in the upstreani
still-ing section were as shown in Fig. 42.
Measurements of the fall in the level of the water surface
through-out the length of the contraction are shown in Fig, 43, where they are
17
-Experiment results and Conclusions
Table 17 gives the positions at which the dye was injected, and these
conditions are shown in Figs. 44 to 51. Experiments with this contraction and with the original screen arrangement were undertaken, but it was found that due to the reduced velocity at the greater depths there was a cross over of streamlines from the sides to the centre, but these are not shown.
Fig. 45 shows the flow on the bottom of the contraction, and attempts to improve this by the insertion of fillets did not prove successful.
Despite this, however, the flow in the working section is very good.
Fig. 43 shows the fall in water level over the length of the
contrac-tion over a rarge of speeds, and it may be seen that this compares
reason-ably with the theoretical values.
X. GENERAL CONCLUSIONS
The prime reason for constructing a scale model of the proposal NPL circulating water channel was to study the stability of the proposed unorthodox circuit, and all of the experimental evidence is encouraging
in this respect. It would appear, however, that if there is any variation in the set speed of the impeller, then fluctuations will occur in the sur-face level and speed of the flow passing through the working section.
Measurements of velocity distribution across the model working section are generally very good and there is no evidence of surface retardation. The velocity along the working section increases by approximately 5% and it is thought that this is mainly due to the thickening of the boundary layer on the bottom of the channel, consequently there will be a slight increase in speed over the length of the model hull on the prototype.
Model experiments to investigate the possibility of using an adjus-table false floor to vary the effective working section depth, indicate that the flow is no worse than that encountered when running the channel at reduced depths. There is a strong possibility that the velocity at
low effective depths will not be time constant, and for this reason, it is doubtful whether the prototype will be useful below about 4 ft depth.
There is an indication that it may be possible to maintain a horizontal water surface in the working section by inclination of the floor, although probably not under all conditions. To reduce the
friction loss over the working section the friction coefficient of the bottom and sides should be as low as possible. Particular care must be
taken to prevent any undulations in the walls of the working section to minimise the possibility of wave formation.
Because of its novelty the cascade weir was subjected to very exhaustive tests and there was every indication that it was superior
to the tilting weir. The draw down was less with the cascade weir, and there was very little increase in velocity immediately upstream of the
weir. Using a cascade weir, it is possible to reduce the length of the
weir section, although provision should, be made for the installation of
a tilting weir at a later date if the model predictions are not verified
on the prototype.
Experiments have shown the arrangement of pump and sump to be perfectly satisfactory. Structurally there are advantages in further slight modifications to the pump inlet arrangements, but these will make no fundamental change to the design tested.
Experimental evidence illustrates the effectiveness of the rubberized hair screens in reducing the air entrained by water passing over the weir and, since the forward velocity is low in this area, the loss of heaa across these screens is negligible. Floating a heavy wooden raft in the area adjacent to the pump inlet may tend to damp out any head fluctuations above the pump and also serve as an inhibitor to the formation of air
entraiming vortices.
Comparison of the MoW and SHL design diffusers indicate that the
SRL design gives slightly less flow asymmetry, but subsequent experiments on screens in the upstream stilling area indicate that the poor flow at exit from the diffuser can be considerably improved. Since the MoW
design is simpler to construct it is intended to fit this to the prototype and to use screens to rectify any irregularity of flow before it reaches
19
-Experiments on the model, three dimensional, free surface contraction have resulted in the production of a flow of high uniformity in the working
section. However, in order to effect changes on the prototype if required,
a method of construction has been proposed by MoW which is capable of final adjustment.
RE VEREN CE S
ORKNEY, J.C. - The development of a hydraulic flume for ship model testing - B.S.R.A. Report No. 165,
1955.
WILLIAMS, E.E. -
Design of a recirculating water channel-NPL Report, unpublished.
DENNY, P.F. -
An experimental study of air entraining vortices inpump sumps - The Institution of Mechanical Engineers, November
1955.
BAINES, W.D.
andPETERSEN, E.G. -
An investigation of flow throughscreens - The American Society of Mechanical
Engineers,
1951.
DRYDEN, H.L. and SCJ-IUBAER, G-.B. - The use of damping screens for the reduction of wind tunnel turbulence - Journal of
21
-BIBLIOGRAPHY
SAUNDERS, H.E. and HUBBARD, C.W. Circulating water channels
-SNAJ1E 1944. Page 325.
SCIT[JSTER, S. - Der Wasser-Umlaufkanal der Versuchsanstalt fr Wasserbau und Schiffbau.
SAUNDERS, HE. - T.M.B. Report C -
574
B, Page87.
cli BELLA, A. - La Vasia a Circuito Chusso Dell - Universita di Genova.
t
FLUG-EL, G. - Ergebnisse aus dem Strumungeinstitut der Technischen Hochschule Danzig - Jahrbuch der Schiffbautechnischen
Gesellschaft,
Vol.31 1930.
BAXER, G.S. - William Froude National Tank - I.N.A. 1912 Page
58.
OKADE, S. - Investigation on the effect of the angular velocityof steering upon the performance of rudder - Tecim. Res. Lab., Hitachi Shipbuilding and Engineering Co.
Ltd. Aug.
1958.
WRIGHT, EA. -
Some international aspects of ship model researchFLOW STABILITY IN WORKING SECTION
Cascade Weir - free flooded Depth in Working Section - IO in
For definition of Q see fig.IB Speed in Working Section (ft/sec) Weir angle (Q) (degrees) Analysed Motor RPM Maximum amplitude of surface ripples (in) Magnitude of surge (in) Period of surge (sec) Remarks O.13 80 300
0.005
0.005
37
0.4.7
79333
0.005
0 O0.58
79320
0.005
O Change in level in working section during experiment but not a surge 1.19 60 4.350.025
0 01.8
50586
0.025
0 02.02
).-8670
-
Change in water level of0.027 in
but no obvious surge2.38
4.0 7350.035
0 03.09
37 9350.010
O O3.17
35 9320.020
0.04.
353.25
34.990
0.015
0.035
50
TABLE 2
FLOWSTABILITY IN WORKING SECTION
Cascade Weir - free flooded Depth in Working Section -
9-
inFor definition of Q see fig.IB
TABLE 3
FLOW STABILITY IN WORKING- SECTION
Cascade Weir
Depth in Working Section - 9 in Speed in Working i Section (ft/sec) Weir angle (Q' (degrees$ Analysed Motor RPM Maximum amplitude of surface ripples (in)
Magnitude
of surge (in)Period
of surge (sec) Remarks 0.57 88395
-
0.015 32 1.00 70)26
0.01
-
-1.147 60 5150.03
-
-1.96 50 6214- 0.03 - - radual change in water level 2.61+ 10 807 0.03 - - Change in level of about 0.005 in over 180 sec 3.18 35 901 0.005 - - Random level changes of about 0.03 inbut not periodic
O.i18 81
366
-
-
-1.07 70 14146 0.005 - - Movement of
water surface
but not periodic
1.57 60 533 0.015 - - Rapid change in
level but not
periodic
1.98
50 6210.037
-
-2.80 10768
-
-
-
Water level change of about 0.035 in butnot periodic
3.1 35880
-
0.01 A definite oscil-latory movement of about 0.01+ inFLOW STABILITY IN WORKIN( SECTION
Cascade Weir - varying degrees of flood Depth in Working Section - 9
in
Speed
in
Working Section (ft/sec) Head drop over weir (in) Magnitude of disturbance in channel working section (in) Remarks3.21+ 1+ Small Artificial surge close to weir in sump causes change in level in working section but not a periodic
surge
1.18 1 Too large
to measure
Slight disturbances in sump cause very large movement in working
section
1.36
3 Too largeto measure
Same as for 1.18 ft/sec
1.09
1- Too largeto measure
Sanie as for 1.18 ft/sec
0.72
60.15
Not as bad as previously but after ceasing artificial surge in sump about3.5
sec for surfaceof working section to cease movement
0.62
90.07
About 1+ seo to show in workingsection after commencement of artificial surge and about
3.4
sec to stop after stoppingsurge creation in suinp
o,61 11 No movement
0.61+ 11 - Artificial surge created over
pump but no movement going back since it is largely damped by
screens in sunip, and weir is free flooded. Seems to indicate that even violent movements in sump are damped out before going around the circuit to the working section
1.08 1- Too large
to measure
The same as above but with weir
not free flooded. Confirms that any movement travels back up-stream when weir is not free flooded
TABLE 5
FLOW STABILITY IN WORKINC- SECTION
Tilting Weir Free flooded Depth in Working Section - 10 in
For definition of see Fig.IC
TABLE 6
FLOW STABILITY IN WORKING- SECTION
Tilting Weir - Free flooded.
Depth in Working Section - 9 in
Speed in Working Section (ft/see) Weir Angle (4) Analysed RPM Maximum amplitude of surface ripples (in) Magnitude of surge (in) Period of surge (sec) Remarks 0.72 19° - )'
470
0.002 0.005 361.125 12° - 52' 5LO
0.005
0.02 70 Surge appears to be genuine and analysis of record of pump revs, shows nofluctuation
1.72 100 631 0.002
0.007
2.16
8° -
20' 731f-
0.02 22.52.47
6° - 20'780
0.010
0.03
30 Motor speed fluctu-ating corresponding to fluctuations of water speed and toperiod surge
0.417
17° -
26'404
-
-
-
Change in level of 0.010 in but not periodic 0.93 15° - 6' 8o - 0.016 33 1.195 12° - 6' 520 - - - No obvious movement1.385
10° -
12' 600 - 0.015 75 Appears to be more achange in level than
a surge
2.38
80700
-
-
-
Absolutely steady2.95
3° - 36' 900 - - - Change in waterlevel of about 0.013 in
FLOW STABILITY IN WORKING- SECTION
Tilting Weir - Free flooded Depth in Working Section - 9 in
For definition of Q see Fig. IC Speed in Working Section (ft/sec) Weir Angle (Q) RPM Maximum amplitude of surface ripples (in) Magnitude of surge (in) Period of surge (sec) Remarks
0.11.3 200 - 6' 230 0.012 - - Very slight water movement
0.35 16° - 181 310 0.008 - - Slight movement, not periodic
0.95
12° - 36' 450 0.003 - - Movement in level of about 0.025 inbut not periodic
1.4 90 510 - 0.025 42
2.02 70 - 12' 620 - - - Increase in rpm of
about 1% causing a change in level but not periodic
2.56 5° - 22' Not taken
- 0.35 64 Surge improbable, only random move-ment of surface, doubtful whether genuine surge 2.77 40 - 10' 880 .015 - - Movement of water surface, not periodic
TABLE 8
FLOW STABILITY IN WORKING- SECTION
Tilting Weir - Varying Degrees of Flood Depth in Working Section -
9.6
in Velocity in Working Section - 0.5 ft/secWeir Angle Q -
17°6'
Head Drop Over Weir (in) Amplitude of main surge (in) Period of main surge (secs)Time from
commence-ment of exciting force to appearance of movement in Working Section Remarks
2.08
0.030
38 Almost InstantaneousSurge created next to weir of period
1-3
sec2.08
0.017
i6
2.3
sec Surge created insump causing movement next to
weir in sump of
about I in
0.78
-
-
2 sec Induced, movementadjacent to weir
of about 2-i' in.
No apparent long
period surge
2.38
-
-
Instantaneous Exciting force nextto weir. Slow
small movement of
surface
3.88
-
-
Instantaneous Two distinct pericof exciting force applied. No
apparent surge but slight movement
5.08
-
-
Instantaneous No obvious longperiod surge but
still slight
movement of water
surface
9.58
-
-
Instantaneous No long periodsurge. Slight change in water level
TABLE 11
Vertical Velocity Distribution in Working Section
Cascade Weir
TABLE
12
Vertical Velocity Distribution in Working Section
Tilting Weir Model Vèlocity (ft/sec) Prototype Velocity (ft/sec)
0.25
0.79
0.5
1.58
1.0
3.16
1.25
3.95
2.25
7.11
2,5
7.90
35
11.06
Model Velocity (ft/sec) Prototype Velocity (ft/sec)0.5
1,58
1.03.16
1,5
L74
2.0
6.32
25
7.90
3.0
9.48
Nominal Speed (ft/sec) . 0 2 0 3Distance of particle from bottom (in)
9.6
9.2
9.0
8.2
4.2
9.3
7.0
6.8
4.6
4.)49.5
8.1
7.3
6.4.
5.7
3.5
Speed factor726
725
725 7L1724
34.9 34.93°
34. 34.7 441)2
4.39 4.38 4.38 4.32 Nominal Speed. (ft/sec) 1.03,5
Distance of particle from bottom (in)
9.4
9.1
6.8
6.5
5.2
3.7
0.6
9.6
8.4.
7.6
6,2
5.8
5.7
3.8
Speed Factor 454.437
424-4-37440
4.31 396523
521 521516
524
526
528
TABLE 9 TABLE 10Vertical Velocity Distribution in Working Section
Vertical Velocity Distribution in Working Section
Cascade Weir
TkBLE 13
Working Section Surface Level
False Floor Fitted
+
indicates slope upwards downstream
- indicates
slope downwards downstream
Water Depth at
entrance to
Working Section (in)
3.6
5.6
7 O-20
+20
+120 +80-20
O+2O
+20
at0.5
ft/sec +880 +750 +860 +1000860
860
+670 +860 +860 at 1.5 ft/sec +6000-30O
-1500 -860 -1000+000
+1330+0O0
+860at 2.5 ft/sec
-200
Standing
WaveStanding
WaveStanding
WaveStanding
WaveStanding
Wave Standing Wave -550 Standing WavePump Inlet Flow Conditions Figure No. Submergence Diameter Ratio Pump Inlet Speed (ft/sec) Screening in sump Remarks
22 2.67 7.J No screen Cushes of air rising
just before pump.
Surface unstable. No Vortex
23 2.88 6.95 1 screen Air rising just before
pump considerably less
than 1. No vortex
2.13 7.10 1 screen Vortex appeared.
Consider-able air rising (about 60%
of surface)
25 2.10 7.00 No screen Vortex as in 2) but not as strong about 80% bubble
cover of surface
26 1.5 6.7 No screen No vortex. reat quantities
of air rising
27 1.44 7.0 1 screen 2 strong vortices. About
80% bubble cover of surface
28 2.67 7.55 2 screens close together
Tendency for vortex to
form. Air considerably reduced
29 2.67 7.30 2 screens far apart
No vortex. Water surface
excellent
30 2.13 7.3 2 screens
far
apart
No vortex. Water surface
good but few more bubbles than 29
TABLE 15
Screens in Upstream Stilling Section -Experiment Conditions
TABLE 17
Contraction Plow Observations
TABLE 16
Velocity Traverse in Working Section - Experimcnt Conditions
Model Speed (ft/sec) Corresponding prototype speed (ft/sec)
0,5
1.58
15
25
7.90
Model Conditions Corresponding prototype conditions Speed in working section1 .5
ft/sec L4.75 ft/sec Depth in working section9.6
in 8 ft Distance from diffuser at which traverse was made 10.5 in8.75
ft Figure No. Water speed in working section (ft/sec) Distance of hypodermic below water surface (in) Remarks0 5 On bottom Potassium permanganate crystals dropped in to show flow on bottom
15
0.5
18 Flow pattern seems very good0.5
12-do-47
0.5
6-do--48
1 5 6The valves on injection apparatus not working properly so valves opened
wide
49
1.5
12-do-50
1.5
18-do-(
DIFFUSER UPSTREAM SII WN' ION\
WATER LEVEL
WOI
SECTiON
\\
DROP'
ER WEIR SUMPi
REThRM CONDUIIIZDIA.
LWATER LEVEL EL VATI ON
CONTRACTION
PLAN
FIG. IA. GENERAL
LAYOUT
OF
CIRCUIT
FLOW
WORPJN SECTiON WATER LEVEL ¡N WORKING SEC11
WEIR SECTiON
DRA WOOWN
SUM P
Ï
HEAD DROP
ovg wEIr
SUMP WAT LEV EL
FIG. iB.
DETAILS OF CASCADE WEIRFIG. IC.
DETAILS
OF TILTING
WEIRs
QF4/
WIDTH OF CHANNEL LOOKING UPSTREAM
EFFECTIVE DEPTH IN MODEL WORKING SECTION 36 INS
NOMINAL SPEED IN MODEL WORKING SECTION IFT/ SEC. POSITION OF TRAVERSE - ENTRANCE
WITH FALSE FLOOR
o
I-w
LI
uZ O
WIDTH OF CHANNEL LOOKING UPSTREAM
(
) DENOTES FLUCTUATIONS > 1o10VELOCITY TRAVERSES ACROSS WORKING SECTION
FIG 2
EFFECTIVE DEPTH IN MODEL WORKING SECTION 36 INS NOMINAL SPEED IN MODEL WORKING SECTION lET / SEC. POSITION OF TRAVERSE - ENTRANCE
NO FALSE FLOOR
3"-443
441440-440---439
I I 440-440----I I I437 -440
I I j2"-439---437
437 437434-435 -435
437440
I I I I(437)-(424)
I"-(432
433 432434-(436) -435-436
I I f I I i J I 6"4'
2" I" O I" 2" 4" 6" I I(425')-428---(429)
432 I3"--(427)--428
I I 430 431 I 432-I2"-423
432 431- 429430-432-431
430-430
I I I I 423I' -(338)-429
429 427 428430-428
429-I I I I I" i O" I I I" 2" 4" I 6" 6" 4" 2"EFFECTIVE DEPTH IN MODEL WORKING SECTION 36 INS NOMINAL SPEED IN MODEL WORKING SECTION I FT/SEC. POSITION OF TRAVERSE - EXIT
NO FALSE FLOOR
3(45O)---- 481
480 481 484 485 484 479 481 I I I i I i2(4O5)---484
486485 482
485- 486(487) -
489-I I I I I i I(4I0)(432)----
474Ç446
-I I I t I4" 2" I" O" I" 2 4
WIDTH 0F CHANNEL LOOKING UPSTREAM FLUCTUATION VERY BAD I"rROM BOTTOM
FALSE FLOOR O I-o
3"(398)(464)(465)---457---- 454
456 455 453-444---I I I Io z
2"- (380) - (473) (475) (475) 474
474 473 475466
-LLI
o
It
-
- (47) -
(42) (4I) -
(4)-za
6 4 2 h O" I 24'
- I-(na WIDTH 0F CHANNEL LOOKING UPSTREAM
FLUCTUATION VERY BAD I"FROM BOTTOM
( )DENOTES FLUCTUATIONS > I0/
EFFECTIVE DEPTH IN MODEL WORKING SECTION 36 INS. NOMINAL SPEED IN MODEL WORKING SECTION I 5 FT/ SEC. POSITION OF TRAVERSE -ENTRANCE
NO FALSE FLOOR
A TRAVERSE WAS NOT MADE AT THIS CONDITION SINCE FLUCTUATIONS
THROUGHOUT CROSS SECTION OF CHANNEL WERE VERY BAD.
FALSE FLOOR 3 459 668 667 t I Z
2-(695)----7O2
698u-I
I I (615) 699 696 I, L 6 4 2 I-J)WIDTH OF CHANNEL LOOKING UPSTREAM
(
)DENOTES FLUCTUATIONS > I0/
VELOCITY TRAVERSES
IN WORKING
SECTION
FIG 4
665 668 665 (66e) 665 .668-I I I(696)-696-
696 696 690 689 I695 -(676)
-696
695- 697 697 t I_ i I O I 2 4 6O I.- I-O
n
O'r
u-OEFFECTIVE DEPTH IN MODEL WORKING SECTION 36"
NOMINAL SPEED IN MODEL WORKING SECTION 20 FT/SEC. POSITION OF TRAVERSE ENTRANCE
NO FALSE FLOOR 3 8(0 (816) (815) 808 808 807 608 809 805
2' 805
833 - 830-
826 (828) 829 - 829
830 832 I I I I Ii" (824)(82o)--Ç825)--(820) 812 (820)(825) (825)
(825)
I i I I I I 64'
2 I O' I 2b 4" 6'WIDTH OF CHANNEL LOOKING UPSTREAM
FALSE FLOOR 3" 779
780-780 (779) (780) (782) (784)
778 -(778)
2e (802)
811 810 809809
8(1 810608 - 8(0
4' i I I I I I ii (716)
816 8(58(0-807
8(0 811
soo-(soo)
I i i I I 6 4 2 I 0" I' 2 4 6HWIDTH OF CHANNEL LOOKING UPSTREAM ( ) DENOTES FLUCTUATIONS > I 0/
o
VELOCITY TRAVERSE ACROSS WORKING SECTION
FIG 6
EFFECTIVE DEPTH IN MODEL WORKING SECTION
36'
NOMINAL SPEED IN MODEL WORKING SECTION 2-0 FT/SEC
POSITION OF TRAVERSE -- EXIT
NO FALSE FLOOR O 3'
(875)(941) 938
929 927932 (931)
930 929z
I I I I I I 2(865)(947)---(943)----(942)--- (950) (948) (951) (951)--- (ess)
U.L) I I i I I i w(870)(920) - Ç880)(895)----(880)--(88O)--(920) (coo) 945
ULL Iz O
t , j, n 64'
2' I O' I" 2 4 6WIDTH OF CHANNEL L00KNG UPSTREAM
) DENOTES FLUCTUATION>3/4 0/0 FALSE FLOOR 3'
(720)
866 (866) (866)
866(o5)(8os)a74 (848)
2' (813) 905908
908-908 908 910
91Q(897)
I i i I I(836) (900)(899)(89o)--(868)--(87o)(895)Ç903)(830)
6* 4 2' I"0'
I'
2"4'
6' WIDTH OF CHANNEL LOOKING UPSTREAMEFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS
NOMINAL SPEED IN MODEL WORKING SECTION I-O FT/SEC
6"
419-418- 419- 417-419---415
417-419
417o
I I I I i I I I t-t- 5437-435
436-435-434
433-434---431-431
I I I I I * W 4435- 435-436---- 434-434-435---434---430--431
J I I I I438 -439 -438 -436--
Il
433-.,.-
430 -431- 429- 436
WO I I i I I IOu-
I2'
434435-434-432---437 -438-436-437
t- i 43 1/) ¡ i i I i J I" FLUCTUATING>2°/O i I 6" 4*2'
I O'I'
2'
4'
6'WIDTH 0F CHANNEL LOOKING UPSTREAM
VELOCITY TRAVERSE ACROSS WORKING SECTION
POSITION OF TRAVERSE - ENTRANCENO FALSE FLOOR
6'
40B-409---
407- 406- 406- 406- 406
-409 -407
O t t II-o
5'433434-434----433-436
435--433---430
4" I I I I I W 431430 -431-- 430- 428 -428 -428---426 -420
3'
431¡ I I I u.429-428---429---428-427
429- 429 -429
WO
O 426 I I IZ
'-<O
t-2'427-426-426-427---427----425-425-427
t t I I i420-426-424---426-
424- 427-426-427-427
Io 6 I I i I 4"2'
I'
0'
I'
2' 4"WIDTH OF CHANNEL LOOKING UPSTREAM
EFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS
NOMINAL SPEED IN MODEL WORKING SECTION 10 FT/SEC.
POSITION OF TRAVERSE - EXIT
O d
-z0<
IXI
u-I f4l(466)Ç456)(466)--47548I(474)
FLUCTUATING NOT TAKEN
I J 2" I" O" " 2" 4'
400
418 I O 5(380) 436
435 433435-434
436 429 (410) I-O -Jt)
i I I I 4"(s
430 428 430429 429 428
426 (410)
z
I I ¡ I I0<
IXI
3 (480) 431 430 429429-428
427427 (425)
u- U 2" (345) 419(a 6) (425) - (425)(425)
-
(426) (4 28)
I II" FLUCTATING SO NOT TAKEN
I J I' I I
6" 4 2 I O I 2 4 6
w I 1 4 * II
WIDTH OF CHANNEL LOOKING UPSTREAM DENOTES FLUCTUATIONS > I0/
VELOCITY
TRAVERSE ACROSS WORKING SECTION
WIDTH OF CHANNEL LOOKING UPSTREAM
FALSE FLOOR
422 (412)
IFIG B
NO 6* FALSE FLOOR i I 5 (454) 464 I 4 (462) 470 I I 470 3 470 I 2" I (462, (473) 6' 4 421 421 421422-421
I I I f I NOT TAKEN I i 419 463467-468
i I I I4740)
468 469 467 I I 467466)-(457)
469 471 472 471
469 464 469 470EFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS NOMINAL SPEED IN MODEL WORKING SECTION I-5FTI SEC.
POSITION OF TRAVERSE - ENTRANCE
NO FALSE FLOOR 6 NOT TAKEN g 5 661 664 660 660
660 - 660 - 660- 660
660 I I I I I j 4"679- 670- 667
668670- 668- 667-666 -668
I I I I I I < 3677-677- 675- 673-674--- 673
674-674
676 I I 2673 - 674
672673 - 672- 671
670 - 671
675 I Ii'
(654')- 668
663- 663- 668- (668)- 668 -668- 66!
O I i I i u 'q I, I 6 4 2 I O I 2 4 6WIDTH OF CHANNEL LOOKING UPSTREAM
FALSE FLOOR 6'
625-O I-I- 5 649-I z 4 664-t II
3665-625- 624- 627- 626 - 625
653- 652
653 653 651 I I i I668-668-667-666-664
I I666-667----668
664-(666)
wo
I I i I I I Q U-f
647- 658
657 657 657656- 655
654-657
z0
I II"
(574)- (590)-(6I6)-
(6I0)-(599)---(6I0)-(59O)--- (59o)(59o)
O
I I I I I
6' 4" 2" I 0" 1" 2" 6"
WIDTH 0F CHANNEL LOOKING UPSTREAM ) DENOTES FLUCTUATIONS >
VELOCITY TRAVERSE ACROSS WORKING
SECTION627 625
624
-653 654 652 I I 667 I 669 668-I 666 666 665O I-O O a: u-6
VELOCITY TRAVERSE ACROSS WORKING SECTION
FIG IO
EFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS NOMINAL SPEED IN MODEL WORKING SECTION 15 FT/SEC. POSITION OF TRAVERSE - EXIT
NO FALSE FLOOR NOT TAKEN I I 5 (790)
701 - 699 - 697
698 695698 - 701
f687) I I i 4 715735- 734
730-732- 733-734---732-
(72O) I I i I 3(705)-741 - 740
739- 742- 742
747 748 745 I I I I i I 2(710)- 747- (740)- (735)- (737,) _747
7D -75O
(743I FLUCTUATING SO NOT TAKEN
I I
I J
6 4 2 I O 2 4 6
WIDTH OF CHANNEL LOOKING UPSTREAM
FALSE FLOOR 6
(600) - (639) -644
643 -643 -642
642 -(643)
(633) I I I 5(600)-667
671669-(669)
672- 670-(67-(665)
I I i I i I 4(620)-(683)--- 684- 682-682
677681- 679-(668)
I I I 3(565)- 676- 676
676-676
676678-(676)--- (669)
uJO I I I I L) u. 2 (617)(670)- (675)
673)(67O)(665)(666)
(58)
(650) I i I i II FLUCTUATING SO NOT TAKE
I I I I i I i I
6 4 2 I O I 2 4 6
WIDTH 0F CHANNEL LOOKING UPSTREAM
( ) DENOTES FLUCTUATIONS > I 0/
EFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS
NOMINAL SPEED IN MODEL WORKING SECTION 20 FT / SEC.
POSITION OF TRAVERSE - ENTRANCE
NO FALSE FLOOR 6'
877-882--- 878- 879- 878-879
874-879---878
O I-. I I :ç5'
916- 916
915915-911-908
911- 912 -912
I I I i 4"916-914----913-914
9129I2--915----913---914
O I I j I I 918 916914-913
913-911 -911-907-911
u.S _1 ( ¡ I I I I U t 2*919 -919 -920--- 914- 913 -916-918 -917---919
zo
I i j I II'
914 917907-913----916---92I---920-923-923
I I I I I 6"4'
2 I"O'
I'
2 4" 6"WIDTH 0F CHANNEL LOOKING UPSTREAM
FALSE FLOOR
6'-(871)----874
877- 877- 874- 976- (975)_(873) -(871)
I I I I892-891
890-891----891----890----890----%90----888
I I I I I I904-906- 902- 903-905- 907-902- 900-902
I I I I906-910- 906-907- 905903-903902
903 I I I I I I860-902-898 - 897 - 898-896- 899 -894 -(897)
I I' NOT TAKEN o I I Id 6"4'
2"I'
O" 2 4" 6WIDTH OF CHANNEL LOOKING UPSTREAM
( ) DENOTES FLUCTUATIONS >
VELOCITY TRAVERSE ACROSS WORKING SECTION
'-
5'
4'
3 u. I', u.z0
2"FIG. 12
EFFECTIVE DEPTH IN MODEL WORKING SECTION 63 INS
NOMINAL SPEED IN MODEL WORKING SECTION 2 O FT/SEC POSITION OF TRAVERSE -EXIT
NO FALSE FLOOR
NEAR SURFACE NOT TAKEN
5'
(962)_IOOO 998
999998 1001
iOOI 1005 (975)4'
(955)IOI9---- 016
1014 1017 1Q18OI6
1016 1016 I I3'
(c75)I"s---lO26
1020-1022---1025
1027lO2EIO22
I I I I I2" FLUCTUATING SO NOT TAKEN
-I FLUCTUATING SO NOT TAKEN
I I I i
4'
2'
I'
O" 1' 2"4'
WIDTH 0F CHANNEL LOOKING UPSTREAM
FALSE FLOOR ob
____Ç863)_ç863)
8618 s"(740)-917
915 913 915 (914) 914 915990
4"(78o)(923)
931 931930
930
931930(916)
I I I I 3«(960)(933)
936 935(935)(934)---- 935-- (930) (925)
2(92 6) 915
(908) -
(91 2)(903)
I'
SP0TS NOT TAKEN AS THOSE FLUCTUATING TOO BADLY
I I I I I
6" 4" 2 I" O" I" 2"
4'
6WIDTH 0F CHANNEL LOOKING UPSTREAM
(
) DENOTES FLUCTUATIONS > I 0/fJ
z
o
t 00
TLLTNG
WEtR
CASC1\DE V'IJR
i.0002S Fi/SEC
1000j.ri SEC
i.00
t023
tO20
I.0i
IOI6
100
L9LSÇC4T°t9 _rl___
t. 053oss
1.04_7I0S3
1040z
o
ti
w
1206 O76 -125_7--.---.---_--t'054
Q io
to
30
40
50
60
80
DISThNCE FROM BENIÑG OF W0RKIG
SECTION
I E 1 I4
3O55
_7O"POINTS
AT WHICH
MSUREMENTS WERE
TAKEN
LONGITUDINAL
VELOCITY
TRAVERSE
-41/2 FROMBOTTOM
OF CHANNEL
TILTING
'NER
CASCP¼DE WEIR 0.S95 FT SC
1000
1000
15 FT SEC
003
1004 o.
-rT SC
1' 021(022
I 02 I 1020I0 O
1048
tO40
1040
z
o
ti
w U, (9z
o
L
o
'J
z
ItJ 1'192 fZ18 107I360
186 ----..---1 082- .---____.
.063
z
o
w
(I)w
t'-o
o
z
IJ
0 IO'4
jO
20
30
40
50
GO70
80
DISTPNCEFROM BEGINNING
OP WORKING SECTION
I I I i I 'Y. 30" -, O"er
POINTSAT WHICH
MtASUREMENTS WR TAKEN
LONGITUDINAL
VELOCITY
TRAVERSE - 6" FROM
BOTTOM
OF
CHANNEL
O
w
(n (Dz
1000
OSSB
t000
OG FT SE
TILTN
WEIR
z
CASCADE WEIR
O
z
o
w
1.7192
o
Líi tao
O
û
I
O
z
z
Idbi
iO4S-p046
13831060
---¶024
s,.
IO3
1040
O i0u4
IO2u
30
40
50
60
10
DISTANCE
PROM BEGIÑNG OF WORKING
SECTION
I I I I I 81"4.
'30"55"2"
POINTS
AT WHICH
MASUREMEÑTS WERE TAKEN
LONGITUDINAL
VELOCITY
TRAVERSE - 8" FROM
BOTTOM
OFCHANNEL
z
o
s-(j
hi CI)TftNG WIR
CASCA
WEIR
O 97
z
o
s-
u
w (j) (-9z
o
ILo
o
z
LAii-liz
fO43o'
o
20
3O40
SO GOO'9 G
bISTANCZFROM B.GiNNtNG
or WORKING
SECTION
10
8O-.-30"
0"
61"
POINTS
AT WHICH
MEASURZMENTS WR TAKEN
LONGITUDINAL
VELOCITY
TRAVERSE - 9" FROM
BOTTOM
OFCHANNEL
11 -ÖDEPTH = 9-6 INS
36-8--37-7-36-6
36.4 36-5---36-6--- 37-5---38--5-382
I I i I I
7.5
35-7-40-0-39-2 -39-0---- 39-O -38-9---39-3---40-3
39-0
I I I
6-5'-- 4I-9---423-4I-7
41-2---40 B-41-I -41-4--42-2
40-I
I I I I i I t
5-5-40-8-43-O-42.! -41-6----4 I-3---41'3----41 9-42-6
41-I
I i I
4-5-40-243-I- 42-2
41-54I'5- 41-6 -42-5-433 -40-8
I I I I I I3-5----37 9-42-3---41-5---- 4!
I 40-9---41-3 416 42-6 40-O
I J J I I s2-5---37-2
41-5-40-5---40-O- 39-9--40-I-40-5-41 5
38-3 I II-5----33-7-38-4-3B-I----37-5
38-I---37-6-- 375- 39-5 -346
I I I I0-5 -30-5 -30-4-29-9--29-5
30-3 -29-5 -29-7- 307 - 30-0
I_
I.,
IV I., 1JI
IR 6-754
3-6 I 8 0 I-B 3-6 5-4 6-7WIDTH OF WEIR SECTION LOOKING UPSTREAM
FIG. IB
NOMINAL MODEL CHANNEL SPEED = I-O FT ¡SEC.li 9-6INS
36-3-38.9-38-5-38-9---38.7--39.7-35.5.. 38-7- 38-7 -38 -7--38-5
I i I I I I I I
75 - 35-0-39-I-39-O - 391
39-I39-0--39-O---- 39-0- 39-0-39-0 -381
I I I I I
6-5--32-4-38-0-39-0-39-0
38-9--38-9-38-9-- 39-O- 38-9 - 38-7-32-4
I I I
I I
55-335--38-7-39-I---38-9
39.0-38.9--38-9-- 389- 39-I - 39-O-36-0
I I I I I I I
45 -35.9- 38-9-38.9- 38-9
389-38-9-38-9-- 38-9- 38-8
38-9--36-I
I J I I I I I I3-5'---38-5---38-9-389---38- 38-S--38-8--38-8 - 388 -38-9 - 38-8--35-0
I I I I I I2-5'--- 33-2 -38.1-39.0 - 39-O - 38-9-'-- 38-7 -38-7--387---39-O
- 387 -33-2
I I I I I iI 5
33.3 -38-I -39-I -39-0-38-8 -.38-7-38-9 -38-7 -39-I - 38-7--33-3
I I I I I I
6-7" 6
O'
2-5'---- 0"
2 5'- 30'- 4-5"---- 6,Ou_6.7
WIDTH OF WORKING SECTION LOOKING UPSTREAM
VELOCITY TRAVERSE AT DOWNSTREAM END OF
z
o
o -JJ
>
w
-JO
w
I-Oz
0o
o
60
65
70 7580
8SDISTANCE FROM START
OF WORKING SECTION (INs)
TILTING
WEIR - DRAWDOWN
WEIR SECTION
OES FT SEC FT SEC 1879F1 SEC e 63 FT SECflLTIN
WEIR
CASCADE WEIRFIG. 20.
/
/
/
/
/
/
/
I
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
,
/
0
05
10
16
20
25
30
SPEED N WORKING SECTION (rr/sEc)
SLOPE OF WATER
LEVEL
OVER
LENGTH
OFWORKING
SECTION
ATVARIOUS
SPEEDSooOz
o.00i
o
l'-o'
L1JoZ
.iW
tPJ
(D FLOW