• Nie Znaleziono Wyników

Reuse of building components: an economic analysis

N/A
N/A
Protected

Academic year: 2021

Share "Reuse of building components: an economic analysis"

Copied!
5
0
0

Pełen tekst

(1)

151

Reuse of building components: an economic analysis

Frédéric Bougrain

1

and Sylvain Laurenceau

2

1

Department of Economic Studies, CSTB, Université Paris-Est, Champs-sur-Marne, France

2

Environment and Energy Direction, CSTB, Université Paris-Est, Champs-sur-Marne, France

Abstract

In France the building industry accounts for the largest share of greenhouse gas emissions. It

represents about one quarter of France’s national emissions. To deal with this challenge, the

French energy transition for Green Growth law was adopted in July 2015. Buildings

renovation, clean transport, renewable energy and the circular economy are at the agenda.

The law sets several ambitious objectives for construction and demolition wastes (C&DW).

The goal is to recycle 70% of construction and engineering waste by 2020 while around 60%

of construction and demolition wastes (C&DW) are currently reused, recycled or recovered.

Reuse of components is currently undisclosed but represents an opportunity to fully take

advantage of wastes potential. Moreover, it brings environmental and economic benefits for

future constructions and local territories.

This paper focuses on the economic benefits of reuse. The aim is to examine whether a

demolition project promoting the reuse of demolition wastes offers value for money in

comparison with a demolition project that does business as usual.

After a literature survey, an in depth evaluation of costs and labour impacts is proposed for a

case concerning bricks for a small arena. Results show that reuse can bring direct economic

benefits if the demolition process is based on the same tools as a traditional demolition.

Moreover it would have a positive impact both in terms of direct costs and local employment

if the process is optimised. Deconstruction is still in its infancy and the value-added chain is

not well developed. Thus, the learning curve is important.

This paper is produced within the REPAR 2 project, cofounded by the Agency for the

Environment and Energy Management.

Keywords:

reuse, economic analysis, deconstruction, local economic impact.

Introduction

To mitigate climate change, most European countries have decided to reduce greenhouse gas

emissions by a factor of 4 before 2050. In France the building industry accounts for the

largest share of greenhouse gas emissions. It represents about one quarter of France’s national

emissions. To deal with this challenge, the French energy transition for Green Growth law

was adopted in July 2015. Buildings renovation, clean transport, renewable energy and the

circular economy are at the agenda. The law aims at tackling waste and promoting the

circular economy. It set several ambitious objectives for construction and demolition wastes

(C&DW). The goal is to recycle 70% of construction and engineering waste by 2020 while

around 60% of construction and demolition wastes (C&DW) are currently reused, recycled or

recovered.

Among the “3Rs” (reuse, recycle and reduction), reuse of components represents an

opportunity to fully take advantage of wastes potential.

This paper focuses on the economic benefits of reuse. After a literature survey, an in depth

evaluation of costs and labour impacts is proposed for a case concerning bricks for a small

arena. The aim of the comparative analysis is to test whether a demolition project promoting

(2)

152

the reuse of demolition wastes offers value for money in comparison with a demolition

project that does business as usual.

The economic advantage of deconstruction: a literature review

Disassembly, demolition and deconstruction concern the end-of-life phase of a building and

are frequently source of confusion while they refer to distinct actions:

Disassembly means “taking apart components without damaging, but not necessarily

to reuse them”;

Demolition is “a term for both the name of the industry and a process of intentional

destruction”;

Deconstruction is “similar to disassembly but with thoughts towards reusing the

components” (McGrath and al., 2000).

The literature provides several reasons to explain why demolition is still dominant and

prevails over deconstruction:

Most buildings are not designed and built to be deconstructed;

Clients may be reluctant to reuse materials when there are no certification schemes

proving that the employment of second-hand materials and components does not

jeopardise the quality of the new building;

The lack of detailed information about the materials and components employed in a

building may affect the economic feasibility of a deconstruction project. This issue

reinforces the need for a careful pre-deconstruction survey;

Demolition is a niche and most contractors prefer to make comfortable margin and to

do business as usual;

Deconstruction is still in its infancy and the value-added chain is not well developed.

There is a lack of guidelines for architects (to create a building that is easier to

deconstruct) and contractors (to improve the efficiency of the disassembly process).

This lack of experience limits the benefits associated with this approach.

Despite these barriers, deconstruction can be a valuable solution since it offers social,

economic and environmental benefits:

Social benefits: demolition is mainly based on mechanical equipment used to bring

down buildings while deconstruction is more labour intensive. As such, it offers

employment opportunities. Deconstruction and the resale of recovered materials is a

source of business. It can provide employment to local communities in search of

economic revitalisation (Penn and al., 2003).

Economic benefits: several examples indicate that sales of materials and components

strongly reduce deconstruction costs. The deconstruction of six downtown buildings

in Wisconsin saved approximately $37,000 (Newenhouse and Fuller, 2003). This is

mainly due to the avoided landfill costs. Since the amount of materials disposed in

landfills is reduced, it has positive environmental impacts. Similar results were found

by Storey and Pedersen (2003) in New-Zealand. Around large cities such as

Auckland and Christchurch, tenders were offered at a price lower than the cost of

demolition. It was offset by the selling of the salvaged materials and the avoidance of

landfill costs. However, costs can also exceed benefits.

According to Eklund and al. (2003) who analysed two projects, “using a large degree

of reused concrete elements cost roughly 10% to 15% more than building with

conventional building practice”. Moreover, it creates financial uncertainty around the

(3)

153

project. They also mentioned the lack of experience of most stakeholders. For

example, the contractors who were surveyed indicated that with more experience and

by developing technology and building techniques for use with reused materials, the

same job could be done with a 10% to 15% cost reduction.

Environmental benefits: Deconstruction improves the effective sorting of C&DW. It

improves the identification of materials and potential contaminants, the separation of

materials that are valuable such as glass, metals, concrete, etc. Thus, it positively

impacts reuse and recycling rates.

However, the economic benefits of reuse and recycling appear strongly dependant on local

conditions:

1.

There is a need to find projects with recovered materials, demands for this type of

resources and established businesses that can do the deconstruction;

2.

Size of sites matters. Manoeuvrability is more limited for small sites. Thus,

productivity is affected. It is also more difficult to store materials on small sites.

Urban sites have probably more resources but they are more constrained by their size

than sites away from densely populated area.

3.

Distance between the construction site and the C&DW treatment installation strongly

impacts the profitability According to Lassandro (2003), transport costs can affect the

demolition costs by 40%.

All these issues are presented in the following case.

Case study: Reuse of bricks

1. The steps from deconstruction to reuse

The case involves an arena made of bricks. The building site was 5 km away from the

deconstruction site consisting of an old factory located in La Courneuve, a city in the suburbs

of Paris. About 5,000 m² were deconstructed but only a small percentage of bricks were

reused. The study examines the different stages of the deconstruction project and details the

data used for the analysis:

Pre-deconstruction survey: it was done by Bellastock a local association specialised

in deconstruction. Two types of bricks with different qualities were identified.

Mechanical equipment used for demolition was not considered as adapted to preserve

these secondary materials. The diagnosis proposed to screen the bricks before sorting

them on the deconstruction site.

Sorting: the bricks were collected and taken for sorting, before being transported to

the building site. A sifter was used for one day to treat 450 m

3

of bricks. Only 16,400

(33%) were recovered. With a manual approach a higher quantity of secondary

materials would have been preserved.

Evacuation: Costs of transport of C&DW to remote backfilling sites and recycling

platforms were avoided. Trucks had only to drive for 5 km instead of 40. Three

round-trip rides were necessary.

Storage: it was done on a site owned by the client.

Transformation of materials: This activity consists in manual sorting, restoration of

the bricks and quality control. It is carried out on the construction site. This step was

performed as part of a school project by 12 low-skilled workers in integration. They

were supervised by one person employed by Bellastock. For this phase of manual

(4)

154

sorting which lasted 17 days, some mechanical equipment was rented for 5 days to

facilitate the handling of the bricks.

Purchases of new materials: the cost for a new brick is €0.68 and the brickyard is

located 60 kilometers away from the construction site.

2. The financial analysis

Six main cost categories were considered for the analysis:

1.

Transportation costs were calculated according to driving hours, distances between

deconstruction site and worksite / recycling platform;

2.

Labour costs consist of deconstruction activities, supervision work and training of the

low-skilled workers;

3.

Pre-diagnosis costs refer to surveys done before the deconstruction in order to

appreciate the potential of the old buildings;

4.

Mechanical equipment costs consist of renting machines for sorting bricks;

5.

Material costs relate to the purchase of new bricks;

6.

Disposal costs.

Cost of reused bricks: €1.41/brick – cost of new brick: €0.90/brick

Figure 1. Secondary materials versus new materials

3. Social analysis

Deconstruction is more labour intensive and it entails greater labour costs. However, it also

has a greater social value since it contributes to the training and employment of low-skilled

workers (table 1).

Table 1. Working days: deconstruction and reuse versus demolition and purchase (for 10 000 bricks)

Deconstruction and reuse of bricks Demolition and purchase of new bricks

Working days Working days

Pre-deconstruction survey

0.1 Transportation of old bricks (to recycling

platforms)

0.1

Mechanical sorting 0.2 Disposal costs 0.6

Supervising, training, restoration and quality

control 210,4 Manufacturing process 5 Transportation of new bricks 2.3 Total 211 Total 8 8% 15,50% 47% 29,50% Mechanical sorting Mechanical equipment 75% 18% 6% 1%

Purchase

of new

materials

(5)

155

4. Sensitivity analysis

Deconstruction is still in its infancy and the value-added chain is not well developed. The

learning curve is important. Thus, it is appropriate to look how productivity improvement in

manual sorting and restoration would impact the economic results. Several hypotheses, set

with different contractors and based on feedbacks, were retained:

Manual sorting and restoration time is reduced by 30%;

Mechanical equipment are better used and renting time is reduced by 30%;

Supervising time is divided by two (the case is a school project and more time is

dedicated to supervision than in traditional projects).

Table 2. Socio-economic analysis integrating productivity improvement due to experience Deconstruction and reuse of

bricks

Demolition and purchase of new bricks

Cost for one brick € 0.79 € 0.90

Working days (10,000 bricks)

132 8

Conclusion

Results show that reusing bricks can bring direct economic benefits. Moreover it would have

a positive impact both in terms of direct costs and local employment if the process is

optimised. Indeed, there is a learning curve since this approach is still in its infancy and the

value added chained is not organised yet. The impact could be very significant on local

employment, especially if processes are based on reintegrated employees.

Two other case studies based on concrete reuse have shown similar results but with a lower

impact on local employment. Those first results suggest that reuse can contribute to the

economic revitalisation of a territory.

References

Eklund M., Dahlgren, Dagersten A and G. Sundbaum, 2003, “The conditions and constraints

for using reused materials in building projects”, in A. R. Chini (Ed.), Deconstruction and

materials reuse, paper 21, CIB Publication 287, Proceedings of the 11

th

Rinker international

Conference, May 7 – 10, 2003, Gainesville, Florida, USA.

Lassandro P., 2003, “Deconstruction case study in Southern Italy: economic and

environmental assessment”, in A. R. Chini (Ed.), op. cit., paper 10.

Mc Grath C., Fletcher S. L. and H. M. Bowes, 2000, “UK deconstruction report”, in C.J.

Kibert and A. R. Chini (Ed.), Overview of deconstruction in selected countries, 158-180, CIB

Publication 252, TG39 Deconstruction.

Newenhouse S., Kunde J. and A. Fuller, 2003, “Overture project deconstruction in Madison,

W1 achieves 74% recycling rate” in A. R. Chini (Ed.) op. cit., paper 8.

Penn G. C., Knudsen S. and I. Bensch, 2003, “Evaluating a deconstruction business model”,

in A. R. Chini (Ed.) op. cit., paper 17.

Storey J. B., and M. Pedersen, 2003, “Overcoming the barriers to deconstruction and

materials reuse in New-Zealand”, in A. R. Chini (Ed.) op. cit., paper 23.

Cytaty

Powiązane dokumenty

[r]

Nie używam Internetu do oszukiwania, nie wprowadzam innych w błąd, dbam, żeby.. w Internecie było jak najwięcej

[r]

x SRSU]H] ]DVWRVRZDQLH RGG]LDá\ZDQLD QD SU]HSá\Z QLH]DOHĪQLH RG VWDQX WHJR. SU]HSá\ZX L ZWHG\ PDP\ GR F]\QLHQLD ] W]Z

1 I was really sick / proud when I got the best mark in class for the project on old Chinese coins and banknotes.. 2 Susie is rather sleepy / nervous because she isn’t sure if

[r]

I II. 1) analizuje i rozwiązuje zadania tekstowe proste i wybrane złożone; dostrzega problem matematyczny oraz tworzy własną strategię jego rozwiązania, odpowiednią do

Zapiszcie temat lekcji: Sprawdzian wiadomości z działu Składniki powietrza i rodzaje przemian, jakim ulegają. Piszecie nr w